2452-2452 1/2 E BOULDER ST 90033
Certificate Information: 2452-2452 1/2 E BOULDER ST 90033
- Application / Permit
- 20010-70000-00210
- Plan Check / Job No.
- B20SL00104
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED 2 CAR GARAGE AT REAR OF LOT
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | LUKE GONZALES |
| Corrections Issued | 2/4/2020 | LUKE GONZALES |
| Quality Review Completed | 2/6/2020 | TEODORO DIAZ RODRIGUEZ |
| Green Plans Picked Up | 6/18/2020 | APPLICANT |
| Applicant returned to address corrections | 6/26/2020 | LUKE GONZALES |
| Plan Check Approved | 4/1/2021 | LUKE GONZALES |
| Issued | 4/15/2021 | APPLICANT |
| Building Plans Picked Up | 4/16/2021 | APPLICANT |
| CofO in Progress | 12/27/2022 | OSVALDO PARAMO |
| CofO in Progress | 12/27/2022 | OSVALDO PARAMO |
| Permit Finaled | 1/19/2023 | DEROLD HAUFF |
| CofO Issued | 1/19/2023 | DEROLD HAUFF |
| Permit Finaled | 1/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/7/2020 | CELINA MORENO |
| Highway dedication | Cleared | 2/7/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 2/13/2020 | EMIL KYUPELYAN |
| Frnt yard landscape/Water mgmt | Cleared | 3/25/2020 | JASON CHAN |
| Green Code | Cleared | 4/1/2020 | DONALD CRICHLOW |
| Grading Pre-Inspection | Cleared | 5/6/2020 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 6/3/2020 | ORVAL HERNANDEZ-MARCI |
| Hydrant and Access approval | Cleared | 6/18/2020 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 6/23/2020 | CECILIO NAVARRO |
| GPI Written Notices | Cleared | 3/24/2021 | LUKE GONZALES |
| Hold | Cleared | 9/15/2021 | JASON SHEETS |
| Hold | Cleared | 9/15/2021 | JASON SHEETS |
| Hold | Cleared | 9/15/2021 | Yasaman Shayesteh |
Contact Information
| Contractor | Precision Construction Experts Inc; Lic. No.: 1026997-B | 16656 CALLE ARBOLADA PACIFIC PALISADES, CA 90272 |
| Engineer | Kaligi,, Sean; Lic. No.: M37797 | 655 N CENTRAL AVE 17TH FL GLENDALE, CA 91203 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 4/26/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 4/26/2021 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 7/22/2021 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/22/2021 | Approved | OSVALDO PARAMO |
| METHANE-Barrier | 7/22/2021 | Approved | OSVALDO PARAMO |
| METHANE-Rough | 7/22/2021 | Approved | OSVALDO PARAMO |
| METHANE-Subgrade | 7/22/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 7/22/2021 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 9/17/2021 | Partial Inspection | RUBEN SALAS |
| HVAC-Rough | 9/17/2021 | Partial Inspection | RUBEN SALAS |
| PLUMBING-Rough | 9/17/2021 | Partial Inspection | RUBEN SALAS |
| ELECTRICAL-Rough | 9/20/2021 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 9/20/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 9/20/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 9/20/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/21/2021 | Partial Approval | OSVALDO PARAMO |
| Insulation | 9/22/2021 | Corrections Issued | RUBEN SALAS |
| Underground Mechanical | 12/10/2021 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Final | 1/26/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Final | 1/26/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Underground Mechanical | 1/26/2022 | Approved | OSVALDO PARAMO |
| HVAC-Final | 2/2/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Final | 4/14/2022 | Corrections Issued | OSVALDO PARAMO |
| Drywall Nailing | 4/15/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 4/15/2022 | Approved | OSVALDO PARAMO |
| Insulation | 4/15/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 4/28/2022 | Approved | OSVALDO PARAMO |
| Gas Test | 4/28/2022 | Approved | OSVALDO PARAMO |
| HVAC-Final | 4/28/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 4/28/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 9/12/2022 | Approved | OSVALDO PARAMO |
| Final | 9/12/2022 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 9/12/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/12/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 9/12/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 9/12/2022 | Approved | OSVALDO PARAMO |
| Service/Power Release | 9/21/2022 | Approved | OSVALDO PARAMO |
| Verify Rec and Parks Fee Memo | 9/21/2022 | Approved | OSVALDO PARAMO |
| Final | 10/18/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Final | 10/18/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/18/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 10/18/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 10/25/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Final | 10/25/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/25/2022 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 10/25/2022 | Approved | OSVALDO PARAMO |
| Final | 10/26/2022 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Final | 11/1/2022 | Approved | OSVALDO PARAMO |
| Final | 11/3/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 11/16/2022 | Corrections Issued | OSVALDO PARAMO |
| Final | 11/29/2022 | No Access for Inspection | OSVALDO PARAMO |
| Final | 12/2/2022 | No Access for Inspection | OSVALDO PARAMO |
| Final | 12/8/2022 | Corrections Issued | OSVALDO PARAMO |
| Final | 12/13/2022 | Conditional Approval | OSVALDO PARAMO |
| Final | 12/16/2022 | Conditional Approval | OSVALDO PARAMO |
| Final | 12/23/2022 | OK to Issue CofO | OSVALDO PARAMO |