430 S MCCADDEN PL 90020
Certificate Information: 430 S MCCADDEN PL 90020
- Application / Permit
- 20014-10000-00046
- Plan Check / Job No.
- B20LA00221
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (40'-9"x 15'-4") AND CONVERT OF (E) 2- CAR GARAGE TO ACCESSORY DWELLING UNIT WITH NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/20/2020
- Issuing Office
- Current Status
- CofO Issued on 3/31/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | TROY DEGUZMAN |
| Corrections Issued | 2/25/2020 | TROY DEGUZMAN |
| Quality Review Completed | 2/25/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/4/2020 | APPLICANT |
| Applicant returned to address corrections | 4/16/2020 | TROY DEGUZMAN |
| Green Plans Picked Up | 6/25/2020 | APPLICANT |
| Plan Check Approved | 7/8/2020 | TROY DEGUZMAN |
| Issued | 8/20/2020 | APPLICANT |
| CofO in Progress | 3/19/2021 | JOSEPH MCGARRY |
| Permit Finaled | 3/31/2021 | DEROLD HAUFF |
| CofO Issued | 3/31/2021 | DEROLD HAUFF |
| Permit Finaled | 3/31/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 3/10/2020 | SUKI GERSHENHORN |
| CPC | Cleared | 3/10/2020 | SUKI GERSHENHORN |
| CPC | Cleared | 3/10/2020 | SUKI GERSHENHORN |
| HPOZ | Cleared | 3/10/2020 | SUKI GERSHENHORN |
| ZI | Cleared | 3/10/2020 | SUKI GERSHENHORN |
| Address approval | Cleared | 3/12/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 4/16/2020 | TROY DEGUZMAN |
| Hydrant and Access approval | Cleared | 4/24/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 4/29/2020 | JUAN ASHTON |
| Construction near power lines | Cleared | 5/2/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/15/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/29/2020 | JUAN ASHTON |
Contact Information
| Architect | Kim,, Steve Chulwon; Lic. No.: C19772 | 2855 W. 7TH ST. #200 LOS ANGELES, CA 90005 |
| Contractor | Apex Construction Solutions Inc; Lic. No.: 1010668-B | 2121 W. IMPERIAL HWY #E468 LA HABRA, CA 90631 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/31/2020 | Partial Approval | ARTHUR SARGSYAN |
| Underground Mechanical | 8/31/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 9/4/2020 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 9/10/2020 | Partial Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 9/10/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Barrier | 9/10/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Rough | 9/10/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Subgrade | 9/10/2020 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 9/15/2020 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 9/15/2020 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 11/24/2020 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2020 | Partial Approval | SCOTT FINNILA |
| Gas Test | 11/24/2020 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 11/24/2020 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 12/10/2020 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 12/10/2020 | Approved | COREY HUPP |
| PLUMBING-Rough | 12/10/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 12/15/2020 | Conditional Approval | JOSEPH MCGARRY |
| Gas Test | 12/15/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 12/15/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 12/15/2020 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/15/2020 | Partial Approval | JOSEPH MCGARRY |
| METHANE-Rough | 12/15/2020 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 12/15/2020 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/18/2020 | Approved | SCOTT FINNILA |
| Insulation | 12/18/2020 | Conditional Approval | SCOTT FINNILA |
| Drywall Nailing | 12/24/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 12/24/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 2/18/2021 | Approved | JOSEPH MCGARRY |
| Final | 2/18/2021 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 2/18/2021 | Approved | JOSEPH MCGARRY |
| Green Building Final | 2/18/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 2/18/2021 | Approved | JOSEPH MCGARRY |
| METHANE-Barrier | 2/18/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 2/18/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/18/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 2/18/2021 | Approved | JOSEPH MCGARRY |
| Final | 2/24/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Gas Test | 2/24/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 3/17/2021 | OK to Issue CofO | JOSEPH MCGARRY |