3031 N MINNESOTA ST 90031
Certificate Information: 3031 N MINNESOTA ST 90031
- Application / Permit
- 20014-10000-00145
- Plan Check / Job No.
- B20LA00659
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 226 sf ADDITION TO ADD (N) MASTER BEDROOM AND REMODEL OF (E) KITCHEN, BATHROOMS, AND DINING ROOM ALONG THE (E) FOOTPRINT OF STRUCTURE. **NO CHANGE TO (E) ATTIC AREA.
- Permit Issued
- Issued on 7/10/2020
- Issuing Office
- Current Status
- CofO Issued on 11/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2020 | APPLICANT |
| Green Plans Picked Up | 1/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | SEAN SHAHMIRI |
| Corrections Issued | 2/10/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 2/14/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 2/18/2020 | APPLICANT |
| Applicant returned to address corrections | 3/27/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 5/13/2020 | SEAN SHAHMIRI |
| Issued | 7/10/2020 | APPLICANT |
| CofO in Progress | 10/28/2022 | OSVALDO PARAMO |
| CofO in Progress | 10/28/2022 | OSVALDO PARAMO |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
| CofO Issued | 11/5/2022 | DEROLD HAUFF |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/25/2020 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 2/25/2020 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 2/25/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 2/25/2020 | PATRICK MISCHLICH |
| Sewer availability | Cleared | 2/25/2020 | JEANIE LAM |
| Green Code | Cleared | 3/2/2020 | VIVIAN LAO |
| BHO/Hillside ordinance | Cleared | 3/13/2020 | JAMES MORALEZ |
| Low Impact Development | Cleared | 3/13/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 3/13/2020 | JAMES MORALEZ |
| "D" conditions | Cleared | 3/19/2020 | RICHARD REASER |
| "Q" conditions | Cleared | 3/19/2020 | RICHARD REASER |
| ZI | Cleared | 3/19/2020 | RICHARD REASER |
| Hydrant and Access approval | Cleared | 6/11/2020 | KURT CORRAL |
Contact Information
| Contractor | Zorzoli Construction Inc; Lic. No.: 965210-B | 19903 EAST RAMBLING ROAD COVINA, CA 91724 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 5525 CANOGA AVE APT 208 WOODLAND HILLS, CA 91367 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/16/2020 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 7/21/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 7/24/2020 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/24/2020 | Approved | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 8/5/2020 | Partial Approval | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 9/1/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2020 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 9/9/2020 | Partial Approval | OSVALDO PARAMO |
| Insulation | 9/11/2020 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 9/11/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 12/28/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| PLUMBING-Rough | 12/29/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 1/6/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 1/13/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/1/2021 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 4/1/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 4/1/2021 | Partial Approval | OSVALDO PARAMO |
| Insulation | 4/7/2021 | Corrections Issued | RUBEN SALAS |
| BUILDING-Rough-Frame | 4/19/2021 | Approved | OSVALDO PARAMO |
| Insulation | 4/19/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 4/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 4/18/2022 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 4/18/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 4/18/2022 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 4/18/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 5/26/2022 | OK to Issue CofO | OSVALDO PARAMO |
| Smoke Detectors | 5/26/2022 | Approved | OSVALDO PARAMO |