16256 W HIAWATHA ST 91344

Certificate Information: 16256 W HIAWATHA ST 91344

Application / Permit
20014-10000-00153
Plan Check / Job No.
B20LA00674
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST FLOOR ADDITION ( 1- BED, 280 SF ) AND STAIRS TO NEW 2ND FLOOR DECK AT REAR TO (E) 2-STORY S.F.D.
Permit Issued
Issued on 7/10/2020
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2020 APPLICANT
Assigned to Plan Check Engineer 1/21/2020 MONICA RAMIREZ
Corrections Issued 1/21/2020 MONICA RAMIREZ
Plan Check Approved 3/3/2020 FERNANDO FLORES
Issued 7/10/2020 APPLICANT
CofO in Progress 2/17/2022 RAUL OLAGI
Permit Finaled 3/16/2022 RONALD MYRICK
CofO Issued 3/16/2022 RONALD MYRICK
Permit Finaled 3/16/2022 RONALD MYRICK

Permit Application Clearance Information

Construction near power lines Cleared 1/21/2020 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 1/21/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/18/2020 JEANIE LAM
Sewer availability Cleared 2/18/2020 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/3/2021 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 8/13/2021 Approved MARK JOHNSON
Footing/Foundation/Slab 8/25/2021 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 10/6/2021 Corrections Issued MARK JOHNSON
Green Building Rough 10/6/2021 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 10/14/2021 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 10/14/2021 Corrections Issued MATTHEW NELSON
Green Building Rough 10/14/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 10/19/2021 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 10/19/2021 Approved MARK JOHNSON
Green Building Rough 10/19/2021 Not Ready for Inspection MARK JOHNSON
Green Building Rough 11/2/2021 Partial Approval MARK JOHNSON
Insulation 11/15/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 11/15/2021 Approved MARK JOHNSON
Drywall Nailing 11/23/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 1/26/2022 Approved JENNIFER RABUCHIN
Final 1/26/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 1/26/2022 Approved JENNIFER RABUCHIN
Green Building Final 1/26/2022 Approved JENNIFER RABUCHIN
Green Building Rough 1/26/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/26/2022 Approved JENNIFER RABUCHIN
Final 2/16/2022 OK to Issue CofO RAUL OLAGI