2630 N ALGODON CT 90046
Certificate Information: 2630 N ALGODON CT 90046
- Application / Permit
- 20010-30001-02656
- Plan Check / Job No.
- B22WL04347
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental ref to pcis # 20010-30000-02656, to revise floor plan, and structural plans due to changes and change in structural engineer of record.
- Permit Issued
- Issued on 3/11/2024
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 4/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | SERGIO SILVA |
| Corrections Issued | 12/7/2022 | SERGIO SILVA |
| Quality Review Completed | 12/9/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/12/2022 | APPLICANT |
| Applicant returned to address corrections | 1/25/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 2/6/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 5/3/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 6/30/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 2/5/2024 | SERGIO SILVA |
| Plan Check Approved | 3/11/2024 | SERGIO SILVA |
| Issued | 3/11/2024 | APPLICANT |
| Permit Finaled | 4/20/2026 | ROY SPAULDING |
Permit Application Clearance Information
| ZI | Cleared | 12/28/2022 | OLGA AYALA |
| ZI | Cleared | 12/28/2022 | OLGA AYALA |
| BHO/Hillside ordinance | Cleared | 1/13/2023 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 1/13/2023 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 1/13/2023 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 1/13/2023 | CHRISTOPHER ROCHA |
| Permit | Cleared | 1/13/2023 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 1/24/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 1/24/2023 | CHRISTOPHER ROCHA |
| GPI Written Notices | Cleared | 1/25/2023 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 1/25/2023 | SERGIO SILVA |
| Hydrant and Access approval | Cleared | 2/2/2023 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2023 | CHRISTOPHER ROCHA |
| Trees in Parkway | Cleared | 3/6/2023 | ADALBERTO VERA |
| Low Impact Development | Cleared | 6/12/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/22/2023 | ADRIAN SANCHEZ |
| Miscellaneous | Cleared | 11/7/2023 | ALBERT TAM |
| Haul Route | Cleared | 3/11/2024 | SERGIO SILVA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Eftekhari,, Hossein; Lic. No.: C50121 | 5945 SETTLER COURT ANAHEIM, CA 92807 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 3101 OCEAN PARK BLVD STE 100, PMB 122 SANTA MONICA, CA 90405 |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
| Engineer | Tuchscher,, James; Lic. No.: C77649 | 5318 E 2ND ST., #539 LONG BEACH, CA 90803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/18/2024 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 4/9/2024 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 4/9/2024 | Not Ready for Inspection | ROY SPAULDING |
| Verify Sprinkler Sign Off | 4/9/2024 | Not Ready for Inspection | ROY SPAULDING |
| Special/Order Compliance | 4/10/2024 | Partial Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Partial Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 5/15/2024 | Conditional Approval | BRIAN SULLIVAN |
| Sewer | 5/22/2024 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 5/23/2024 | Partial Approval | RAUL BARAJAS |
| Sewer | 5/23/2024 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 7/10/2024 | Partial Approval | RAUL BARAJAS |
| Reinforced Concrete Frame | 7/10/2024 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 7/30/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Underground Mechanical | 8/30/2024 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 9/26/2024 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 9/26/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 9/26/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 9/26/2024 | Partial Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 11/14/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 11/18/2024 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 12/4/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 12/4/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 12/4/2024 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 12/10/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 12/10/2024 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 12/16/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 12/16/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 12/16/2024 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 12/16/2024 | Approved | ROY SPAULDING |
| Shower Pan | 1/7/2025 | Approved | ROY SPAULDING |
| Insulation | 1/17/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 1/27/2025 | Approved | ROY SPAULDING |
| Drywall Nailing | 1/29/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 2/14/2025 | Approved | BRENDAN MORELLI |
| HVAC-Final | 1/6/2026 | Approved | ROY SPAULDING |
| Final | 4/20/2026 | Permit Finaled | ROY SPAULDING |
| Footing/Foundation/Slab | 4/20/2026 | Approved | ROY SPAULDING |
| Green Building Final | 4/20/2026 | Approved | ROY SPAULDING |