449 N PARKWOOD DR 90077
Certificate Information: 449 N PARKWOOD DR 90077
- Application / Permit
- 20014-10000-00230
- Plan Check / Job No.
- B20LA01034
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- Convert (e) pool house to accessory living quarter and propose ground floor addition
- Permit Issued
- Issued on 2/17/2021
- Issuing Office
- Current Status
- CofO Issued on 9/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2020 | VU NGUYEN |
| Corrections Issued | 1/21/2020 | VU NGUYEN |
| Plan Check Approved | 1/21/2020 | ADAM HEGAZI |
| Issued | 2/17/2021 | APPLICANT |
| Building Plans Picked Up | 2/19/2021 | APPLICANT |
| CofO in Progress | 9/8/2022 | CHRISTOPHER WILSON |
| CofO in Progress | 9/8/2022 | CHRISTOPHER WILSON |
| CofO Issued | 9/10/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/10/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| CPC | Cleared | 1/21/2020 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 1/21/2020 | VU NGUYEN |
| Miscellaneous | Cleared | 1/21/2020 | JOE LUCKEY |
| Miscellaneous | Cleared | 1/21/2020 | JOE LUCKEY |
| Roof/Waste drainage to street | Cleared | 1/21/2020 | JEANIE LAM |
Contact Information
| Architect | Manion,, Richard M; Lic. No.: C26957 | 11400 WEST OLYMPIC BLVD SUITE 410 LOS ANGELES, CA 90025 |
| Contractor | J D S S Construction Company Inc; Lic. No.: 425872-B | 1702 S ROBERTSON BLVD #285 LOS ANGELES, CA 90035 |
| Engineer | Golabtounkar,, Tony Hamid; Lic. No.: C49104 | 1434 WESTWOOD BLVD ST 17 LOS ANGELES, CA 90024 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/26/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Underground Mechanical | 3/26/2021 | Approved | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 3/31/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 4/12/2021 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/17/2021 | Approved | MATT KELLERMAN |
| PLUMBING-Rough | 8/17/2021 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 10/28/2021 | Partial Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 10/28/2021 | Partial Inspection | CHRISTOPHER WILSON |
| Insulation | 10/28/2021 | Partial Inspection | CHRISTOPHER WILSON |
| Rough-Elec/Plmb/HVAC | 10/28/2021 | Partial Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 12/1/2021 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 12/8/2021 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 12/8/2021 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 12/8/2021 | Partial Approval | CHRISTOPHER WILSON |
| Insulation | 12/13/2021 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 12/22/2021 | Approved | RYAN SALAZAR |
| Shower Pan | 1/13/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 1/18/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 8/22/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 8/22/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Final | 8/22/2022 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 8/22/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 8/22/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 8/22/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 8/31/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 8/31/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Final | 8/31/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 8/31/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 9/7/2022 | Approved | CHRISTOPHER WILSON |
| Final | 9/7/2022 | OK to Issue CofO | CHRISTOPHER WILSON |
| HVAC-Final | 9/7/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 9/7/2022 | Approved | CHRISTOPHER WILSON |