10367 S KIMBERLY AVE 90002
Certificate Information: 10367 S KIMBERLY AVE 90002
- Application / Permit
- 20010-70000-00195
- Plan Check / Job No.
- B20SL00095
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20' X 27' ACCESSORY DWELLING UNIT THAT INCLUDES KITCHEN, LIVING ROOM, 2 BEDROOM AND 1 BATHROOM.
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 2/6/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 2/11/2020 | JASON HEALEY |
| Building Plans Picked Up | 2/14/2020 | APPLICANT |
| Green Plans Picked Up | 2/26/2020 | APPLICANT |
| Applicant returned to address corrections | 3/6/2020 | CRYSTEL MAALOUF |
| Plan Check Approved | 3/11/2020 | CRYSTEL MAALOUF |
| Issued | 3/16/2020 | LADBS |
| CofO in Progress | 1/12/2022 | EUGENE CASSIDY |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
| CofO Issued | 1/22/2022 | DEROLD HAUFF |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/26/2020 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 3/4/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 3/4/2020 | THOMAS LANG |
| Stormwater Pollution Mitigatn | Cleared | 3/4/2020 | ORVAL HERNANDEZ-MARCIAL |
| Green Code | Cleared | 3/11/2020 | VIVIAN LAO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/20/2020 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/21/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 4/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 4/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/29/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/5/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/2/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 6/2/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 6/2/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2020 | Partial Approval | BRIAN CHRISTIAN |
| Green Building Rough | 6/8/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 7/9/2020 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 7/9/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/13/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/15/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/15/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 7/15/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 7/15/2020 | Approved | EUGENE CASSIDY |
| Insulation | 7/30/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 8/4/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/4/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/17/2020 | Approved | EUGENE CASSIDY |
| Gas Test | 10/14/2020 | Approved | EUGENE CASSIDY |
| Sewer | 10/14/2020 | Approved | EUGENE CASSIDY |
| Final | 10/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 10/21/2020 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/21/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 10/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 10/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 2/26/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/26/2021 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 2/26/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 2/26/2021 | Approved | EUGENE CASSIDY |
| Final | 5/28/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 5/28/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/28/2021 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 5/28/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 8/30/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 8/30/2021 | Approved | EUGENE CASSIDY |
| Service/Power Release | 8/30/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 9/7/2021 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 9/7/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 10/12/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 10/12/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/11/2022 | Approved | EUGENE CASSIDY |
| Final | 1/11/2022 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 1/11/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/11/2022 | Approved | EUGENE CASSIDY |
| Service/Power Release | 1/11/2022 | Approved | EUGENE CASSIDY |