1219 W 75TH ST 90044

Certificate Information: 1219 W 75TH ST 90044

Application / Permit
20010-70000-00849
Plan Check / Job No.
B20SL00415
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADU WITH ATTACHED GARAGE
Permit Issued
Issued on 3/24/2021
Issuing Office
Current Status
Issued on 3/24/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/20/2020 ADAM HEGAZI
Corrections Issued 3/23/2020 ADAM HEGAZI
Quality Review Completed 3/24/2020 STANLEY RAAP
Green Plans Picked Up 4/24/2020 APPLICANT
Plan Check Approved 2/22/2021 ADAM HEGAZI
Issued 3/24/2021 APPLICANT
Building Plans Picked Up 3/25/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/6/2020 ELAINE LEI
Sewer availability Cleared 5/29/2020 ELAINE LEI
Construction near power lines Cleared 6/10/2020 RIDWAN HARDY
Hydrant and Access approval Cleared 6/30/2020 KURT CORRAL
Low Impact Development Cleared 7/22/2020 ANDRES COVARRUBIAS
Eng Process Fee Ord 176,300 Cleared 10/14/2020 ELAINE LEI
Roof/Waste drainage to street Cleared 12/22/2020 ROSA SILVA
Green Code Cleared 1/21/2021 ADAM HEGAZI

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/10/2022 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 2/14/2022 Approved HORACE FULTZ
Footing/Foundation/Slab 2/14/2022 Approved HORACE FULTZ
Wood Frame 11/8/2024 Corrections Issued MICHAEL LEWIS
Notice of Violation 8/18/2025 Not Required JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Conditional Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 11/14/2025 Partial Inspection JOHN QUINTANILLA
Wood Frame 3/13/2026 Not Ready for Inspection JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 3/17/2026 Partial Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 4/10/2026 No Access for Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 4/13/2026 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 4/29/2026 Corrections Issued JOHN QUINTANILLA
HVAC-Rough 4/29/2026 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 4/29/2026 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 5/5/2026 Approved LUIS CASTRO
ELECTRICAL-Rough 5/5/2026 Approved LUIS CASTRO
Green Building Rough 5/5/2026 Approved LUIS CASTRO
HVAC-Rough 5/5/2026 Approved LUIS CASTRO
PLUMBING-Rough 5/5/2026 Approved LUIS CASTRO
Shower Pan 5/5/2026 Approved LUIS CASTRO
Verify Sprinkler Sign Off 5/5/2026 Approved LUIS CASTRO
Insulation 5/18/2026 Approved JOHN QUINTANILLA