850 E 97TH ST 90002
Certificate Information: 850 E 97TH ST 90002
- Application / Permit
- 20014-10000-00397
- Plan Check / Job No.
- B20LA01754
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FIRE DAMAGE REPAIR AND BEDROOM ADDITION TO REAR OF (E) SFD, REMOVE AND REPLACE PORTION OF ROOF RAFTERS, INTERIOR REMODEL
- Permit Issued
- Issued on 2/10/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | KEVIN MORALES |
| Corrections Issued | 1/30/2020 | KEVIN MORALES |
| Issued | 2/10/2020 | LADBS |
| CofO in Progress | 6/8/2021 | JOHN KLARIN |
| Permit Finaled | 7/8/2021 | DEROLD HAUFF |
| CofO Issued | 7/8/2021 | DEROLD HAUFF |
| Permit Finaled | 7/8/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2020 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 1/30/2020 | JEANETTE VONG |
Contact Information
| Contractor | Lua'S Construction Inc; Lic. No.: 760513-B | 3010 8TH AVE LOS ANGELES, CA 90018 |
| Engineer | Estrada,, Jorge; Lic. No.: C87410 | 1344 CLAREMONT PLACE POMONA, CA 91767 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/3/2020 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/2/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 10/2/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 10/2/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2020 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 11/6/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/6/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 4/6/2021 | Approved | EUGENE CASSIDY |
| Final | 4/6/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/6/2021 | Approved | EUGENE CASSIDY |
| Green Building Final | 4/6/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 4/6/2021 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/6/2021 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 4/6/2021 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 4/6/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/21/2021 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/21/2021 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 5/21/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/7/2021 | Approved | JOHN KLARIN |
| Final | 6/7/2021 | OK to Issue CofO | JOHN KLARIN |
| HVAC-Final | 6/7/2021 | Approved | JOHN KLARIN |
| PLUMBING-Final | 6/7/2021 | Approved | JOHN KLARIN |