630 E 74TH ST 90001

Certificate Information: 630 E 74TH ST 90001

Application / Permit
20010-70000-00989
Plan Check / Job No.
B20SL00484
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADU ADDITION TO EXISTING GARAGE PER ORDINANCE 186481
Permit Issued
Issued on 1/25/2021
Issuing Office
Current Status
CofO Issued on 9/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2020 APPLICANT
Assigned to Plan Check Engineer 3/26/2020 STARR CHEN
Corrections Issued 4/8/2020 STARR CHEN
Quality Review Completed 4/10/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 10/1/2020 APPLICANT
Applicant returned to address corrections 12/10/2020 STARR CHEN
Plan Check Approved 1/13/2021 STARR CHEN
Plan Check Approved 1/25/2021 STARR CHEN
Issued 1/25/2021 APPLICANT
Building Plans Picked Up 1/27/2021 APPLICANT
CofO in Progress 8/21/2021 ALEJANDRO DE ARTOLA
CofO Issued 9/2/2021 DEROLD HAUFF
Permit Finaled 9/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 7/29/2020 DALE WILLIAMS
Address approval Cleared 7/30/2020 JEANIE LAM
Sewer availability Cleared 7/30/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/4/2020 JEANIE LAM
Community Plan Implem. Overlay Cleared 8/11/2020 JOHN KIM
Community Plan Implem. Overlay Cleared 8/31/2020 RIDWAN HARDY
Green Code Cleared 9/1/2020 KHEDER ALRAZAA
Hydrant and Access approval Cleared 9/4/2020 KURT CORRAL
Low Impact Development Cleared 10/22/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/27/2020 CELINA MORENO
Community Plan Implem. Overlay Cleared 11/17/2020 HELEN JADALI

Contact Information

Contractor De La Rosa Construction; Lic. No.: 855010-B 3684 E PERCY ST      LOS ANGELES, CA 90023
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/28/2021 Partial Inspection DAVID FEILER
Underground Mechanical 1/28/2021 Partial Approval DAVID FEILER
Footing/Foundation/Slab 2/1/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 2/18/2021 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 2/18/2021 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/18/2021 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 2/18/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/4/2021 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/4/2021 Approved DAVID FEILER
HVAC-Rough 3/4/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 3/9/2021 Approved DAVID FEILER
Green Building Rough 3/9/2021 Approved DAVID FEILER
Rough-Elec/Plmb/HVAC 3/9/2021 Approved DAVID FEILER
Insulation 3/11/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 3/11/2021 Approved ROBERT MCDOWELL
Drywall Nailing 3/19/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/19/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/30/2021 Approved DAVID FEILER
Underground Mechanical 4/7/2021 Approved EUGENE CASSIDY
Final 7/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 7/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/23/2021 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 7/23/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/5/2021 Approved ALEJANDRO DE ARTOLA
Final 8/5/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 8/5/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 8/5/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 8/5/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/5/2021 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/5/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Final 8/20/2021 OK to Issue CofO ALEJANDRO DE ARTOLA