2630 N ALGODON CT 90046

Certificate Information: 2630 N ALGODON CT 90046

Application / Permit
20010-30001-02656
Plan Check / Job No.
B22WL04347
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental ref to pcis # 20010-30000-02656, to revise floor plan, and structural plans due to changes and change in structural engineer of record.
Permit Issued
Issued on 3/11/2024
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 4/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 SERGIO SILVA
Corrections Issued 12/7/2022 SERGIO SILVA
Quality Review Completed 12/9/2022 CHIHARU SUZUKI
Building Plans Picked Up 12/12/2022 APPLICANT
Applicant returned to address corrections 1/25/2023 SERGIO SILVA
Applicant returned to address corrections 2/6/2023 SERGIO SILVA
Applicant returned to address corrections 5/3/2023 SERGIO SILVA
Applicant returned to address corrections 6/30/2023 SERGIO SILVA
Applicant returned to address corrections 2/5/2024 SERGIO SILVA
Plan Check Approved 3/11/2024 SERGIO SILVA
Issued 3/11/2024 APPLICANT
Permit Finaled 4/20/2026 ROY SPAULDING

Permit Application Clearance Information

ZI Cleared 12/28/2022 OLGA AYALA
ZI Cleared 12/28/2022 OLGA AYALA
BHO/Hillside ordinance Cleared 1/13/2023 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 1/13/2023 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 1/13/2023 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 1/13/2023 CHRISTOPHER ROCHA
Permit Cleared 1/13/2023 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 1/24/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 1/24/2023 CHRISTOPHER ROCHA
GPI Written Notices Cleared 1/25/2023 SERGIO SILVA
Grading Pre-Inspection Cleared 1/25/2023 SERGIO SILVA
Hydrant and Access approval Cleared 2/2/2023 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 2/24/2023 CHRISTOPHER ROCHA
Trees in Parkway Cleared 3/6/2023 ADALBERTO VERA
Low Impact Development Cleared 6/12/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/22/2023 ADRIAN SANCHEZ
Miscellaneous Cleared 11/7/2023 ALBERT TAM
Haul Route Cleared 3/11/2024 SERGIO SILVA

Contact Information

Contractor Owner-Builder       ,
Engineer Eftekhari,, Hossein; Lic. No.: C50121 5945 SETTLER COURT      ANAHEIM, CA 92807
Engineer Obando,, Gaspar Eduardo; Lic. No.: C71382 3101 OCEAN PARK BLVD   STE 100, PMB 122    SANTA MONICA, CA 90405
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040
Engineer Tuchscher,, James; Lic. No.: C77649 5318 E 2ND ST., #539      LONG BEACH, CA 90803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2024 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 4/9/2024 Not Ready for Inspection ROY SPAULDING
Green Building Rough 4/9/2024 Not Ready for Inspection ROY SPAULDING
Verify Sprinkler Sign Off 4/9/2024 Not Ready for Inspection ROY SPAULDING
Special/Order Compliance 4/10/2024 Partial Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Partial Approval BRIAN SULLIVAN
Deputy Steel/Welding 5/15/2024 Conditional Approval BRIAN SULLIVAN
Sewer 5/22/2024 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 5/23/2024 Partial Approval RAUL BARAJAS
Sewer 5/23/2024 Partial Approval RAUL BARAJAS
PLUMBING-Rough 7/10/2024 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 7/10/2024 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/30/2024 Not Ready for Inspection RAUL BARAJAS
Underground Mechanical 8/30/2024 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 9/26/2024 Partial Approval BRIAN SULLIVAN
Green Building Rough 9/26/2024 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 9/26/2024 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 9/26/2024 Partial Approval BRIAN SULLIVAN
Deputy Steel/Welding 11/14/2024 Conditional Approval BRIAN SULLIVAN
Deputy Steel/Welding 11/18/2024 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval BRIAN SULLIVAN
Green Building Rough 12/4/2024 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 12/4/2024 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 12/4/2024 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 12/10/2024 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 12/10/2024 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 12/16/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 12/16/2024 Approved ROY SPAULDING
Green Building Rough 12/16/2024 Approved ROY SPAULDING
Verify Sprinkler Sign Off 12/16/2024 Approved ROY SPAULDING
Shower Pan 1/7/2025 Approved ROY SPAULDING
Insulation 1/17/2025 Approved ROY SPAULDING
Interior/Exterior Lathing 1/27/2025 Approved ROY SPAULDING
Drywall Nailing 1/29/2025 Approved ROY SPAULDING
Interior/Exterior Lathing 2/14/2025 Approved BRENDAN MORELLI
HVAC-Final 1/6/2026 Approved ROY SPAULDING
Final 4/20/2026 Permit Finaled ROY SPAULDING
Footing/Foundation/Slab 4/20/2026 Approved ROY SPAULDING
Green Building Final 4/20/2026 Approved ROY SPAULDING