5929 W 76TH ST 90045

Certificate Information: 5929 W 76TH ST 90045

Application / Permit
20014-10000-00123
Plan Check / Job No.
B20LA00555
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1-STORY ADDITION NEW ADU ATTACHED TO (E) DETACHED GARAGE.
Permit Issued
Issued on 7/24/2020
Issuing Office
Current Status
CofO Issued on 1/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2020 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 ALBERT SERVIN
Corrections Issued 2/11/2020 ALBERT SERVIN
Quality Review Completed 2/12/2020 KEN GILL
Building Plans Picked Up 2/21/2020 APPLICANT
Applicant returned to address corrections 4/8/2020 ALBERT SERVIN
Applicant returned to address corrections 5/5/2020 ALBERT SERVIN
Green Plans Picked Up 6/4/2020 APPLICANT
Applicant returned to address corrections 6/9/2020 ALBERT SERVIN
Plan Check Approved 7/10/2020 ALBERT SERVIN
Issued 7/24/2020 APPLICANT
CofO in Progress 11/16/2020 JUAN VALENZUELA
Permit Finaled 1/5/2021 RONALD MYRICK
CofO Issued 1/5/2021 RONALD MYRICK
Permit Finaled 1/5/2021 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 5/1/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 5/4/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/5/2020 DINAH GARIN
Sewer availability Cleared 5/5/2020 DINAH GARIN
Green Code Cleared 6/1/2020 NEGAR NEJAD

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/30/2020 Approved JUAN VALENZUELA
Underground Mechanical 7/30/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/10/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Partial Approval JUAN VALENZUELA
Green Building Rough 8/13/2020 Not Ready for Inspection JUAN VALENZUELA
Interior/Exterior Lathing 8/14/2020 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 8/26/2020 No Access for Inspection KENNETH NAGLE
HVAC-Rough 8/26/2020 No Access for Inspection KENNETH NAGLE
PLUMBING-Rough 8/26/2020 No Access for Inspection KENNETH NAGLE
ELECTRICAL-Rough 8/27/2020 Corrections Issued CRAIG DAVIS
HVAC-Rough 8/27/2020 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 8/27/2020 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 8/31/2020 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 8/31/2020 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 9/2/2020 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 9/2/2020 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 9/2/2020 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 9/3/2020 Approved JUAN VALENZUELA
Green Building Rough 9/3/2020 Approved JUAN VALENZUELA
Rough-Elec/Plmb/HVAC 9/3/2020 Approved JUAN VALENZUELA
Insulation 9/4/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 9/4/2020 Approved JUAN VALENZUELA
Shower Pan 9/4/2020 Approved JUAN VALENZUELA
Drywall Nailing 9/11/2020 Approved JUAN VALENZUELA
ELECTRICAL-Final 11/5/2020 Corrections Issued JUAN VALENZUELA
Final 11/5/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 11/5/2020 Approved JUAN VALENZUELA
Green Building Final 11/5/2020 Approved JUAN VALENZUELA
HVAC-Final 11/5/2020 Approved JUAN VALENZUELA
PLUMBING-Final 11/5/2020 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/5/2020 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 11/5/2020 Approved JUAN VALENZUELA
ELECTRICAL-Final 11/16/2020 Approved JUAN VALENZUELA
Final 11/16/2020 OK to Issue CofO JUAN VALENZUELA
PLUMBING-Final 11/16/2020 Approved JUAN VALENZUELA
Service/Power Release 11/16/2020 Approved JUAN VALENZUELA