2709 N BENEDICT ST 90039

Certificate Information: 2709 N BENEDICT ST 90039

Application / Permit
20014-10000-00221
Plan Check / Job No.
B20LA00998
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 10'X20' PLAYROOM TO ADU AND ADD 20'X3'1" & 13'11"X8 IRREGULAR SHAPE GROUND FLOOR ADDITION.
Permit Issued
Issued on 9/17/2020
Issuing Office
Current Status
CofO Issued on 9/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2020 APPLICANT
Assigned to Plan Check Engineer 2/7/2020 AMIR DANAI
Corrections Issued 2/11/2020 AMIR DANAI
Quality Review Completed 2/28/2020 TIEN JEN WANG
Building Plans Picked Up 3/4/2020 APPLICANT
Green Plans Picked Up 7/10/2020 APPLICANT
Applicant returned to address corrections 7/16/2020 AMIR DANAI
Plan Check Approved 8/4/2020 AMIR DANAI
Issued 9/17/2020 APPLICANT
CofO in Progress 8/24/2021 THOMAS LOGRASSO
Permit Finaled 9/16/2021 DEROLD HAUFF
Permit Finaled 9/16/2021 DEROLD HAUFF
CofO Issued 9/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/23/2020 ELENA LOPEZ
Low Impact Development Cleared 6/23/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/23/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 6/24/2020 ELENA LOPEZ
Sewer availability Cleared 6/24/2020 ELENA LOPEZ
ZI Cleared 6/24/2020 TERRI OSBORNE
Green Code Cleared 7/6/2020 KHEDER ALRAZAA

Contact Information

No Data Available.

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/14/2020 Not Ready for Inspection DAVID CHAN
Underground Mechanical 10/14/2020 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 10/26/2020 Approved SCOTT FINNILA
Underground Mechanical 10/26/2020 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 12/10/2020 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 12/10/2020 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 12/10/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 12/10/2020 Corrections Issued KATHRYN BUTTERWORTH
MERV13>=Rough 12/10/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 12/10/2020 Approved KATHRYN BUTTERWORTH
Sewer 12/10/2020 Approved KATHRYN BUTTERWORTH
Shower Pan 12/10/2020 Approved KATHRYN BUTTERWORTH
Underground Mechanical 12/10/2020 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 12/29/2020 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 12/29/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 12/29/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/29/2020 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/6/2021 Approved SCOTT FINNILA
Green Building Rough 1/6/2021 Approved SCOTT FINNILA
HVAC-Rough 1/6/2021 Approved SCOTT FINNILA
Insulation 1/6/2021 Approved SCOTT FINNILA
MERV13>=Rough 1/6/2021 Approved SCOTT FINNILA
Drywall Nailing 1/11/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 1/11/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 3/23/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 3/23/2021 Corrections Issued KATHRYN BUTTERWORTH
Gas Test 3/23/2021 Approved KATHRYN BUTTERWORTH
Green Building Final 3/23/2021 Approved KATHRYN BUTTERWORTH
HVAC-Final 3/23/2021 Approved KATHRYN BUTTERWORTH
MERV13>=Final 3/23/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Final 3/23/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 3/23/2021 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 3/23/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 4/30/2021 Approved ROBERT VORHIS
Final 4/30/2021 Corrections Issued ROBERT VORHIS
HVAC-Final 4/30/2021 Approved ROBERT VORHIS
PLUMBING-Final 4/30/2021 Approved ROBERT VORHIS
Smoke Detectors 4/30/2021 Approved ROBERT VORHIS
Final 5/21/2021 Corrections Issued HAMIK HARTOUNIAN
Final 8/23/2021 OK to Issue CofO THOMAS LOGRASSO