10701 S CROESUS AVE 90059

Certificate Information: 10701 S CROESUS AVE 90059

Application / Permit
20010-70000-00194
Plan Check / Job No.
B20SL00094
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage into an ADU.
Permit Issued
Issued on 12/23/2020
Issuing Office
Current Status
CofO Issued on 12/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 SAMUEL GONZALEZ
Corrections Issued 3/17/2020 SAMUEL GONZALEZ
Quality Review Completed 3/18/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 10/14/2020 APPLICANT
Applicant returned to address corrections 10/21/2020 SAMUEL GONZALEZ
Plan Check Approved 12/21/2020 SAMUEL GONZALEZ
Issued 12/23/2020 APPLICANT
Building Plans Picked Up 12/24/2020 APPLICANT
CofO in Progress 11/15/2021 EUGENE CASSIDY
Permit Finaled 12/15/2021 DEROLD HAUFF
CofO Issued 12/15/2021 DEROLD HAUFF
Permit Finaled 12/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/3/2020 KURT CORRAL
Community Plan Implem. Overlay Cleared 9/15/2020 HELEN JADALI
Address approval Cleared 9/22/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 9/23/2020 CECILIO NAVARRO
Sewer availability Cleared 9/23/2020 CECILIO NAVARRO
Green Code Cleared 10/11/2020 SAMUEL GONZALEZ
Low Impact Development Cleared 10/23/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/23/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/8/2021 Corrections Issued EUGENE CASSIDY
Pre-Inspection 1/14/2021 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 2/8/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 2/8/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 2/8/2021 Not Ready for Inspection EUGENE CASSIDY
Sewer 2/8/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 6/28/2021 Corrections Issued ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Partial Approval ANSON MAGLASANG
Green Building Rough 6/28/2021 Not Ready for Inspection ANSON MAGLASANG
Rough-Elec/Plmb/HVAC 6/28/2021 Corrections Issued ANSON MAGLASANG
Wood Frame 6/28/2021 Corrections Issued ANSON MAGLASANG
BUILDING-Rough-Frame 7/2/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 7/2/2021 Partial Approval EUGENE CASSIDY
Green Building Rough 7/2/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 7/2/2021 Partial Approval EUGENE CASSIDY
Gas Test 7/7/2021 Approved EUGENE CASSIDY
HVAC-Rough 7/7/2021 Partial Approval EUGENE CASSIDY
Insulation 7/7/2021 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 7/7/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 7/15/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Approved EUGENE CASSIDY
Green Building Rough 7/15/2021 Approved EUGENE CASSIDY
Insulation 7/15/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/15/2021 Partial Approval EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 7/15/2021 Approved EUGENE CASSIDY
Wood Frame 7/15/2021 Approved EUGENE CASSIDY
Drywall Nailing 7/20/2021 Partial Approval EUGENE CASSIDY
Drywall Nailing 7/26/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/26/2021 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 8/17/2021 Approved EUGENE CASSIDY
Shower Pan 8/17/2021 Corrections Issued EUGENE CASSIDY
Shower Pan 8/23/2021 Corrections Issued EUGENE CASSIDY
Shower Pan 8/24/2021 Approved EUGENE CASSIDY
Final 10/8/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 10/8/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 10/8/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 10/14/2021 Approved EUGENE CASSIDY
Final 10/14/2021 OK to Issue CofO EUGENE CASSIDY
Green Building Final 10/14/2021 Approved EUGENE CASSIDY
HVAC-Final 10/14/2021 Approved EUGENE CASSIDY
PLUMBING-Final 10/14/2021 Approved EUGENE CASSIDY
Smoke Detectors 10/14/2021 Approved EUGENE CASSIDY