2322 N GLOVER PL 90031

Certificate Information: 2322 N GLOVER PL 90031

Application / Permit
20010-30000-04821
Plan Check / Job No.
B20WL05445
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
construction of (n) two-story s.f.r. of type V construction with attached garage
Permit Issued
Issued on 6/7/2021
Issuing Office
Current Status
CofO Issued on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 12/28/2020 KAMRAN GHOTBI RAVANDI
Quality Review Completed 12/29/2020 CHIHARU SUZUKI
Building Plans Picked Up 1/4/2021 APPLICANT
Applicant returned to address corrections 4/27/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 5/4/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 5/15/2021 KAMRAN GHOTBI RAVANDI
Issued 6/7/2021 APPLICANT
CofO in Progress 1/20/2022 THOMAS LOGRASSO
CofO Issued 2/1/2022 DEROLD HAUFF
Permit Finaled 2/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 1/7/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/20/2021 CECILIO NAVARRO
Trees in Parkway Cleared 2/8/2021 JOHN KIM
Hydrant and Access approval Cleared 2/16/2021 MATTHEW CRAIG
ZI Cleared 2/19/2021 LOUIS ORTEGA
Sewer availability Cleared 3/18/2021 CECILIO NAVARRO
Low Impact Development Cleared 4/19/2021 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 4/20/2021 THAN WIN

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/14/2021 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 6/14/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 6/17/2021 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 9/1/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 9/1/2021 Approved KATHRYN BUTTERWORTH
Green Building Rough 9/1/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 9/1/2021 Corrections Issued KATHRYN BUTTERWORTH
MERV13>=Rough 9/1/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 9/1/2021 Corrections Issued KATHRYN BUTTERWORTH
Sewer 9/1/2021 Corrections Issued KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 9/1/2021 Corrections Issued KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/8/2021 Corrections Issued THOMAS LOGRASSO
Green Building Rough 9/8/2021 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 9/8/2021 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 9/15/2021 Partial Approval THOMAS LOGRASSO
HVAC-Rough 9/15/2021 Approved THOMAS LOGRASSO
PLUMBING-Rough 9/15/2021 Approved THOMAS LOGRASSO
Underground Mechanical 9/15/2021 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 9/30/2021 Corrections Issued THOMAS LOGRASSO
Verify Sprinkler Sign Off 9/30/2021 Approved THOMAS LOGRASSO
Insulation 10/5/2021 Conditional Approval THOMAS LOGRASSO
Drywall Nailing 10/7/2021 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 10/7/2021 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 10/14/2021 Approved THOMAS LOGRASSO
Shower Pan 10/14/2021 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 12/16/2021 Approved THOMAS LOGRASSO
Drywall Nailing 12/16/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Final 12/16/2021 Corrections Issued THOMAS LOGRASSO
Final 12/16/2021 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 12/16/2021 Approved THOMAS LOGRASSO
Gas Test 12/16/2021 Approved THOMAS LOGRASSO
Green Building Final 12/16/2021 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Final 12/16/2021 Corrections Issued THOMAS LOGRASSO
MERV13>=Final 12/16/2021 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 12/16/2021 Corrections Issued THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 12/16/2021 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 12/16/2021 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 12/16/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Final 12/22/2021 Approved THOMAS LOGRASSO
Final 12/22/2021 Corrections Issued THOMAS LOGRASSO
Green Building Final 12/22/2021 Approved THOMAS LOGRASSO
HVAC-Final 12/22/2021 Approved THOMAS LOGRASSO
MERV13>=Final 12/22/2021 Approved THOMAS LOGRASSO
PLUMBING-Final 12/22/2021 Approved THOMAS LOGRASSO
Service/Power Release 12/22/2021 Not Ready for Inspection THOMAS LOGRASSO
Final 1/20/2022 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 1/20/2022 Approved THOMAS LOGRASSO