6134 N GLADE AVE 91367

Certificate Information: 6134 N GLADE AVE 91367

Application / Permit
20014-10000-00085
Plan Check / Job No.
B20LA00421
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(8) Automobile Sales - new
Work Description
ADDITION AND TENANT IMPROVEMENTS OF AN EXISTING CAR DEALERSHIP BUILDING. NEW REPAIR SERVICE STATION WITH ROOF DECK PARKING FOR INVENTORY CARS. NEW FACADE IMPROVEMENTS AND INTERIOR LAYOUT MODIFICATIONS TO PART OF EXISTING BUILDING. JAGUAR/LAND ROVER DEALERSHIP.
Permit Issued
Issued on 3/5/2021
Issuing Office
Current Status
CofO Issued on 6/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2020 APPLICANT
Disabled Access Plans Picked Up 3/6/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 JOE VO
Corrections Issued 3/17/2020 JOE VO
Quality Review Completed 3/18/2020 KEN GILL
Applicant returned to address corrections 6/23/2020 JOE VO
Applicant returned to address corrections 6/29/2020 JOE VO
Applicant returned to address corrections 7/6/2020 JOE VO
Applicant returned to address corrections 8/19/2020 JOE VO
Applicant returned to address corrections 12/17/2020 JOE VO
Applicant returned to address corrections 12/21/2020 JOE VO
Applicant returned to address corrections 1/7/2021 JOE VO
Green Plans Picked Up 1/11/2021 APPLICANT
Applicant returned to address corrections 2/23/2021 JOE VO
Plan Check Approved 3/2/2021 JOE VO
Issued 3/5/2021 APPLICANT
Building Plans Picked Up 3/11/2021 APPLICANT
TCO Issued (Expire Date: 07-04-2023) 1/5/2023 JEFFREY DURAN
TCO Issued (Expire Date: 01-03-2024) 7/7/2023 JEFFREY DURAN
TCO Issued (Expire Date: 06-18-2024) 12/21/2023 JEFFREY DURAN
CofO in Progress 6/18/2024 CAMERON CHABAN
Permit Finaled 6/20/2024 RICKEY JACKSON
CofO Issued 6/20/2024 RICKEY JACKSON
Permit Finaled 6/20/2024 RICKEY JACKSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/16/2020 GABRIEL ROBLES
Sewer availability Cleared 6/16/2020 GABRIEL ROBLES
Driveway location Cleared 7/1/2020 COLLINS ALLAN
Address approval Cleared 7/9/2020 HOWARD COOPER
Automotive Use Cleared 10/28/2020 RICHARD REASER
Automotive Use Cleared 10/28/2020 RICHARD REASER
CPC Cleared 10/28/2020 RICHARD REASER
Comm Cor/Mini-Mall Cleared 10/28/2020 RICHARD REASER
Comm Cor/Mini-Mall Cleared 10/28/2020 RICHARD REASER
Comm Cor/Mini-Mall Cleared 10/28/2020 RICHARD REASER
Prkng lot landscape/Water mgmt Cleared 10/28/2020 RICHARD REASER
ZA Case Cleared 10/28/2020 RICHARD REASER
ZA Case Cleared 10/28/2020 RICHARD REASER
DAS Clearance Cleared 12/22/2020 SHINE LIN
Green Code Cleared 1/8/2021 VIVIAN LAO
Hydrant and Access approval Cleared 1/19/2021 KURT CORRAL
Specific Plan Cleared 1/28/2021 RICHARD REASER
ZI Cleared 1/28/2021 RICHARD REASER
Low Impact Development Cleared 2/11/2021 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 3/1/2021 MARKOS PEREZ-BRAN

Contact Information

Architect Petruzzi,, Peter; Lic. No.: C18480 1165 FRANCISCO ST #7      SAN FRANCISCO, CA 94109
Contractor Pacific West Builders Inc; Lic. No.: 752705-B 1197 LOS ANGELES AVE STE C 166      SIMI VALLEY, CA 93065
Engineer Nangia,, Robert Vivak; Lic. No.: S5400 7423 HOLLOW RIDGE DR      HOUSTON, TX 77095

