1707 W 38TH PL 90062
Certificate Information: 1707 W 38TH PL 90062
- Application / Permit
- 20010-70000-00042
- Plan Check / Job No.
- B20SL00042
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT PER WOOD FRAME PRESPECTIVE.
- Permit Issued
- Issued on 8/26/2020
- Issuing Office
- Current Status
- CofO Issued on 4/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | ERIC WONG |
| Corrections Issued | 2/21/2020 | ERIC WONG |
| Quality Review Completed | 2/24/2020 | KEN GILL |
| Applicant returned to address corrections | 4/8/2020 | ERIC WONG |
| Applicant returned to address corrections | 5/22/2020 | ERIC WONG |
| Green Plans Picked Up | 6/29/2020 | APPLICANT |
| Applicant returned to address corrections | 7/31/2020 | ERIC WONG |
| Plan Check Approved | 8/19/2020 | ERIC WONG |
| Issued | 8/26/2020 | APPLICANT |
| CofO in Progress | 4/4/2021 | ROBERT MCDOWELL |
| CofO in Progress | 4/4/2021 | ROBERT MCDOWELL |
| Permit Finaled | 4/20/2021 | DEROLD HAUFF |
| CofO Issued | 4/20/2021 | DEROLD HAUFF |
| Permit Finaled | 4/20/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/26/2020 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 5/15/2020 | GEORGE SUCHAND |
| Address approval | Cleared | 5/18/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2020 | WALLIE JONG |
| Permit | Cleared | 5/19/2020 | WALLIE JONG |
| Sewer availability | Cleared | 5/20/2020 | WALLIE JONG |
| Green Code | Cleared | 6/24/2020 | VIVIAN LAO |
| Low Impact Development | Cleared | 7/2/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/13/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/11/2020 | Partial Inspection | COREY HUPP |
| Footing/Foundation/Slab | 9/18/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2020 | Partial Approval | ROBERT MCDOWELL |
| Underground Mechanical | 10/5/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 10/23/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 10/23/2020 | Approved | ROBERT MCDOWELL |
| Wood Frame | 10/23/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 11/23/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 11/23/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 11/23/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 2/17/2021 | Corrections Issued | ROBERT MCDOWELL |
| Service/Power Release | 2/17/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 2/26/2021 | Approved | ROBERT MCDOWELL |
| Service/Power Release | 3/4/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 3/30/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 3/30/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 3/30/2021 | Approved | ROBERT MCDOWELL |
| Final | 3/30/2021 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Final | 3/30/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 3/30/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 3/30/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 3/30/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Smoke Detectors | 3/30/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 3/30/2021 | Approved | ROBERT MCDOWELL |
| Final | 4/5/2021 | OK to Issue CofO | ROBERT MCDOWELL |