1575-1577 W 35TH PL 90018
Certificate Information: 1575-1577 W 35TH PL 90018
- Application / Permit
- 20010-70000-00093
- Plan Check / Job No.
- B20SL00079
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW THREE STORY DUPLEX. TYPE VB FULLY SPRINKLERED THROUGHOUT.
- Permit Issued
- Issued on 8/25/2020
- Issuing Office
- Current Status
- CofO Issued on 6/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | RICARDO RAMIREZ |
| Corrections Issued | 1/28/2020 | RICARDO RAMIREZ |
| Green Plans Picked Up | 1/29/2020 | APPLICANT |
| Quality Review Completed | 1/30/2020 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 7/16/2020 | RICARDO RAMIREZ |
| Building Plans Picked Up | 7/16/2020 | APPLICANT |
| Issued | 8/25/2020 | APPLICANT |
| CofO in Progress | 6/29/2021 | DEROLD HAUFF |
| Permit Finaled | 6/29/2021 | DEROLD HAUFF |
| CofO Issued | 6/29/2021 | DEROLD HAUFF |
| Permit Finaled | 6/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 4/20/2020 | VIVIAN LAO |
| Hydrant and Access approval | Cleared | 5/4/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 5/8/2020 | JUAN ASHTON |
| Address approval | Cleared | 5/28/2020 | JUAN ASHTON |
| ZI | Cleared | 6/4/2020 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 6/30/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/30/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | Meza Aurelio; Lic. No.: 1065516-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
| Engineer | Sanchez,, Pablo Beltran; Lic. No.: C86223 | 1840 S GAFFEY ST 382 SAN PEDRO, CA 90731 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/20/2020 | Approved | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 10/23/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 10/23/2020 | Approved | ROBERT MCDOWELL |
| METHANE-Barrier | 10/23/2020 | Approved | ROBERT MCDOWELL |
| METHANE-Subgrade | 10/23/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 1/25/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 1/25/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 1/25/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 1/25/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 1/25/2021 | Approved | ROBERT MCDOWELL |
| METHANE-Rough | 1/25/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 1/25/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 1/25/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 2/3/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 2/3/2021 | Approved | ROBERT MCDOWELL |
| Service/Power Release | 2/4/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 5/4/2021 | Approved | ROBERT MCDOWELL |
| Final | 5/4/2021 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Final | 5/4/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 5/4/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 5/4/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 5/4/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Smoke Detectors | 5/4/2021 | Approved | ROBERT MCDOWELL |
| Final | 5/27/2021 | Conditional Approval | ROBERT MCDOWELL |