6134 N GLADE AVE 91367
Certificate Information: 6134 N GLADE AVE 91367
- Application / Permit
- 20014-10000-00085
- Plan Check / Job No.
- B20LA00421
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (8) Automobile Sales - new
- Work Description
- ADDITION AND TENANT IMPROVEMENTS OF AN EXISTING CAR DEALERSHIP BUILDING. NEW REPAIR SERVICE STATION WITH ROOF DECK PARKING FOR INVENTORY CARS. NEW FACADE IMPROVEMENTS AND INTERIOR LAYOUT MODIFICATIONS TO PART OF EXISTING BUILDING. JAGUAR/LAND ROVER DEALERSHIP.
- Permit Issued
- Issued on 3/5/2021
- Issuing Office
- Current Status
- CofO Issued on 6/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 3/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2020 | JOE VO |
| Corrections Issued | 3/17/2020 | JOE VO |
| Quality Review Completed | 3/18/2020 | KEN GILL |
| Applicant returned to address corrections | 6/23/2020 | JOE VO |
| Applicant returned to address corrections | 6/29/2020 | JOE VO |
| Applicant returned to address corrections | 7/6/2020 | JOE VO |
| Applicant returned to address corrections | 8/19/2020 | JOE VO |
| Applicant returned to address corrections | 12/17/2020 | JOE VO |
| Applicant returned to address corrections | 12/21/2020 | JOE VO |
| Applicant returned to address corrections | 1/7/2021 | JOE VO |
| Green Plans Picked Up | 1/11/2021 | APPLICANT |
| Applicant returned to address corrections | 2/23/2021 | JOE VO |
| Plan Check Approved | 3/2/2021 | JOE VO |
| Issued | 3/5/2021 | APPLICANT |
| Building Plans Picked Up | 3/11/2021 | APPLICANT |
| TCO Issued (Expire Date: 07-04-2023) | 1/5/2023 | JEFFREY DURAN |
| TCO Issued (Expire Date: 01-03-2024) | 7/7/2023 | JEFFREY DURAN |
| TCO Issued (Expire Date: 06-18-2024) | 12/21/2023 | JEFFREY DURAN |
| CofO in Progress | 6/18/2024 | CAMERON CHABAN |
| Permit Finaled | 6/20/2024 | RICKEY JACKSON |
| CofO Issued | 6/20/2024 | RICKEY JACKSON |
| Permit Finaled | 6/20/2024 | RICKEY JACKSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/16/2020 | GABRIEL ROBLES |
| Driveway location | Cleared | 7/1/2020 | COLLINS ALLAN |
| Address approval | Cleared | 7/9/2020 | HOWARD COOPER |
| Automotive Use | Cleared | 10/28/2020 | RICHARD REASER |
| Automotive Use | Cleared | 10/28/2020 | RICHARD REASER |
| CPC | Cleared | 10/28/2020 | RICHARD REASER |
| Comm Cor/Mini-Mall | Cleared | 10/28/2020 | RICHARD REASER |
| Comm Cor/Mini-Mall | Cleared | 10/28/2020 | RICHARD REASER |
| Comm Cor/Mini-Mall | Cleared | 10/28/2020 | RICHARD REASER |
| Prkng lot landscape/Water mgmt | Cleared | 10/28/2020 | RICHARD REASER |
| ZA Case | Cleared | 10/28/2020 | RICHARD REASER |
| ZA Case | Cleared | 10/28/2020 | RICHARD REASER |
| DAS Clearance | Cleared | 12/22/2020 | SHINE LIN |
| Green Code | Cleared | 1/8/2021 | VIVIAN LAO |
| Hydrant and Access approval | Cleared | 1/19/2021 | KURT CORRAL |
| Specific Plan | Cleared | 1/28/2021 | RICHARD REASER |
| ZI | Cleared | 1/28/2021 | RICHARD REASER |
| Low Impact Development | Cleared | 2/11/2021 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 3/1/2021 | MARKOS PEREZ-BRAN |
Contact Information
| Architect | Petruzzi,, Peter; Lic. No.: C18480 | 1165 FRANCISCO ST #7 SAN FRANCISCO, CA 94109 |
| Contractor | Pacific West Builders Inc; Lic. No.: 752705-B | 1197 LOS ANGELES AVE STE C 166 SIMI VALLEY, CA 93065 |
| Engineer | Nangia,, Robert Vivak; Lic. No.: S5400 | 7423 HOLLOW RIDGE DR HOUSTON, TX 77095 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/9/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Pre-Inspection | 5/12/2021 | Partial Inspection | CAMERON CHABAN |
| Deputy Reinf. Concrete | 6/9/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 6/11/2021 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 6/14/2021 | Corrections Issued | DANIEL VARNUM |
| Piling/Pier/Caisson | 6/15/2021 | Partial Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 6/16/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 6/16/2021 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 6/16/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 6/21/2021 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 6/30/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 7/1/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 7/7/2021 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 7/7/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 7/8/2021 | Conditional Approval | CAMERON CHABAN |
| Green Building Rough | 7/13/2021 | Partial Inspection | CAMERON CHABAN |
| Structural Steel Frame | 7/13/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 7/14/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 7/15/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 7/16/2021 | Conditional Approval | CAMERON CHABAN |
| Green Building Rough | 7/16/2021 | Partial Inspection | CAMERON CHABAN |
| Structural Steel Frame | 7/16/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 7/23/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 7/29/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 7/30/2021 | Conditional Approval | CAMERON CHABAN |
| Structural Steel Frame | 7/30/2021 | Not Ready for Inspection | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/2/2021 | Conditional Approval | CAMERON CHABAN |
| Masonry Wall/Backfill | 8/2/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/3/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/4/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/5/2021 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 8/5/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/9/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/10/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/11/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/12/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 8/13/2021 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 8/13/2021 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 8/16/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 8/17/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Reinf. Masonry | 8/18/2021 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 8/18/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/19/2021 | Conditional Approval | CAMERON CHABAN |
