148-150 N ROBINSON ST 90026

Certificate Information: 148-150 N ROBINSON ST 90026

Application / Permit
20014-10000-00088
Plan Check / Job No.
B20LA00433
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADDITION OF (25'-7" X 50'-6") TO 1ST FLOOR IN REAR OF 2-STORY DUPLEX
Permit Issued
Issued on 8/26/2021
Issuing Office
Metro
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 MOHAMMAD ESMAILI
Corrections Issued 2/25/2020 MOHAMMAD ESMAILI
Quality Review Completed 3/9/2020 OMID HEDAYAT
Green Plans Picked Up 6/26/2020 APPLICANT
Building Plans Picked Up 7/21/2020 APPLICANT
Applicant returned to address corrections 11/19/2020 MOHAMMAD ESMAILI
Plan Check Approved 3/15/2021 MOHAMMAD ESMAILI
Issued 8/26/2021 APPLICANT
CofO in Progress 9/19/2023 ALIZAH MAYAGOITIA
CofO Issued 9/25/2023 DEROLD HAUFF
Permit Finaled 9/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/12/2020 RENZ SORIANO
Sewer availability Cleared 5/12/2020 RENZ SORIANO
Green Code Cleared 6/24/2020 VIVIAN LAO
Tenant Habitability Plan Cleared 7/21/2020 MICHAEL GREGERSON
Grading Pre-Inspection Cleared 7/28/2020 KIRK LINKLATER
Low Impact Development Cleared 10/4/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/9/2020 JEANIE LAM
GPI Written Notices Cleared 3/3/2021 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Donlong Peter; Lic. No.: S3948 8748 E VALLEY BLVD L      ROSEMEAD, CA 91770

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/15/2022 Corrections Issued FREDDIE RIVERA
METHANE-Barrier 3/15/2022 Not Ready for Inspection FREDDIE RIVERA
METHANE-Subgrade 3/15/2022 Not Ready for Inspection FREDDIE RIVERA
Deputy Drilled-In Anchors 3/18/2022 Conditional Approval FREDDIE RIVERA
Deputy Other (see comments) 3/18/2022 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 3/22/2022 Corrections Issued STUART CHAPMAN
METHANE-Barrier 3/22/2022 Approved STUART CHAPMAN
METHANE-Subgrade 3/22/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 3/25/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/11/2022 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 4/11/2022 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 6/16/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/16/2022 Partial Approval FREDDIE RIVERA
Gas Test 6/16/2022 Partial Inspection FREDDIE RIVERA
Green Building Rough 6/16/2022 Partial Inspection FREDDIE RIVERA
HVAC-Rough 6/16/2022 Partial Inspection FREDDIE RIVERA
METHANE-Rough 6/16/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 6/16/2022 Partial Inspection FREDDIE RIVERA
Wood Frame 6/16/2022 Partial Inspection FREDDIE RIVERA
HVAC-Rough 6/21/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 6/21/2022 Approved FREDDIE RIVERA
Wood Frame 6/21/2022 Partial Inspection FREDDIE RIVERA
Green Building Rough 6/23/2022 Approved FREDDIE RIVERA
Insulation 6/23/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 6/23/2022 Approved FREDDIE RIVERA
Wood Frame 6/23/2022 Corrections Issued FREDDIE RIVERA
Insulation 6/30/2022 Corrections Issued FREDDIE RIVERA
Wood Frame 6/30/2022 Approved FREDDIE RIVERA
Drywall Nailing 7/13/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 7/13/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 7/20/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 11/17/2022 Approved FREDDIE RIVERA
Final 11/17/2022 Corrections Issued FREDDIE RIVERA
Green Building Final 11/17/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/17/2022 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 11/17/2022 Corrections Issued FREDDIE RIVERA
Final 4/3/2023 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 4/3/2023 SGSOV Not Ready FREDDIE RIVERA
Final 6/9/2023 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/9/2023 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 6/9/2023 Partial Inspection FREDDIE RIVERA
Final 9/5/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 9/5/2023 SGSOV Not Ready THOMAS LOGRASSO
Smoke Detectors 9/5/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 9/13/2023 Partial Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/13/2023 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 9/13/2023 Approved ALIZAH MAYAGOITIA
Final 9/18/2023 OK to Issue CofO ALIZAH MAYAGOITIA