6083 E YORK BLVD 90042

Certificate Information: 6083 E YORK BLVD 90042

Application / Permit
20014-10000-00204
Plan Check / Job No.
B20LA00945
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1-STORY ADDITION AND REMODEL TO SFD; WORLK TO ICLUIDE RELOCATING KITCHEN AND ADDITION OF 2 BEDROOMS AND FRONT PORCH
Permit Issued
Issued on 2/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2020 APPLICANT
Assigned to Plan Check Engineer 1/17/2020 SINA KHOSRAVI
Corrections Issued 1/17/2020 SINA KHOSRAVI
Applicant returned to address corrections 1/24/2020 SINA KHOSRAVI
Issued 2/10/2020 LADBS
CofO in Progress 12/30/2020 CRAIG VAUGHAN
Permit Finaled 1/7/2021 DEROLD HAUFF
CofO Issued 1/7/2021 DEROLD HAUFF
Permit Finaled 1/7/2021 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 1/24/2020 JASON CHAN
Eng Process Fee Ord 176,300 Cleared 1/24/2020 ELAINE LEI
Grading Pre-Inspection Cleared 1/24/2020 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 1/24/2020 ELAINE LEI
Sewer availability Cleared 1/24/2020 ELAINE LEI
GPI Written Notices Cleared 2/10/2020 SINA KHOSRAVI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/16/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 3/18/2020 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 3/20/2020 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 4/7/2020 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 4/7/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/22/2020 Partial Approval CRAIG VAUGHAN
Green Building Rough 4/22/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 5/21/2020 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 5/21/2020 Partial Approval CRAIG VAUGHAN
Wood Frame 5/21/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 5/28/2020 Approved CRAIG VAUGHAN
Green Building Rough 5/28/2020 Approved CRAIG VAUGHAN
HVAC-Rough 5/28/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/28/2020 Approved CRAIG VAUGHAN
Wood Frame 5/28/2020 Approved CRAIG VAUGHAN
Insulation 6/3/2020 Not Ready for Inspection COREY HUPP
Insulation 6/5/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/5/2020 Partial Approval CRAIG VAUGHAN
Drywall Nailing 6/12/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/16/2020 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/3/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Final 9/3/2020 Corrections Issued CRAIG VAUGHAN
Final 9/3/2020 Corrections Issued CRAIG VAUGHAN
Gas Test 9/3/2020 Approved CRAIG VAUGHAN
Green Building Final 9/3/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 9/3/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/3/2020 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 9/3/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Final 10/16/2020 Approved CRAIG VAUGHAN
Final 10/16/2020 Corrections Issued CRAIG VAUGHAN
Green Building Final 10/16/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 10/16/2020 Approved CRAIG VAUGHAN
PLUMBING-Final 10/16/2020 Approved CRAIG VAUGHAN
Final 12/29/2020 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 12/29/2020 Approved CRAIG VAUGHAN