6459 W WYNKOOP ST 90045
Certificate Information: 6459 W WYNKOOP ST 90045
- Application / Permit
- 20014-10000-00081
- Plan Check / Job No.
- B20LA00412
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 1-STORY 1 CAR DETACHED GARAGE INTO A (N) ACESSORY DWELLING UNIT PER STATE ORDINANCE 186,481.
- Permit Issued
- Issued on 2/23/2021
- Issuing Office
- Current Status
- CofO Issued on 8/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | SERGIO MUNIZ |
| Corrections Issued | 2/10/2020 | SERGIO MUNIZ |
| Quality Review Completed | 2/13/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 2/20/2020 | APPLICANT |
| Green Plans Picked Up | 6/18/2020 | APPLICANT |
| Applicant returned to address corrections | 7/24/2020 | SERGIO MUNIZ |
| Plan Check Approved | 7/27/2020 | SERGIO MUNIZ |
| No Progress | 12/26/2020 | SERGIO MUNIZ |
| Plan Check Approved | 1/30/2021 | SERGIO MUNIZ |
| Plan Check Approved | 2/23/2021 | ALDO UBAU |
| Issued | 2/23/2021 | APPLICANT |
| CofO in Progress | 8/3/2022 | JESUS RODRIGUEZ |
| Permit Finaled | 8/4/2022 | DANIEL ORRANTE |
| CofO Issued | 8/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 3/12/2020 | ELENA LOPEZ |
| Construction near power lines | Cleared | 3/25/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/25/2020 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 5/29/2020 | VASIL MIHALEV |
| Green Code | Cleared | 6/15/2020 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 6/18/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/2/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 7/24/2020 | SERGIO MUNIZ |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | Manasse Inc; Lic. No.: 607634-B | 29059 RAINTREE LN SAUGUS, CA 91390 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/15/2021 | Partial Approval | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 4/5/2021 | Corrections Issued | PIERRE VEGA |
| Footing/Foundation/Slab | 4/5/2021 | Not Ready for Inspection | PIERRE VEGA |
| Footing/Foundation/Slab | 4/26/2021 | Partial Approval | MATT KELLERMAN |
| Gas Test | 4/26/2021 | Partial Approval | MATT KELLERMAN |
| PLUMBING-Rough | 4/26/2021 | Partial Approval | MATT KELLERMAN |
| PLUMBING-Rough | 5/19/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Underground Mechanical | 5/19/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 7/20/2021 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 7/20/2021 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 7/20/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 7/20/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 7/20/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/20/2021 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 8/16/2021 | Conditional Approval | BRENDAN LOONEY |
| Green Building Rough | 8/16/2021 | Approved | BRENDAN LOONEY |
| Insulation | 8/16/2021 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 8/16/2021 | Partial Approval | BRENDAN LOONEY |
| Insulation | 8/19/2021 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 8/25/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 8/30/2021 | Approved | JOHNNY MIRANDA |
| Shower Pan | 8/30/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/16/2021 | Approved | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 5/4/2022 | Approved | JESUS RODRIGUEZ |
| Final | 5/4/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 5/4/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 5/4/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/7/2022 | Approved | JESUS RODRIGUEZ |
| Final | 7/7/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 7/7/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 7/7/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/7/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Final | 8/2/2022 | OK to Issue CofO | JESUS RODRIGUEZ |
| HVAC-Final | 8/2/2022 | Approved | JESUS RODRIGUEZ |