850 E 97TH ST 90002

Certificate Information: 850 E 97TH ST 90002

Application / Permit
20014-10000-00397
Plan Check / Job No.
B20LA01754
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FIRE DAMAGE REPAIR AND BEDROOM ADDITION TO REAR OF (E) SFD, REMOVE AND REPLACE PORTION OF ROOF RAFTERS, INTERIOR REMODEL
Permit Issued
Issued on 2/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 KEVIN MORALES
Corrections Issued 1/30/2020 KEVIN MORALES
Issued 2/10/2020 LADBS
CofO in Progress 6/8/2021 JOHN KLARIN
Permit Finaled 7/8/2021 DEROLD HAUFF
CofO Issued 7/8/2021 DEROLD HAUFF
Permit Finaled 7/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/30/2020 JEANETTE VONG
Roof/Waste drainage to street Cleared 1/30/2020 JEANETTE VONG

Contact Information

Contractor Lua'S Construction Inc; Lic. No.: 760513-B 3010 8TH AVE      LOS ANGELES, CA 90018
Engineer Estrada,, Jorge; Lic. No.: C87410 1344 CLAREMONT PLACE      POMONA, CA 91767

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/3/2020 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 10/2/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 10/2/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 10/2/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/6/2020 Partial Approval EUGENE CASSIDY
Green Building Rough 11/6/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 4/6/2021 Approved EUGENE CASSIDY
Drywall Nailing 4/6/2021 Approved EUGENE CASSIDY
Final 4/6/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 4/6/2021 Approved EUGENE CASSIDY
Green Building Final 4/6/2021 Approved EUGENE CASSIDY
Green Building Rough 4/6/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/6/2021 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 4/6/2021 Approved EUGENE CASSIDY
Smoke Detectors 4/6/2021 Not Ready for Inspection EUGENE CASSIDY
Final 5/21/2021 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/21/2021 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 5/21/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 6/7/2021 Approved JOHN KLARIN
Final 6/7/2021 OK to Issue CofO JOHN KLARIN
HVAC-Final 6/7/2021 Approved JOHN KLARIN
PLUMBING-Final 6/7/2021 Approved JOHN KLARIN