1327 W 71ST ST 90044
Certificate Information: 1327 W 71ST ST 90044
- Application / Permit
- 20014-10000-00175
- Plan Check / Job No.
- B20LA00781
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND NEW ADDITION (12'-8" X 14'-2") TO REAR OF (E) SFD; ALL WORK PER WFPP
- Permit Issued
- Issued on 5/14/2020
- Issuing Office
- Metro
- Current Status
- Issued on 5/14/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 1/16/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 1/23/2020 | SINA KHOSRAVI |
| Plan Check Approved | 1/23/2020 | FERNANDO FLORES |
| Issued | 5/14/2020 | LADBS |
| Building Plans Picked Up | 5/15/2020 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 1/23/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 1/23/2020 | JUAN ASHTON |
| ZI | Cleared | 1/23/2020 | ANNA VIDAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/7/2020 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/14/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/30/2020 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 7/30/2020 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 8/5/2020 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/25/2020 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/25/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 9/25/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/29/2020 | Partial Approval | FREDDIE RIVERA |
| Wood Frame | 10/29/2020 | Partial Approval | FREDDIE RIVERA |
| Insulation | 11/6/2020 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 11/16/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/6/2023 | Approved | ENRIQUE MIRELES |
| Final | 6/6/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 6/6/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 6/6/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 6/6/2023 | Approved | ENRIQUE MIRELES |