5077 W BANGOR ST 90016
Certificate Information: 5077 W BANGOR ST 90016
- Application / Permit
- 20010-70000-00945
- Plan Check / Job No.
- B20SL00466
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story detached 4-car garage, storage and ADU building. ADU on second floor. Detached ADU per ordinance 186,481.
- Permit Issued
- Issued on 6/29/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2020 | AMIR DANAI |
| Corrections Issued | 4/2/2020 | AMIR DANAI |
| Quality Review Completed | 4/15/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 4/24/2020 | APPLICANT |
| Green Plans Picked Up | 5/15/2020 | APPLICANT |
| Applicant returned to address corrections | 9/3/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/7/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 1/13/2022 | HELEN NGUYEN |
| Plan Check Approved | 4/7/2022 | HELEN NGUYEN |
| Issued | 6/29/2022 | APPLICANT |
| CofO in Progress | 3/6/2024 | JUSTIN HAWLEY |
| CofO Issued | 3/8/2024 | DEROLD HAUFF |
| Permit Finaled | 3/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/2/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 3/9/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/9/2021 | ROSA SILVA |
| Hydrant and Access approval | Cleared | 4/25/2021 | ROBERT DUFF |
| Tenant Habitability Plan | Cleared | 8/5/2021 | ISMAEL HERNANDEZ |
| Green Code | Cleared | 4/7/2022 | VIVIAN LAO |
Contact Information
| Contractor | Bejarano'S Construction; Lic. No.: 711144-B | 3258 OCOTILLO DR LAUGHLIN, NV 89029 |
| Engineer | Gonzalez,, Felix Bolivar; Lic. No.: C64738 | 14619 CATALINA AVE GARDENA, CA 90247 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/18/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/7/2022 | Approved | STUART CHAPMAN |
| Deputy Reinf. Concrete | 11/10/2022 | Conditional Approval | STUART CHAPMAN |
| Drywall Nailing | 12/5/2022 | Not Ready for Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Conditional Approval | BRENDAN MORELLI |
| Deputy Drilled-In Anchors | 4/5/2023 | Approved | CALEB MEISTER |
| Deputy Wood Construction | 4/7/2023 | Conditional Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 4/17/2023 | No Access for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/17/2023 | No Access for Inspection | MICHAEL LEWIS |
| Green Building Rough | 4/17/2023 | No Access for Inspection | MICHAEL LEWIS |
| HVAC-Rough | 4/17/2023 | No Access for Inspection | MICHAEL LEWIS |
| MERV13>=Rough | 4/17/2023 | No Access for Inspection | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 4/17/2023 | No Access for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/24/2023 | Conditional Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 4/24/2023 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 4/24/2023 | Approved | SCOTT FINNILA |
| Deputy Wood Construction | 4/27/2023 | Conditional Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Wood Frame | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 6/7/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 6/7/2023 | Approved | CALEB MEISTER |
| MERV13>=Rough | 6/7/2023 | Approved | CALEB MEISTER |
| Verify Sprinkler Sign Off | 6/7/2023 | Approved | CALEB MEISTER |
| Insulation | 6/16/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/16/2023 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 7/3/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 7/27/2023 | Approved | CALEB MEISTER |
| Gas Test | 11/1/2023 | Approved | DAVID FEILER |
| Sewer | 11/1/2023 | Approved | DAVID FEILER |
| Underground Mechanical | 11/1/2023 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Final | 1/9/2024 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 2/21/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 2/21/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 2/21/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 2/21/2024 | Approved | JUSTIN HAWLEY |
| MERV13>=Final | 2/21/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 2/21/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Not Ready | JUSTIN HAWLEY |
| Service/Power Release | 2/21/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 2/21/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Final | 2/28/2024 | Approved | JUSTIN HAWLEY |
| Final | 2/28/2024 | Corrections Issued | JUSTIN HAWLEY |
| Service/Power Release | 2/28/2024 | Approved | JUSTIN HAWLEY |
| Final | 3/5/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 3/5/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 3/5/2024 | Approved | JUSTIN HAWLEY |