11461 W THURSTON CIR 90049

Certificate Information: 11461 W THURSTON CIR 90049

Application / Permit
20014-10000-00319
Plan Check / Job No.
B20LA01369
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE AND STORAGE TO A TWO STORY ADU PER DETACHED ADU ORDINANCE
Permit Issued
Issued on 2/16/2023
Issuing Office
West Los Angeles
Current Status
Issued on 2/16/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 CARLOS MONTES
Corrections Issued 3/6/2020 AMIR DANAI
Quality Review Completed 3/19/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 5/14/2020 APPLICANT
Applicant returned to address corrections 4/27/2021 CARLOS MONTES
Green Plans Picked Up 12/22/2021 APPLICANT
Plan Check Approved 2/8/2023 CARLOS MONTES
Issued 2/16/2023 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/23/2020 HISASHI KOBAYAKAWA
Green Code Cleared 8/19/2020 DONALD CRICHLOW
BHO/Hillside ordinance Cleared 9/23/2020 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 9/23/2020 HISASHI KOBAYAKAWA
Street Frontage Cleared 9/23/2020 HISASHI KOBAYAKAWA
Address approval Cleared 9/24/2020 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 10/2/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 10/2/2020 HISASHI KOBAYAKAWA
Distance to fire station Cleared 10/23/2020 MATTHEW CRAIG
Grading Pre-Inspection Cleared 4/20/2021 BRIAN MILLER
Hydrant and Access approval Cleared 7/15/2022 KURT CORRAL
Low Impact Development Cleared 12/16/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 1/4/2023 JENSON LEE
GPI Written Notices Cleared 2/8/2023 AMIR DANAI

Contact Information

Contractor Owner-Builder       ,
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/12/2023 Approved CARLOS MATAMOROS
Pre-Inspection 10/24/2023 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 10/27/2023 Approved CARLOS MATAMOROS
Pre-Inspection 11/7/2023 Approved CARLOS MATAMOROS
Pre-Inspection 3/4/2024 Corrections Issued CARLOS MATAMOROS
Pre-Inspection 10/3/2024 Approved CARLOS MATAMOROS
Piling/Pier/Caisson 11/13/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 1/6/2025 Partial Approval CARLOS MATAMOROS
Gas Test 6/4/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 6/4/2025 Partial Approval CARLOS MATAMOROS
Sewer 6/4/2025 Approved CARLOS MATAMOROS
Underground Mechanical 6/4/2025 Approved CARLOS MATAMOROS
Special/Order Compliance 7/1/2025 Partial Inspection MICHAEL PELHAM
BUILDING-Rough-Frame 9/25/2025 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 9/25/2025 Approved CARLOS MATAMOROS
Gas Test 9/25/2025 Approved CARLOS MATAMOROS
HVAC-Rough 9/25/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 9/25/2025 Not Ready for Inspection CARLOS MATAMOROS
Deputy Wood Construction 10/8/2025 Conditional Approval JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 10/16/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 11/4/2025 Approved CARLOS MATAMOROS
Insulation 11/10/2025 Corrections Issued DANIEL VERA
Insulation 11/18/2025 Corrections Issued DANIEL VERA
Insulation 1/28/2026 Approved EVAN COOPER
Drywall Nailing 2/18/2026 Approved EVAN COOPER
Green Building Rough 2/18/2026 Approved EVAN COOPER
Shower Pan 4/8/2026 Approved EVAN COOPER