608 W ETTA ST 90065
Certificate Information: 608 W ETTA ST 90065
- Application / Permit
- 20014-10000-00179
- Plan Check / Job No.
- B20LA00791
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMOLISH (E) 3 LEVEL BALCONIES AND REBUILD.
- Permit Issued
- Issued on 7/6/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/25/2025
Permit Application Status History
| Submitted | 1/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | SAMUEL GONZALEZ |
| Green Plans Picked Up | 8/27/2020 | APPLICANT |
| Corrections Issued | 2/4/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 2/4/2021 | SAMUEL GONZALEZ |
| Issued | 7/6/2021 | APPLICANT |
| Building Plans Picked Up | 7/7/2021 | APPLICANT |
| CofO in Progress | 7/18/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 7/24/2025 | RAUL BARAJAS |
| No Progress | 7/24/2025 | RAUL BARAJAS |
| CofO in Progress | 7/24/2025 | RAUL BARAJAS |
| CofO in Progress | 7/24/2025 | RAUL BARAJAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/15/2020 | VASIL MIHALEV |
| Roof/Waste drainage to street | Cleared | 5/19/2020 | JEANIE LAM |
| Green Code | Cleared | 8/26/2020 | SAMUEL GONZALEZ |
| Specific Plan | Cleared | 11/17/2020 | SARAHI ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2020 | JUAN ASHTON |
| ZA Case | Cleared | 7/2/2021 | SARAHI ORTEGA |
Contact Information
| Architect | , ; Lic. No.: C34529 | , |
| Contractor | Mint Leaf Construction Inc The; Lic. No.: 994908-B | 314 W 58TH ST STE 160 LOS ANGELES, CA 90037 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
| Geologist | Cugno,, Giuseppe; Lic. No.: EG1804 | 1461 E CHEVY CHASE DR 200 BYER GEOTECHNICAL, INC. GLENDALE, CA 91206 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/6/2022 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/6/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 7/19/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 8/1/2022 | Approved | OSVALDO PARAMO |
| Piling/Pier/Caisson | 8/1/2022 | Approved | OSVALDO PARAMO |
| Structural Steel Frame | 9/29/2022 | Approved | OSVALDO PARAMO |
| Wood Frame | 9/29/2022 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 10/12/2022 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 10/26/2022 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 6/5/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/10/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/10/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/10/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 7/16/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/16/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/18/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 7/24/2025 | Permit Finaled | RAUL BARAJAS |