223 S AVENUE 55 90042
Certificate Information: 223 S AVENUE 55 90042
- Application / Permit
- 20014-10000-00407
- Plan Check / Job No.
- B20LA01812
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE INTO AN ACCESSORY DWELLING UNIT W/ ADDITION ( 2'-7" X 25'-10") TO THE SIDE AND NEW COVERED PATIO (3'-8" X 12'-7"). DEMO PORTION OF (E) GARAGE (6'-2" X 14').
- Permit Issued
- Issued on 6/3/2020
- Issuing Office
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | FARSHAD ALIMOHAMADI |
| Green Plans Picked Up | 2/14/2020 | APPLICANT |
| Corrections Issued | 2/19/2020 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 3/13/2020 | FARSHAD ALIMOHAMADI |
| Issued | 6/3/2020 | APPLICANT |
| Building Plans Picked Up | 6/4/2020 | APPLICANT |
| CofO in Progress | 3/21/2023 | AMY COLIN |
| No Progress | 3/21/2023 | RUBEN SALAS |
| CofO in Progress | 3/13/2024 | LILIANA PORTILLO |
| CofO Issued | 3/19/2024 | DEROLD HAUFF |
| Permit Finaled | 3/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 3/4/2020 | KATIE DEBIASE |
| Miscellaneous | Cleared | 3/4/2020 | KATIE DEBIASE |
| Miscellaneous | Cleared | 3/4/2020 | KATIE DEBIASE |
| Miscellaneous | Cleared | 3/4/2020 | KATIE DEBIASE |
| Address approval | Cleared | 3/5/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 3/5/2020 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 3/5/2020 | JEANIE LAM |
| Sewer availability | Cleared | 3/5/2020 | JEANIE LAM |
| Green Code | Cleared | 3/12/2020 | FARSHAD ALIMOHAMADI |
Contact Information
| Contractor | D C L A Design Build Inc; Lic. No.: 1060451-B | 45 S ARROYO PKWY STE 214 PASADENA, CA 91105 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/27/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/27/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 8/27/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2020 | Partial Approval | COREY HUPP |
| Underground Mechanical | 9/21/2020 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 9/28/2020 | Approved | COREY HUPP |
| PLUMBING-Rough | 9/28/2020 | Approved | COREY HUPP |
| Underground Mechanical | 9/28/2020 | Approved | COREY HUPP |
| HVAC-Final | 10/9/2020 | Not Ready for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 10/9/2020 | Partial Approval | COREY HUPP |
| Insulation | 10/20/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 11/13/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 11/13/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/13/2020 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 11/13/2020 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 11/13/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 12/9/2020 | Approved | COREY HUPP |
| Final | 3/10/2022 | Partial Inspection | COREY HUPP |
| Footing/Foundation/Slab | 3/10/2022 | Approved | COREY HUPP |
| Green Building Final | 3/10/2022 | Not Ready for Inspection | COREY HUPP |
| MERV13>=Final | 3/10/2022 | Approved | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Not Ready | COREY HUPP |
| Smoke Detectors | 3/10/2022 | Approved | COREY HUPP |
| Final | 3/31/2022 | Corrections Issued | AMY COLIN |
| Green Building Final | 3/31/2022 | Partial Inspection | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 3/31/2022 | SGSOV Approved | AMY COLIN |
| ELECTRICAL-Final | 5/17/2022 | Approved | AMY COLIN |
| Final | 5/17/2022 | Corrections Issued | AMY COLIN |
| Green Building Final | 5/17/2022 | Not Ready for Inspection | AMY COLIN |
| HVAC-Final | 5/17/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 5/17/2022 | Approved | AMY COLIN |
| Gas Test | 5/23/2022 | Approved | AMY COLIN |
| Final | 8/9/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Final | 8/9/2022 | Corrections Issued | AMY COLIN |
| Final | 3/21/2023 | OK to Issue CofO | AMY COLIN |
| Green Building Final | 3/21/2023 | Approved | AMY COLIN |
| Final | 3/12/2024 | OK to Issue CofO | LILIANA PORTILLO |