1613 E 113TH ST 90059

Certificate Information: 1613 E 113TH ST 90059

Application / Permit
20010-70000-00926
Plan Check / Job No.
B20SL00458
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE. TYPE VB FULLY SPRINKLERED.
Permit Issued
Issued on 10/28/2020
Issuing Office
Current Status
CofO Issued on 9/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2020 APPLICANT
Assigned to Plan Check Engineer 3/23/2020 LUKE GONZALES
Corrections Issued 3/25/2020 RICARDO RAMIREZ
Quality Review Completed 3/31/2020 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 4/17/2020 APPLICANT
Applicant returned to address corrections 6/17/2020 RICARDO RAMIREZ
Green Plans Picked Up 7/17/2020 APPLICANT
Plan Check Approved 9/30/2020 RICARDO RAMIREZ
Issued 10/28/2020 APPLICANT
CofO in Progress 8/30/2021 EUGENE CASSIDY
Permit Finaled 9/11/2021 DEROLD HAUFF
CofO Issued 9/11/2021 DEROLD HAUFF
Permit Finaled 9/11/2021 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 5/18/2020 DANIEL CORONADO
Address approval Cleared 5/22/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 5/29/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/29/2020 HISASHI KOBAYAKAWA
ZA Case Cleared 6/23/2020 DANIEL CORONADO
ZA Case Cleared 6/23/2020 DANIEL CORONADO
Green Code Cleared 7/17/2020 VIVIAN LAO
Hydrant and Access approval Cleared 8/17/2020 MATTHEW CRAIG
Low Impact Development Cleared 9/4/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/22/2020 CELINA MORENO

Contact Information

Contractor Top You Llc; Lic. No.: 1064383-B 6125 WASHINGTON BLVD #300      CULVER CITY, CA 90232

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/10/2020 Partial Approval EUGENE CASSIDY
Underground Mechanical 11/10/2020 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 11/17/2020 Approved EUGENE CASSIDY
Footing/Foundation/Slab 11/17/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/16/2020 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 12/30/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 12/30/2020 Corrections Issued EUGENE CASSIDY
Wood Frame 12/30/2020 Partial Approval EUGENE CASSIDY
HVAC-Rough 1/7/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 1/7/2021 Approved EUGENE CASSIDY
Wood Frame 1/7/2021 Partial Approval EUGENE CASSIDY
HVAC-Rough 1/12/2021 Partial Approval EUGENE CASSIDY
Insulation 1/12/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 1/12/2021 Approved EUGENE CASSIDY
Drywall Nailing 1/21/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 1/21/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 1/21/2021 Approved EUGENE CASSIDY
Wood Frame 1/21/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 7/28/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/28/2021 Not Ready for Inspection EUGENE CASSIDY
Final 7/28/2021 Corrections Issued EUGENE CASSIDY
Gas Test 7/28/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 7/28/2021 Approved EUGENE CASSIDY
Green Building Rough 7/28/2021 Approved EUGENE CASSIDY
HVAC-Final 7/28/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 7/28/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/28/2021 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 7/28/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 7/28/2021 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 7/28/2021 Approved EUGENE CASSIDY
Final 8/11/2021 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/11/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 8/11/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 8/11/2021 Approved EUGENE CASSIDY
Final 8/23/2021 Corrections Issued EUGENE CASSIDY
Service/Power Release 8/23/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 8/27/2021 Approved EUGENE CASSIDY
Final 8/27/2021 OK to Issue CofO EUGENE CASSIDY
Gas Test 8/27/2021 Approved EUGENE CASSIDY
HVAC-Final 8/27/2021 Approved EUGENE CASSIDY
PLUMBING-Final 8/27/2021 Approved EUGENE CASSIDY
Service/Power Release 8/27/2021 Approved EUGENE CASSIDY