1157 1/2 W 37TH DR 90007
Certificate Information: 1157 1/2 W 37TH DR 90007
- Application / Permit
- 20010-70000-00247
- Plan Check / Job No.
- B20SL00122
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1 STORY ADU PER 12.22 A33 C & D
- Permit Issued
- Issued on 5/3/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | STARR CHEN |
| Corrections Issued | 2/20/2020 | STARR CHEN |
| Quality Review Completed | 2/25/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 2/26/2020 | APPLICANT |
| Green Plans Picked Up | 6/23/2020 | APPLICANT |
| Applicant returned to address corrections | 1/11/2021 | STARR CHEN |
| Applicant returned to address corrections | 3/26/2021 | STARR CHEN |
| Applicant returned to address corrections | 4/9/2021 | STARR CHEN |
| Plan Check Approved | 4/14/2021 | STARR CHEN |
| Issued | 5/3/2021 | APPLICANT |
| CofO in Progress | 12/2/2021 | HORACE FULTZ |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
| CofO Issued | 12/17/2021 | DEROLD HAUFF |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 2/28/2020 | JUAN ASHTON |
| Green Code | Cleared | 3/9/2020 | COLIN LOREDO |
| Green Code | Cleared | 3/9/2020 | STARR CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2020 | PAMELA TENEZA |
| Sewer availability | Cleared | 4/16/2020 | PAMELA TENEZA |
| Community Plan Implem. Overlay | Cleared | 5/7/2020 | OSCAR CASTRO |
| Hydrant and Access approval | Cleared | 6/12/2020 | MATTHEW CRAIG |
| Community Plan Implem. Overlay | Cleared | 6/25/2020 | HELEN JADALI |
| Solar Clearance | Cleared | 7/14/2020 | STARR CHEN |
| Community Plan Implem. Overlay | Cleared | 2/18/2021 | JOHN KIM |
| Community Plan Implem. Overlay | Cleared | 2/24/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/7/2021 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/11/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 6/17/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Pre-Inspection | 6/17/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/29/2021 | Approved | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 7/2/2021 | Partial Approval | RONALD KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 7/9/2021 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 8/9/2021 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 8/9/2021 | Approved | SABAS ALONSO |
| Wood Frame | 8/9/2021 | Approved | SABAS ALONSO |
| Insulation | 8/20/2021 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 8/20/2021 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 8/20/2021 | Partial Approval | SABAS ALONSO |
| Shower Pan | 8/20/2021 | Partial Approval | SABAS ALONSO |
| Insulation | 8/26/2021 | Approved | HORACE FULTZ |
| Drywall Nailing | 9/1/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 9/1/2021 | Approved | SABAS ALONSO |
| Shower Pan | 9/1/2021 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/16/2021 | Approved | SABAS ALONSO |
| Underground Mechanical | 9/29/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/8/2021 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 11/8/2021 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/12/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 11/12/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 11/12/2021 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 11/12/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 11/12/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 11/12/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 11/12/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/18/2021 | Approved | SABAS ALONSO |
| Final | 11/18/2021 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 11/18/2021 | Approved | SABAS ALONSO |
| Smoke Detectors | 11/18/2021 | Approved | SABAS ALONSO |
| Final | 11/24/2021 | OK to Issue CofO | SABAS ALONSO |