1958 N JONES AVE 90032

Certificate Information: 1958 N JONES AVE 90032

Application / Permit
20014-10000-00339
Plan Check / Job No.
B20LA01467
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (240 SQ FT) 1-STORY ADDITION TO EXISTING SFD 1 OF 2
Permit Issued
Issued on 10/9/2020
Issuing Office
Current Status
CofO Issued on 3/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2020 APPLICANT
Assigned to Plan Check Engineer 1/28/2020 MONICA RAMIREZ
Corrections Issued 1/28/2020 MONICA RAMIREZ
Plan Check Approved 1/31/2020 KEVIN MORALES
Issued 10/9/2020 APPLICANT
CofO in Progress 3/8/2023 AMY COLIN
Permit Finaled 3/9/2023 DEROLD HAUFF
CofO Issued 3/9/2023 DEROLD HAUFF
Permit Finaled 3/9/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/28/2020 CELINA MORENO
Grading Pre-Inspection Cleared 1/28/2020 ALEXANDER HELFER
Roof/Waste drainage to street Cleared 1/28/2020 CELINA MORENO
Sewer availability Cleared 1/28/2020 CELINA MORENO

Contact Information

Contractor Iconx Inc; Lic. No.: 980801-B 4248 PANAMINT STREET      LOS ANGELES, CA 90065
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/30/2020 Partial Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 1/7/2021 Not Ready for Inspection COREY HUPP
Excavation/Setback/Form/Re-Bar 1/8/2021 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 3/15/2021 Not Ready for Inspection COREY HUPP
Underground Mechanical 3/15/2021 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 3/31/2021 Approved OSVALDO PARAMO
Underground Mechanical 3/31/2021 Approved OSVALDO PARAMO
ELECTRICAL-Rough 5/18/2021 Approved COREY HUPP
Wood Frame 5/18/2021 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 1/5/2022 Approved ADAM ESCOTO
HVAC-Rough 1/5/2022 Approved ADAM ESCOTO
Insulation 1/5/2022 Approved ADAM ESCOTO
Interior/Exterior Lathing 1/5/2022 Partial Approval ADAM ESCOTO
Drywall Nailing 1/10/2022 Approved OSVALDO PARAMO
Shower Pan 1/13/2022 Approved COREY HUPP
Interior/Exterior Lathing 1/14/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 4/20/2022 Partial Approval ADAM ESCOTO
Insulation 4/22/2022 Corrections Issued RUBEN SALAS
Final 12/29/2022 OK to Issue CofO AMY COLIN
Footing/Foundation/Slab 12/29/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Approved AMY COLIN
Smoke Detectors 12/29/2022 Approved AMY COLIN