1414-1414 1/2 E 23RD ST 90011
Certificate Information: 1414-1414 1/2 E 23RD ST 90011
- Application / Permit
- 20010-70000-00940
- Plan Check / Job No.
- B20SL00464
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 101'X30' 2-STORY DUPLEX WITH TWO 2-CAR ATTACHED GARAGES.
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Current Status
- CofO Issued on 7/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 4/14/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 4/28/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 5/4/2020 | APPLICANT |
| Green Plans Picked Up | 5/14/2020 | APPLICANT |
| Applicant returned to address corrections | 7/6/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 7/15/2020 | CHUNG-WEN CHUANG |
| Issued | 10/9/2020 | APPLICANT |
| CofO in Progress | 7/22/2021 | ELMER BLAND |
| Permit Finaled | 7/28/2021 | DEROLD HAUFF |
| CofO Issued | 7/28/2021 | DEROLD HAUFF |
| Permit Finaled | 7/28/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/12/2020 | CELINA MORENO |
| Permit | Cleared | 5/12/2020 | CELINA MORENO |
| Green Code | Cleared | 5/13/2020 | DONALD CRICHLOW |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2020 | CELINA MORENO |
| Sewer availability | Cleared | 5/19/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 5/22/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 6/9/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/12/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/28/2020 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 10/28/2020 | Partial Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 11/5/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 11/5/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 12/22/2020 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 12/22/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 12/22/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Rough | 12/22/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 12/22/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 12/22/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 12/28/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 12/28/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 1/4/2021 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 1/4/2021 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Drywall Nailing | 1/7/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 1/7/2021 | Partial Approval | JOSEPH MCGARRY |
| Gas Test | 2/16/2021 | Approved | ROBERT MCDOWELL |
| Sewer | 2/16/2021 | Approved | ROBERT MCDOWELL |
| Verify Rec and Parks Fee Memo | 2/16/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 4/15/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 4/15/2021 | Approved | ROBERT MCDOWELL |
| Final | 4/15/2021 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Final | 4/15/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 4/15/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 4/15/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 4/15/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 4/15/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 4/15/2021 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 4/15/2021 | Approved | ROBERT MCDOWELL |
| Final | 7/21/2021 | OK to Issue CofO | ELMER BLAND |