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/9/2021 Partial Inspection DANNY RODRIGUEZ
Pre-Inspection 5/12/2021 Partial Inspection CAMERON CHABAN
Deputy Reinf. Concrete 6/9/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/11/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 6/14/2021 Corrections Issued DANIEL VARNUM
Piling/Pier/Caisson 6/15/2021 Partial Approval DANIEL VARNUM
Deputy Drilled-In Anchors 6/16/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/16/2021 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 6/16/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 6/21/2021 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 6/30/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/1/2021 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 7/7/2021 Conditional Approval DANIEL VARNUM
Footing/Foundation/Slab 7/7/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/8/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 7/13/2021 Partial Inspection CAMERON CHABAN
Structural Steel Frame 7/13/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/14/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/15/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/16/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 7/16/2021 Partial Inspection CAMERON CHABAN
Structural Steel Frame 7/16/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/23/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 7/29/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/30/2021 Conditional Approval CAMERON CHABAN
Structural Steel Frame 7/30/2021 Not Ready for Inspection CAMERON CHABAN
Deputy Reinf. Masonry 8/2/2021 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 8/2/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/3/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/4/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/5/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 8/5/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/9/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/10/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/11/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/12/2021 Conditional Approval DANIEL VARNUM
Deputy Drilled-In Anchors 8/13/2021 Conditional Approval ROBERT DAVIS
Deputy Reinf. Masonry 8/13/2021 Conditional Approval ROBERT DAVIS
Deputy Reinf. Masonry 8/16/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/17/2021 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Masonry 8/18/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 8/18/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/19/2021 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 8/19/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 8/19/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 8/20/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/20/2021 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 8/20/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/23/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 8/23/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 8/24/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/24/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/25/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/26/2021 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 8/26/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/27/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 8/30/2021 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Concrete 9/8/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 9/8/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 9/9/2021 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 9/13/2021 Not Ready for Inspection CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 9/17/2021 Partial Approval PAUL DAVIDSON
Masonry Wall/Backfill 9/21/2021 Partial Approval DANIEL VARNUM
Deputy Reinf. Masonry 9/22/2021 Conditional Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 9/23/2021 Partial Approval KENNETH ROBERTS
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Partial Approval DANIEL VARNUM
Green Building Rough 10/6/2021 Not Ready for Inspection DANIEL VARNUM
Deputy Pre-Stress Concrete 10/8/2021 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 10/8/2021 Partial Approval DANIEL VARNUM
Special/Order Compliance 10/8/2021 No Access for Inspection DANIEL VARNUM
Deputy Pre-Stress Concrete 10/12/2021 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 10/13/2021 Conditional Approval JEFFREY DURAN
Green Building Rough 10/13/2021 Not Ready for Inspection DANIEL VARNUM
Structural Steel Frame 10/13/2021 Partial Approval DANIEL VARNUM
Deputy Pre-Stress Concrete 10/14/2021 Conditional Approval DANIEL VARNUM
Deputy Pre-Stress Concrete 10/15/2021 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 11/1/2021 Not Ready for Inspection PAUL DAVIDSON
Deputy Shotcrete 11/2/2021 Conditional Approval KENNETH ROBERTS
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Partial Approval KENNETH ROBERTS
Deputy Shotcrete 11/3/2021 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 11/4/2021 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 11/5/2021 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 11/10/2021 Conditional Approval JEFFREY DURAN
Light Gage Steel Frame 11/15/2021 Partial Approval CAMERON CHABAN
Footing/Foundation/Slab 11/19/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 11/24/2021 Partial Approval DANIEL VARNUM
Drywall Nailing 12/2/2021 Partial Approval CAMERON CHABAN
Green Building Rough 12/2/2021 Approved CAMERON CHABAN
Insulation 12/2/2021 Partial Approval CAMERON CHABAN
Insulation 12/7/2021 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/8/2021 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 12/10/2021 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 12/13/2021 Conditional Approval CAMERON CHABAN
Drywall Nailing 12/13/2021 Conditional Approval CAMERON CHABAN
Light Gage Steel Frame 12/20/2021 Conditional Approval CAMERON CHABAN
Insulation 12/21/2021 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/23/2021 Not Ready for Inspection CAMERON CHABAN
Insulation 12/23/2021 Approved CAMERON CHABAN
Footing/Foundation/Slab 12/28/2021 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 12/29/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 1/12/2022 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 1/31/2022 Conditional Approval CAMERON CHABAN
T-Bar Ceiling 1/31/2022 Not Ready for Inspection CAMERON CHABAN
T-Bar Ceiling 2/1/2022 Conditional Approval CAMERON CHABAN
Drywall Nailing 2/4/2022 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 2/14/2022 Approved CAMERON CHABAN
Interior/Exterior Lathing 3/8/2022 Partial Approval CAMERON CHABAN
T-Bar Ceiling 3/22/2022 Approved CAMERON CHABAN
Deputy Drilled-In Anchors 4/15/2022 Conditional Approval CAMERON CHABAN
Green Building Final 6/24/2022 Approved CAMERON CHABAN
Drywall Nailing 7/1/2022 Approved CAMERON CHABAN
Final 7/1/2022 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 7/1/2022 Approved CAMERON CHABAN
Reinforced Concrete Frame 7/1/2022 Approved CAMERON CHABAN
Reinforced Masonry Frame 7/1/2022 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 7/1/2022 SGSOV Approved CAMERON CHABAN
Smoke Detectors 7/1/2022 Approved CAMERON CHABAN
Structural Steel Frame 7/1/2022 Approved CAMERON CHABAN
Special/Order Compliance 12/8/2022 Not Ready for Inspection CAMERON CHABAN
Special/Order Compliance 6/7/2023 Conditional Approval STEVEN LEVITT
Special/Order Compliance 12/5/2023 Partial Inspection CAMERON CHABAN
Special/Order Compliance 5/23/2024 Approved STEVEN LEVITT
Final 6/18/2024 OK to Issue CofO CAMERON CHABAN