2831 1/2 N HURON ST 90065

Certificate Information: 2831 1/2 N HURON ST 90065

Application / Permit
20014-10000-00324
Plan Check / Job No.
B20LA01397
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY ADU PER ORDINANCE 186481
Permit Issued
Issued on 1/12/2021
Issuing Office
Current Status
CofO Issued on 5/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 STARR CHEN
Corrections Issued 3/19/2020 STARR CHEN
Quality Review Completed 3/23/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 7/13/2020 APPLICANT
Plan Check Approved 8/11/2020 STARR CHEN
Issued 1/12/2021 APPLICANT
Building Plans Picked Up 1/21/2022 APPLICANT
CofO in Progress 5/2/2023 OSVALDO PARAMO
CofO in Progress 5/2/2023 OSVALDO PARAMO
Permit Finaled 5/5/2023 DEROLD HAUFF
CofO Issued 5/5/2023 DEROLD HAUFF
Permit Finaled 5/5/2023 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 6/8/2020 JASON CHAN
Address approval Cleared 6/9/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/10/2020 CECILIO NAVARRO
Sewer availability Cleared 6/10/2020 CECILIO NAVARRO
ZI Cleared 6/17/2020 ADRINEH MELKONIAN
Low Impact Development Cleared 6/19/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/23/2020 CECILIO NAVARRO
Green Code Cleared 6/26/2020 KHEDER ALRAZAA
Hydrant and Access approval Cleared 6/26/2020 MATTHEW CRAIG
Grading Pre-Inspection Cleared 8/11/2020 STARR CHEN

Contact Information

Contractor Apel Construction Inc; Lic. No.: 1051980-B 644 NORTH FULLER AVE 454      LOS ANGELES, CA 90036
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/1/2021 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 11/10/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 11/13/2021 Approved RICHARD ROBLES
Excavation/Setback/Form/Re-Bar 11/16/2021 Corrections Issued OSVALDO PARAMO
Special/Order Compliance 11/16/2021 Partial Inspection LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 11/18/2021 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 12/16/2021 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 2/4/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Approved OSVALDO PARAMO
Green Building Rough 3/22/2022 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 3/22/2022 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 4/1/2022 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 5/9/2022 Corrections Issued OSVALDO PARAMO
HVAC-Rough 5/9/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 5/9/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 5/17/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 5/17/2022 Approved OSVALDO PARAMO
Green Building Rough 5/27/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 5/31/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Interior/Exterior Lathing 6/3/2022 Partial Approval OSVALDO PARAMO
Shower Pan 6/3/2022 Approved OSVALDO PARAMO
Insulation 6/10/2022 Not Ready for Inspection OSVALDO PARAMO
Insulation 6/15/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 6/16/2022 No Access for Inspection OSVALDO PARAMO
Drywall Nailing 6/24/2022 Not Ready for Inspection OSVALDO PARAMO
Drywall Nailing 6/28/2022 Approved AMY COLIN
Final 8/1/2022 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 8/1/2022 Approved OSVALDO PARAMO
Green Building Final 8/1/2022 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 8/1/2022 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 8/1/2022 Approved OSVALDO PARAMO
Final 8/22/2022 Corrections Issued OSVALDO PARAMO
Green Building Final 8/22/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 8/22/2022 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 8/22/2022 Approved OSVALDO PARAMO
Final 9/1/2022 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 9/1/2022 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/9/2022 SGSOV Not Ready OSVALDO PARAMO
Final 9/26/2022 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 9/26/2022 Not Ready for Inspection OSVALDO PARAMO
Final 11/28/2022 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 11/28/2022 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 12/12/2022 SGSOV Not Ready OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 12/16/2022 SGSOV Not Ready OSVALDO PARAMO
Final 3/20/2023 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 3/20/2023 Approved OSVALDO PARAMO
Final 3/24/2023 Partial Inspection RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 3/24/2023 SGSOV Approved RUBEN SALAS
Final 4/3/2023 Corrections Issued OSVALDO PARAMO
Final 4/10/2023 OK to Issue CofO OSVALDO PARAMO