1575-1577 W 35TH PL 90018

Certificate Information: 1575-1577 W 35TH PL 90018

Application / Permit
20010-70000-00093
Plan Check / Job No.
B20SL00079
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW THREE STORY DUPLEX. TYPE VB FULLY SPRINKLERED THROUGHOUT.
Permit Issued
Issued on 8/25/2020
Issuing Office
Current Status
CofO Issued on 6/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2020 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 RICARDO RAMIREZ
Corrections Issued 1/28/2020 RICARDO RAMIREZ
Green Plans Picked Up 1/29/2020 APPLICANT
Quality Review Completed 1/30/2020 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 7/16/2020 RICARDO RAMIREZ
Building Plans Picked Up 7/16/2020 APPLICANT
Issued 8/25/2020 APPLICANT
CofO in Progress 6/29/2021 DEROLD HAUFF
Permit Finaled 6/29/2021 DEROLD HAUFF
CofO Issued 6/29/2021 DEROLD HAUFF
Permit Finaled 6/29/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 4/20/2020 VIVIAN LAO
Hydrant and Access approval Cleared 5/4/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 5/8/2020 JUAN ASHTON
Sewer availability Cleared 5/8/2020 JUAN ASHTON
Address approval Cleared 5/28/2020 JUAN ASHTON
ZI Cleared 6/4/2020 MAXFIELD VERMY
Low Impact Development Cleared 6/30/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/30/2020 EMIL KYUPELYAN

Contact Information

Contractor Meza Aurelio; Lic. No.: 1065516-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045
Engineer Sanchez,, Pablo Beltran; Lic. No.: C86223 1840 S GAFFEY ST 382      SAN PEDRO, CA 90731

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/20/2020 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 10/23/2020 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 10/23/2020 Approved ROBERT MCDOWELL
METHANE-Barrier 10/23/2020 Approved ROBERT MCDOWELL
METHANE-Subgrade 10/23/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 12/22/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 1/25/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 1/25/2021 Approved ROBERT MCDOWELL
Green Building Rough 1/25/2021 Approved ROBERT MCDOWELL
HVAC-Rough 1/25/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 1/25/2021 Approved ROBERT MCDOWELL
METHANE-Rough 1/25/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 1/25/2021 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 1/25/2021 Approved ROBERT MCDOWELL
Drywall Nailing 2/3/2021 Approved ROBERT MCDOWELL
Insulation 2/3/2021 Approved ROBERT MCDOWELL
Service/Power Release 2/4/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 5/4/2021 Approved ROBERT MCDOWELL
Final 5/4/2021 Corrections Issued ROBERT MCDOWELL
Green Building Final 5/4/2021 Approved ROBERT MCDOWELL
HVAC-Final 5/4/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 5/4/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 5/4/2021 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 5/4/2021 Approved ROBERT MCDOWELL
Final 5/27/2021 Conditional Approval ROBERT MCDOWELL