| Excavation/Setback/Form/Re-Bar | 8/19/2021 | Partial Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 8/19/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 8/20/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/20/2021 | Conditional Approval | CAMERON CHABAN |
| Masonry Wall/Backfill | 8/20/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/23/2021 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 8/23/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 8/24/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/24/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/25/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/26/2021 | Conditional Approval | CAMERON CHABAN |
| Masonry Wall/Backfill | 8/26/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Masonry | 8/27/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 8/30/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 9/8/2021 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 9/8/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 9/9/2021 | Conditional Approval | CAMERON CHABAN |
| Excavation/Setback/Form/Re-Bar | 9/13/2021 | Not Ready for Inspection | CAMERON CHABAN |
| Excavation/Setback/Form/Re-Bar | 9/17/2021 | Partial Approval | PAUL DAVIDSON |
| Masonry Wall/Backfill | 9/21/2021 | Partial Approval | DANIEL VARNUM |
| Deputy Reinf. Masonry | 9/22/2021 | Conditional Approval | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 9/23/2021 | Partial Approval | KENNETH ROBERTS |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Partial Approval | DANIEL VARNUM |
| Green Building Rough | 10/6/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Pre-Stress Concrete | 10/8/2021 | Conditional Approval | JEFFREY DURAN |
| Masonry Wall/Backfill | 10/8/2021 | Partial Approval | DANIEL VARNUM |
| Special/Order Compliance | 10/8/2021 | No Access for Inspection | DANIEL VARNUM |
| Deputy Pre-Stress Concrete | 10/12/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Pre-Stress Concrete | 10/13/2021 | Conditional Approval | JEFFREY DURAN |
| Green Building Rough | 10/13/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Structural Steel Frame | 10/13/2021 | Partial Approval | DANIEL VARNUM |
| Deputy Pre-Stress Concrete | 10/14/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Pre-Stress Concrete | 10/15/2021 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 11/1/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Shotcrete | 11/2/2021 | Conditional Approval | KENNETH ROBERTS |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Partial Approval | KENNETH ROBERTS |
| Deputy Shotcrete | 11/3/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Shotcrete | 11/4/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Shotcrete | 11/5/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Pre-Stress Concrete | 11/10/2021 | Conditional Approval | JEFFREY DURAN |
| Light Gage Steel Frame | 11/15/2021 | Partial Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 11/19/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 11/24/2021 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 12/2/2021 | Partial Approval | CAMERON CHABAN |
| Green Building Rough | 12/2/2021 | Approved | CAMERON CHABAN |
| Insulation | 12/2/2021 | Partial Approval | CAMERON CHABAN |
| Insulation | 12/7/2021 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 12/8/2021 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 12/10/2021 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 12/13/2021 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 12/13/2021 | Conditional Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 12/20/2021 | Conditional Approval | CAMERON CHABAN |
| Insulation | 12/21/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 12/23/2021 | Not Ready for Inspection | CAMERON CHABAN |
| Insulation | 12/23/2021 | Approved | CAMERON CHABAN |
| Footing/Foundation/Slab | 12/28/2021 | Conditional Approval | CAMERON CHABAN |
| Masonry Wall/Backfill | 12/29/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 1/12/2022 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 1/31/2022 | Conditional Approval | CAMERON CHABAN |
| T-Bar Ceiling | 1/31/2022 | Not Ready for Inspection | CAMERON CHABAN |
| T-Bar Ceiling | 2/1/2022 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 2/4/2022 | Partial Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 2/14/2022 | Approved | CAMERON CHABAN |
| Interior/Exterior Lathing | 3/8/2022 | Partial Approval | CAMERON CHABAN |
| T-Bar Ceiling | 3/22/2022 | Approved | CAMERON CHABAN |
| Deputy Drilled-In Anchors | 4/15/2022 | Conditional Approval | CAMERON CHABAN |
| Green Building Final | 6/24/2022 | Approved | CAMERON CHABAN |
| Drywall Nailing | 7/1/2022 | Approved | CAMERON CHABAN |
| Final | 7/1/2022 | Partial Inspection | CAMERON CHABAN |
| Footing/Foundation/Slab | 7/1/2022 | Approved | CAMERON CHABAN |
| Reinforced Concrete Frame | 7/1/2022 | Approved | CAMERON CHABAN |
| Reinforced Masonry Frame | 7/1/2022 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Approved | CAMERON CHABAN |
| Smoke Detectors | 7/1/2022 | Approved | CAMERON CHABAN |
| Structural Steel Frame | 7/1/2022 | Approved | CAMERON CHABAN |
| Special/Order Compliance | 12/8/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Special/Order Compliance | 6/7/2023 | Conditional Approval | STEVEN LEVITT |
| Special/Order Compliance | 12/5/2023 | Partial Inspection | CAMERON CHABAN |
| Special/Order Compliance | 5/23/2024 | Approved | STEVEN LEVITT |
| Final | 6/18/2024 | OK to Issue CofO | CAMERON CHABAN |