10701 S CROESUS AVE 90059
Certificate Information: 10701 S CROESUS AVE 90059
- Application / Permit
- 20010-70000-00194
- Plan Check / Job No.
- B20SL00094
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing garage into an ADU.
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Current Status
- CofO Issued on 12/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 3/17/2020 | SAMUEL GONZALEZ |
| Quality Review Completed | 3/18/2020 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 10/14/2020 | APPLICANT |
| Applicant returned to address corrections | 10/21/2020 | SAMUEL GONZALEZ |
| Plan Check Approved | 12/21/2020 | SAMUEL GONZALEZ |
| Issued | 12/23/2020 | APPLICANT |
| Building Plans Picked Up | 12/24/2020 | APPLICANT |
| CofO in Progress | 11/15/2021 | EUGENE CASSIDY |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
| CofO Issued | 12/15/2021 | DEROLD HAUFF |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/3/2020 | KURT CORRAL |
| Community Plan Implem. Overlay | Cleared | 9/15/2020 | HELEN JADALI |
| Address approval | Cleared | 9/22/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/23/2020 | CECILIO NAVARRO |
| Green Code | Cleared | 10/11/2020 | SAMUEL GONZALEZ |
| Low Impact Development | Cleared | 10/23/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/23/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/8/2021 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 1/14/2021 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 2/8/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 2/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Sewer | 2/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/28/2021 | Corrections Issued | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2021 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 6/28/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 6/28/2021 | Corrections Issued | ANSON MAGLASANG |
| Wood Frame | 6/28/2021 | Corrections Issued | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 7/2/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/2/2021 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 7/2/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 7/2/2021 | Partial Approval | EUGENE CASSIDY |
| Gas Test | 7/7/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 7/7/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 7/7/2021 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/7/2021 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/15/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/15/2021 | Approved | EUGENE CASSIDY |
| Insulation | 7/15/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/15/2021 | Partial Approval | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 7/15/2021 | Approved | EUGENE CASSIDY |
| Wood Frame | 7/15/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/20/2021 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 7/26/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/26/2021 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/17/2021 | Approved | EUGENE CASSIDY |
| Shower Pan | 8/17/2021 | Corrections Issued | EUGENE CASSIDY |
| Shower Pan | 8/23/2021 | Corrections Issued | EUGENE CASSIDY |
| Shower Pan | 8/24/2021 | Approved | EUGENE CASSIDY |
| Final | 10/8/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/8/2021 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 10/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/14/2021 | Approved | EUGENE CASSIDY |
| Final | 10/14/2021 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 10/14/2021 | Approved | EUGENE CASSIDY |
| HVAC-Final | 10/14/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/14/2021 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 10/14/2021 | Approved | EUGENE CASSIDY |