5077 W BANGOR ST 90016

Certificate Information: 5077 W BANGOR ST 90016

Application / Permit
20010-70000-00945
Plan Check / Job No.
B20SL00466
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story detached 4-car garage, storage and ADU building. ADU on second floor. Detached ADU per ordinance 186,481.
Permit Issued
Issued on 6/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/27/2020 AMIR DANAI
Corrections Issued 4/2/2020 AMIR DANAI
Quality Review Completed 4/15/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 4/24/2020 APPLICANT
Green Plans Picked Up 5/15/2020 APPLICANT
Applicant returned to address corrections 9/3/2021 HELEN NGUYEN
Applicant returned to address corrections 10/7/2021 HELEN NGUYEN
Applicant returned to address corrections 1/13/2022 HELEN NGUYEN
Plan Check Approved 4/7/2022 HELEN NGUYEN
Issued 6/29/2022 APPLICANT
CofO in Progress 3/6/2024 JUSTIN HAWLEY
CofO Issued 3/8/2024 DEROLD HAUFF
Permit Finaled 3/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/2/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/2/2020 CECILIO NAVARRO
Sewer availability Cleared 10/2/2020 CECILIO NAVARRO
Low Impact Development Cleared 3/9/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/9/2021 ROSA SILVA
Hydrant and Access approval Cleared 4/25/2021 ROBERT DUFF
Tenant Habitability Plan Cleared 8/5/2021 ISMAEL HERNANDEZ
Green Code Cleared 4/7/2022 VIVIAN LAO

Contact Information

Contractor Bejarano'S Construction; Lic. No.: 711144-B 3258 OCOTILLO DR      LAUGHLIN, NV 89029
Engineer Gonzalez,, Felix Bolivar; Lic. No.: C64738 14619 CATALINA AVE      GARDENA, CA 90247

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/18/2022 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 11/7/2022 Approved STUART CHAPMAN
Deputy Reinf. Concrete 11/10/2022 Conditional Approval STUART CHAPMAN
Drywall Nailing 12/5/2022 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Conditional Approval BRENDAN MORELLI
Deputy Drilled-In Anchors 4/5/2023 Approved CALEB MEISTER
Deputy Wood Construction 4/7/2023 Conditional Approval CALEB MEISTER
BUILDING-Rough-Frame 4/17/2023 No Access for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 4/17/2023 No Access for Inspection MICHAEL LEWIS
Green Building Rough 4/17/2023 No Access for Inspection MICHAEL LEWIS
HVAC-Rough 4/17/2023 No Access for Inspection MICHAEL LEWIS
MERV13>=Rough 4/17/2023 No Access for Inspection MICHAEL LEWIS
Verify Sprinkler Sign Off 4/17/2023 No Access for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 4/24/2023 Conditional Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Corrections Issued SCOTT FINNILA
HVAC-Rough 4/24/2023 Approved SCOTT FINNILA
PLUMBING-Rough 4/24/2023 Approved SCOTT FINNILA
Deputy Wood Construction 4/27/2023 Conditional Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Not Ready for Inspection CALEB MEISTER
Wood Frame 5/8/2023 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 6/7/2023 Approved CALEB MEISTER
Green Building Rough 6/7/2023 Approved CALEB MEISTER
MERV13>=Rough 6/7/2023 Approved CALEB MEISTER
Verify Sprinkler Sign Off 6/7/2023 Approved CALEB MEISTER
Insulation 6/16/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/16/2023 Partial Approval STUART CHAPMAN
Drywall Nailing 7/3/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 7/27/2023 Approved CALEB MEISTER
Gas Test 11/1/2023 Approved DAVID FEILER
Sewer 11/1/2023 Approved DAVID FEILER
Underground Mechanical 11/1/2023 Partial Approval DAVID FEILER
ELECTRICAL-Final 1/9/2024 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 2/21/2024 Not Ready for Inspection JUSTIN HAWLEY
Final 2/21/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 2/21/2024 Approved JUSTIN HAWLEY
HVAC-Final 2/21/2024 Approved JUSTIN HAWLEY
MERV13>=Final 2/21/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 2/21/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Not Ready JUSTIN HAWLEY
Service/Power Release 2/21/2024 Not Ready for Inspection JUSTIN HAWLEY
Smoke Detectors 2/21/2024 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Final 2/28/2024 Approved JUSTIN HAWLEY
Final 2/28/2024 Corrections Issued JUSTIN HAWLEY
Service/Power Release 2/28/2024 Approved JUSTIN HAWLEY
Final 3/5/2024 OK to Issue CofO JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 3/5/2024 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 3/5/2024 Approved JUSTIN HAWLEY