420 S BUNDY DR 90049

Certificate Information: 420 S BUNDY DR 90049

Application / Permit
20010-30000-04802
Plan Check / Job No.
B20WL05419
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-story ADU w./ att. trellised roof patio cover at rear of the lot per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 3/31/2021
Issuing Office
Current Status
CofO Issued on 11/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2020 APPLICANT
Assigned to Plan Check Engineer 1/6/2021 REZA HAGHIGHAT
Corrections Issued 1/11/2021 REZA HAGHIGHAT
Quality Review Completed 1/21/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 3/26/2021 REZA HAGHIGHAT
Issued 3/31/2021 APPLICANT
Building Plans Picked Up 11/15/2021 APPLICANT
CofO in Progress 11/7/2022 DANIEL ORRANTE
Permit Finaled 11/16/2022 DANIEL ORRANTE
CofO Issued 11/16/2022 DANIEL ORRANTE
Permit Finaled 11/16/2022 DANIEL ORRANTE

Permit Application Clearance Information

Historic monument Cleared 2/5/2021 LOUIS ORTEGA
Miscellaneous Cleared 2/5/2021 LOUIS ORTEGA
Address approval Cleared 2/17/2021 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 2/17/2021 TRACY TATE
Permit Cleared 2/17/2021 TRACY TATE
Sewer availability Cleared 2/18/2021 TRACY TATE
Specific Plan Cleared 2/18/2021 FREDDY GARCIA
Hydrant and Access approval Cleared 3/8/2021 KURT CORRAL
Low Impact Development Cleared 3/16/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/23/2021 DINAH GARIN
GPI Written Notices Cleared 3/26/2021 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 3/26/2021 REZA HAGHIGHAT

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Geologist , ; Lic. No.: GEO2985    17106 CEREDO PL    GRANADA HILLS, CA 91344

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/12/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/20/2021 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 5/24/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 6/3/2021 Approved JOHN KIDWELL
Wood Frame 7/8/2021 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Approved JUAN VALENZUELA
PLUMBING-Rough 11/4/2021 Approved JOHN KIDWELL
ELECTRICAL-Rough 11/19/2021 Approved JOHN KIDWELL
HVAC-Rough 11/19/2021 Approved JOHN KIDWELL
Interior/Exterior Lathing 11/19/2021 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 12/7/2021 Approved JOHN KIDWELL
Green Building Rough 12/7/2021 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 12/7/2021 Approved JOHN KIDWELL
Insulation 12/17/2021 Approved KRISTEN CAUSEY
Drywall Nailing 1/13/2022 Corrections Issued JUAN VALENZUELA
Drywall Nailing 1/19/2022 No Access for Inspection KRISTEN CAUSEY
Shower Pan 1/21/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/28/2022 Approved JOHN KIDWELL
PLUMBING-Final 10/3/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 10/5/2022 Approved JUAN VALENZUELA
Special/Order Compliance 10/5/2022 Partial Inspection CLAYTON GRAHAM
HVAC-Final 10/14/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 10/24/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 10/24/2022 Approved KEVIN SARGSYAN
Drywall Nailing 11/7/2022 Approved DANIEL ORRANTE
Final 11/7/2022 OK to Issue CofO DANIEL ORRANTE
Green Building Final 11/7/2022 Approved DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Approved DANIEL ORRANTE
Service/Power Release 11/7/2022 Approved DANIEL ORRANTE
Smoke Detectors 11/7/2022 Approved DANIEL ORRANTE