931-931 1/2 S LORENA ST 90023
Certificate Information: 931-931 1/2 S LORENA ST 90023
- Application / Permit
- 20010-70000-00899
- Plan Check / Job No.
- B20SL00436
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED GARAGE AT REAR
- Permit Issued
- Issued on 8/20/2020
- Issuing Office
- Current Status
- CofO Issued on 9/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | JOHNNY WU |
| Corrections Issued | 4/1/2020 | JOHNNY WU |
| Quality Review Completed | 4/2/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/14/2020 | APPLICANT |
| Green Plans Picked Up | 4/22/2020 | APPLICANT |
| Applicant returned to address corrections | 7/29/2020 | JOHNNY WU |
| Applicant returned to address corrections | 8/19/2020 | JOHNNY WU |
| Plan Check Approved | 8/19/2020 | JOHNNY WU |
| Issued | 8/20/2020 | APPLICANT |
| CofO in Progress | 9/28/2021 | ROBERT VORHIS |
| CofO in Progress | 9/28/2021 | ROBERT VORHIS |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
| CofO Issued | 9/29/2021 | DEROLD HAUFF |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2020 | WALLIE JONG |
| Address approval | Cleared | 4/15/2020 | WALLIE JONG |
| Green Code | Cleared | 4/21/2020 | JOHNNY WU |
| Green Code | Cleared | 4/21/2020 | KHEDER ALRAZAA |
| Trees in Parkway | Cleared | 5/4/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 5/7/2020 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2020 | WALLIE JONG |
| Permit | Cleared | 5/27/2020 | WALLIE JONG |
| Sewer availability | Cleared | 5/27/2020 | WALLIE JONG |
| ZI | Cleared | 6/1/2020 | DANIEL CORONADO |
| ZI | Cleared | 6/3/2020 | DANIEL CORONADO |
| Low Impact Development | Cleared | 6/30/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/7/2020 | EMIL KYUPELYAN |
| GPI Written Notices | Cleared | 7/29/2020 | JOHNNY WU |
| Grading Pre-Inspection | Cleared | 7/29/2020 | JOHNNY WU |
| Highway dedication | Cleared | 8/12/2020 | WALLIE JONG |
Contact Information
| Contractor | Rios William A; Lic. No.: 866335-B | P O BOX 1061 DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/16/2020 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/23/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2020 | Partial Approval | ROBERT VORHIS |
| Deputy Wood Construction | 12/2/2020 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2020 | Partial Approval | ROBERT VORHIS |
| PLUMBING-Rough | 12/7/2020 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 12/14/2020 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 12/14/2020 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 12/14/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/18/2020 | Not Ready for Inspection | ROBERT VORHIS |
| HVAC-Rough | 12/18/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Wood Frame | 12/18/2020 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 12/24/2020 | Approved | ROBERT VORHIS |
| HVAC-Rough | 12/24/2020 | Corrections Issued | ROBERT VORHIS |
| HVAC-Rough | 12/30/2020 | Approved | ROBERT VORHIS |
| Wood Frame | 12/30/2020 | Not Ready for Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 1/5/2021 | Partial Inspection | ROBERT VORHIS |
| Green Building Rough | 1/5/2021 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 1/5/2021 | Partial Approval | ROBERT VORHIS |
| MERV13>=Rough | 1/5/2021 | Approved | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 1/5/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Interior/Exterior Lathing | 1/6/2021 | Partial Approval | RUBEN SALAS |
| BUILDING-Rough-Frame | 1/7/2021 | Approved | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 1/7/2021 | Approved | ROBERT VORHIS |
| Insulation | 1/11/2021 | Corrections Issued | ROBERT VORHIS |
| Insulation | 1/14/2021 | Approved | ROBERT VORHIS |
| Drywall Nailing | 1/22/2021 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 1/27/2021 | Approved | ROBERT VORHIS |
| Final | 4/13/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 4/13/2021 | Not Ready for Inspection | STUART CHAPMAN |
| MERV13>=Final | 4/13/2021 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 4/13/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 4/13/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 4/16/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 4/16/2021 | Approved | SCOTT FINNILA |
| HVAC-Final | 4/16/2021 | Approved | SCOTT FINNILA |
| MERV13>=Final | 4/16/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 4/16/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 4/22/2021 | Approved | STUART CHAPMAN |
| Final | 4/22/2021 | Conditional Approval | STUART CHAPMAN |
| Service/Power Release | 4/22/2021 | Approved | STUART CHAPMAN |
| Final | 5/26/2021 | Corrections Issued | STUART CHAPMAN |
| Final | 9/28/2021 | OK to Issue CofO | ROBERT VORHIS |