6409 N CAMELLIA AVE 91606
Certificate Information: 6409 N CAMELLIA AVE 91606
- Application / Permit
- 20014-10000-00352
- Plan Check / Job No.
- B20LA01538
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ADDITION TO (E) STORAGE AND CONVERTING TO BE (N) ADU per STATE LAW GCS 65852.2(e)(1)(A) WITH ATTACHED STORAGE. ALL CONSTRUCTION PER WFPP. "COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE: 12/25/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 6/5/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | DEAN LEE |
| Corrections Issued | 3/4/2020 | MIGUEL JIMENEZ |
| Quality Review Completed | 3/18/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 3/25/2020 | APPLICANT |
| Green Plans Picked Up | 7/1/2020 | APPLICANT |
| Plan Check Approved | 12/6/2022 | KELVIN CHUONG |
| Issued | 6/5/2023 | APPLICANT |
| CofO in Progress | 10/17/2024 | THOMAS WOODS |
| Permit Finaled | 1/27/2026 | DAVID JAMES |
| CofO Issued | 1/27/2026 | DAVID JAMES |
| Permit Finaled | 1/27/2026 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 7/1/2020 | MIGUEL JIMENEZ |
| Sewer availability | Cleared | 3/21/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2022 | PAMELA TENEZA |
| Low Impact Development | Cleared | 7/11/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/9/2022 | JOHN LIN |
| Construction near power lines | Cleared | 12/6/2022 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/18/2024 | Partial Approval | THOMAS WOODS |
| Excavation/Setback/Form/Re-Bar | 1/29/2024 | Approved | THOMAS WOODS |
| Underground Mechanical | 1/29/2024 | Approved | THOMAS WOODS |
| Excavation/Setback/Form/Re-Bar | 2/13/2024 | Approved | THOMAS WOODS |
| Footing/Foundation/Slab | 2/13/2024 | Approved | THOMAS WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Approved | THOMAS WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 3/21/2024 | Not Ready for Inspection | THOMAS WOODS |
| HVAC-Rough | 4/1/2024 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 4/1/2024 | Partial Approval | THOMAS WOODS |
| PLUMBING-Rough | 4/1/2024 | Approved | THOMAS WOODS |
| ELECTRICAL-Rough | 4/29/2024 | Approved | THOMAS WOODS |
| HVAC-Rough | 4/29/2024 | Approved | THOMAS WOODS |
| Insulation | 5/2/2024 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 5/2/2024 | Approved | THOMAS WOODS |
| Drywall Nailing | 5/10/2024 | Approved | DAVID HICKMAN |
| BUILDING-Rough-Frame | 9/26/2024 | Approved | THOMAS WOODS |
| Final | 9/26/2024 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 9/26/2024 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Rough | 9/26/2024 | Approved | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 9/26/2024 | SGSOV Not Ready | THOMAS WOODS |
| Smoke Detectors | 9/26/2024 | Not Ready for Inspection | THOMAS WOODS |
| Final | 10/15/2024 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 10/15/2024 | Approved | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Not Ready | THOMAS WOODS |
| Smoke Detectors | 10/15/2024 | Approved | THOMAS WOODS |
| ELECTRICAL-Final | 10/17/2024 | Approved | THOMAS WOODS |
| Final | 10/17/2024 | OK to Issue CofO | THOMAS WOODS |
| HVAC-Final | 10/17/2024 | Approved | THOMAS WOODS |
| PLUMBING-Final | 10/17/2024 | Approved | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Approved | THOMAS WOODS |
| Service/Power Release | 10/17/2024 | Approved | THOMAS WOODS |