10519 W TROON AVE 90064

Certificate Information: 10519 W TROON AVE 90064

Application / Permit
20010-40000-00936
Plan Check / Job No.
B20SP00293
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
1-story addition (121 SF) to (e) detached two-car garage (328 SF) (TOTAL = 449 SF)
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 2/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2020 APPLICANT
Assigned to Plan Check Engineer 4/8/2020 REZA HAGHIGHAT
Green Plans Picked Up 4/15/2020 APPLICANT
Corrections Issued 4/16/2020 REZA HAGHIGHAT
Quality Review Completed 4/24/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 6/26/2020 APPLICANT
Applicant returned to address corrections 5/14/2021 REZA HAGHIGHAT
Applicant returned to address corrections 6/3/2021 REZA HAGHIGHAT
Plan Check Approved 8/17/2021 TARIK SAOUD
Issued 8/18/2021 APPLICANT
CofO in Progress 12/12/2024 ARAM AVEDISIAN
CofO Issued 2/7/2025 RICHARD STEINBACH
Permit Finaled 2/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/29/2020 NIKTA MOUSAVI
Low Impact Development Cleared 10/20/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 12/11/2020 NIKTA MOUSAVI
Specific Plan Cleared 1/13/2021 DYLAN SITTIG
GPI Written Notices Cleared 7/15/2021 KAVIAN REFAHI
Grading Pre-Inspection Cleared 7/15/2021 REZA HAGHIGHAT

Contact Information

Contractor Armstrong Cal Builders Inc; Lic. No.: 990992-B 3031 E WILLOW STREET      SIGNAL HILL, CA 90755
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 15038 CLARK AVE      HACIENDA HEIGHTS, CA 91745
Geologist , ; Lic. No.: GEO2579    1290 N LAKE AVENUE #204    PASADENA, CA 91104

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/7/2022 Partial Approval KEVIN SARGSYAN
Masonry Wall/Backfill 7/15/2022 Partial Approval KEVIN SARGSYAN
Reinforced Masonry Frame 7/20/2022 Approved OGANES TARAKHCHYAN
Masonry Wall/Backfill 7/27/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Partial Approval CLAYTON GRAHAM
Interior/Exterior Lathing 5/3/2023 Partial Approval CLAYTON GRAHAM
ELECTRICAL-Rough 8/16/2023 Approved MEL KHACHATOURIAN
Wood Frame 8/16/2023 Approved MEL KHACHATOURIAN
Pre-Inspection 2/13/2024 Partial Inspection TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Not Ready OGANES TARAKHCHYAN
ELECTRICAL-Final 6/12/2024 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 7/25/2024 Approved ASHLEY THOMPSON
Final 7/25/2024 Not Ready for Inspection ASHLEY THOMPSON
Footing/Foundation/Slab 7/25/2024 Approved ASHLEY THOMPSON
Green Building Final 7/25/2024 Approved ASHLEY THOMPSON
Green Building Rough 7/25/2024 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 7/25/2024 SGSOV Not Required ASHLEY THOMPSON
Smoke Detectors 7/25/2024 Approved ASHLEY THOMPSON
Special/Order Compliance 7/25/2024 Partial Approval REGINA MENDEZ
Final 7/31/2024 Corrections Issued ASHLEY THOMPSON
Final 12/12/2024 OK to Issue CofO ARAM AVEDISIAN