2521 S PURDUE AVE 90064

Certificate Information: 2521 S PURDUE AVE 90064

Application / Permit
20014-10000-00043
Plan Check / Job No.
B20LA00211
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISITING IRREGULAR SINGLE FAMILY RESIDENCE W/ (E) GARAGE
Permit Issued
Issued on 2/26/2021
Issuing Office
Current Status
CofO Issued on 12/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2020 APPLICANT
Green Plans Picked Up 1/21/2020 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 FERNANDO FLORES
Corrections Issued 2/10/2020 FERNANDO FLORES
Quality Review Completed 2/29/2020 STANLEY RAAP
Plan Check Approved 2/16/2021 FERNANDO FLORES
Issued 2/26/2021 APPLICANT
Building Plans Picked Up 4/21/2021 APPLICANT
CofO in Progress 12/15/2022 ASHLEY THOMPSON
Permit Finaled 12/21/2022 DANIEL ORRANTE
CofO Issued 12/21/2022 DANIEL ORRANTE
Permit Finaled 12/21/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 1/12/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 1/26/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/28/2021 DINAH GARIN
Green Code Cleared 2/5/2021 KHEDER ALRAZAA

Contact Information

Architect Imoto,, Kyle Seiji; Lic. No.: C33852 1919 MARENGO AVENUE      SOUTH PASADENA, CA 91030
Contractor Rafu Construction Company Inc; Lic. No.: 343622-B 552 JADE TREE DR      MONTEREY PARK, CA 91754

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/14/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 5/24/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 7/1/2021 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 7/6/2021 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/6/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 No Access for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/31/2021 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/3/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/12/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/12/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 10/12/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 10/12/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/18/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 10/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
MERV13>=Rough 10/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 10/18/2021 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 10/21/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/22/2021 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Corrections Issued JOHNNY MIRANDA
Green Building Rough 10/22/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 10/22/2021 Not Ready for Inspection JOHNNY MIRANDA
MERV13>=Rough 10/22/2021 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 10/22/2021 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 10/26/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/26/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 10/26/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 10/26/2021 Approved OGANES TARAKHCHYAN
MERV13>=Rough 10/26/2021 Approved OGANES TARAKHCHYAN
Wood Frame 10/26/2021 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/29/2021 Approved OGANES TARAKHCHYAN
Insulation 11/2/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/2/2021 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 11/3/2021 Partial Approval RYAN SALAZAR
Drywall Nailing 11/9/2021 Approved OGANES TARAKHCHYAN
Final 3/16/2022 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 3/16/2022 Approved OGANES TARAKHCHYAN
Green Building Final 3/16/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 3/16/2022 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Final 3/16/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/16/2022 SGSOV Approved OGANES TARAKHCHYAN
Final 4/1/2022 Corrections Issued OGANES TARAKHCHYAN
Smoke Detectors 4/1/2022 Approved OGANES TARAKHCHYAN
MERV13>=Final 5/26/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 11/21/2022 No Access for Inspection ASHLEY THOMPSON
Final 11/21/2022 No Access for Inspection ASHLEY THOMPSON
HVAC-Final 11/21/2022 No Access for Inspection ASHLEY THOMPSON
PLUMBING-Final 11/21/2022 No Access for Inspection ASHLEY THOMPSON
Final 12/14/2022 Conditional Approval ASHLEY THOMPSON