482-482 1/2 E 49TH ST 90011
Certificate Information: 482-482 1/2 E 49TH ST 90011
- Application / Permit
- 20010-40000-00249
- Plan Check / Job No.
- B20SP00089
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) two-story duplex with attached garage. All work per engineered design.
- Permit Issued
- Issued on 8/31/2020
- Issuing Office
- Current Status
- CofO Issued on 6/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/12/2020 | JASON JANGADA |
| Green Plans Picked Up | 2/26/2020 | APPLICANT |
| Corrections Issued | 3/12/2020 | JASON JANGADA |
| Quality Review Completed | 3/12/2020 | CHRISTOPHER KOMANCHECK |
| Applicant returned to address corrections | 8/10/2020 | JASON JANGADA |
| Applicant returned to address corrections | 8/13/2020 | JASON JANGADA |
| Applicant returned to address corrections | 8/20/2020 | JASON JANGADA |
| Applicant returned to address corrections | 8/21/2020 | JASON JANGADA |
| Applicant returned to address corrections | 8/26/2020 | JASON JANGADA |
| Plan Check Approved | 8/27/2020 | JASON JANGADA |
| Issued | 8/31/2020 | APPLICANT |
| Building Plans Picked Up | 9/3/2020 | APPLICANT |
| CofO in Progress | 6/14/2021 | HORACE FULTZ |
| Permit Finaled | 6/25/2021 | DEROLD HAUFF |
| CofO Issued | 6/25/2021 | DEROLD HAUFF |
| Permit Finaled | 6/25/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2020 | ELENA LOPEZ |
| Highway dedication | Cleared | 4/16/2020 | ELENA LOPEZ |
| Permit | Cleared | 4/16/2020 | ELENA LOPEZ |
| Hydrant and Access approval | Cleared | 6/9/2020 | MATTHEW CRAIG |
| Sewer availability | Cleared | 7/1/2020 | AVALYN KAMACHI |
| Low Impact Development | Cleared | 7/7/2020 | MARTIN FRAGOSO |
| Green Code | Cleared | 7/27/2020 | RICHARD GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2020 | AVALYN KAMACHI |
| Roof/Waste drainage to street | Cleared | 7/28/2020 | WALLIE JONG |
Contact Information
| Contractor | Advanced Construction; Lic. No.: 801955-B | 18841 PASADERO DRIVE TARZANA, CA 91356 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/25/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Underground Mechanical | 9/25/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 10/5/2020 | Approved | DAVID FEILER |
| Deputy Drilled-In Anchors | 10/6/2020 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2020 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/25/2020 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 11/25/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 11/25/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Insulation | 12/3/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/2/2021 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 3/2/2021 | Corrections Issued | DAVID FEILER |
| Green Building Rough | 3/2/2021 | Approved | DAVID FEILER |
| HVAC-Rough | 3/2/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/2/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 3/2/2021 | Approved | DAVID FEILER |
| Verify Sprinkler Sign Off | 3/2/2021 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 3/8/2021 | Approved | DAVID FEILER |
| Insulation | 3/8/2021 | Partial Approval | DAVID FEILER |
| Interior/Exterior Lathing | 3/8/2021 | Partial Approval | DAVID FEILER |
| Drywall Nailing | 3/13/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/22/2021 | Approved | DAVID FEILER |
| Sewer | 4/16/2021 | Off-Hour Fees Due | |
| Sewer | 4/19/2021 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 4/19/2021 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Final | 5/20/2021 | Approved | ROBERT MCDOWELL |
| Final | 5/20/2021 | OK to Issue CofO | ROBERT MCDOWELL |
| Green Building Final | 5/20/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 5/20/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 5/20/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 5/20/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 5/20/2021 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 5/20/2021 | Approved | ROBERT MCDOWELL |