10603 W BRADBURY ROAD 90064

Certificate Information: 10603 W BRADBURY ROAD 90064

Application / Permit
20014-10000-00218
Plan Check / Job No.
B20LA00993
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMO AND REMOVE INTERIOR STAIR, ADD A STAIR AND NOOK @ FIRST FLOOR ADD A HALLWAY @ 2ND FLOOR, ENLARGE EXISTING BEDROOM AND DECK @ 2ND FLOOR
Permit Issued
Issued on 7/15/2020
Issuing Office
Current Status
CofO Issued on 3/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 JESSE ARELLANO
Corrections Issued 3/7/2020 JESSE ARELLANO
Quality Review Completed 3/18/2020 BILL STUTSMAN
Applicant returned to address corrections 5/1/2020 JESSE ARELLANO
Green Plans Picked Up 5/20/2020 APPLICANT
Plan Check Approved 6/26/2020 JESSE ARELLANO
Issued 7/15/2020 APPLICANT
Building Plans Picked Up 7/17/2020 APPLICANT
CofO in Progress 3/11/2022 KEVIN SARGSYAN
CofO in Progress 3/15/2022 KENNETH NAGLE
Permit Finaled 3/17/2022 DANIEL ORRANTE
CofO Issued 3/17/2022 DANIEL ORRANTE
Permit Finaled 3/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Green Code Cleared 5/7/2020 JESSE ARELLANO
Roof/Waste drainage to street Cleared 5/19/2020 DINAH GARIN
Sewer availability Cleared 5/19/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/20/2020 DINAH GARIN
GPI Written Notices Cleared 5/27/2020 JESSE ARELLANO
Grading Pre-Inspection Cleared 5/29/2020 VASIL MIHALEV

Contact Information

Contractor Mike T Construction Inc; Lic. No.: 800312-B 9517 WOODLEY AVENUE      NORTH HILLS, CA 91343
Engineer Saleh,, Zouheir Toufic; Lic. No.: C42881 1304 CORTE MALTERA      COSTA MESA, CA 92626

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Elevation Certificate 8/18/2020 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 8/18/2020 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2020 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 11/12/2020 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 11/12/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 11/12/2020 Corrections Issued KEVIN SARGSYAN
Wood Frame 11/12/2020 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 11/17/2020 Approved KEVIN SARGSYAN
FLOOD-Proofing Certificate 11/17/2020 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Approved KEVIN SARGSYAN
Green Building Rough 11/17/2020 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 11/17/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 11/17/2020 Approved KEVIN SARGSYAN
HVAC-Rough 1/12/2021 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 1/12/2021 Not Ready for Inspection KEVIN SARGSYAN
Wood Frame 1/12/2021 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 1/21/2021 Corrections Issued KEVIN SARGSYAN
FLOOD-Proofing Certificate 1/21/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 1/21/2021 Approved KEVIN SARGSYAN
HVAC-Rough 1/21/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 1/21/2021 Partial Approval KEVIN SARGSYAN
Shower Pan 1/21/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 1/25/2021 Partial Approval KEVIN SARGSYAN
Insulation 1/28/2021 Approved KEVIN SARGSYAN
Drywall Nailing 2/16/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/7/2022 No Access for Inspection KEVIN SARGSYAN
FLOOD-Proofing Certificate 1/7/2022 No Access for Inspection KEVIN SARGSYAN
Final 1/7/2022 No Access for Inspection KEVIN SARGSYAN
Green Building Final 1/7/2022 No Access for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/7/2022 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 1/7/2022 No Access for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 2/2/2022 Approved KEVIN SARGSYAN
FLOOD-Proofing Certificate 2/2/2022 Approved KEVIN SARGSYAN
Final 2/2/2022 Corrections Issued KEVIN SARGSYAN
Green Building Final 2/2/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/2/2022 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 2/2/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 2/11/2022 Approved KEVIN SARGSYAN
Final 2/11/2022 Not Ready for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Approved KEVIN SARGSYAN
Final 2/24/2022 Corrections Issued EVAN COOPER
Final 3/11/2022 OK to Issue CofO KEVIN SARGSYAN