430 S BUNDY DR 90049

Certificate Information: 430 S BUNDY DR 90049

Application / Permit
20010-30000-04801
Plan Check / Job No.
B20WL05419
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-Story SFD W./ att. 3-car garage and att. covered patio
Permit Issued
Issued on 4/2/2021
Issuing Office
Current Status
CofO Issued on 11/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2020 APPLICANT
Assigned to Plan Check Engineer 1/6/2021 REZA HAGHIGHAT
Corrections Issued 1/11/2021 REZA HAGHIGHAT
Quality Review Completed 1/21/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 3/26/2021 REZA HAGHIGHAT
Issued 4/2/2021 APPLICANT
Building Plans Picked Up 11/15/2021 APPLICANT
CofO in Progress 11/7/2022 DANIEL ORRANTE
Permit Finaled 11/15/2022 DANIEL ORRANTE
CofO Issued 11/15/2022 DANIEL ORRANTE
Permit Finaled 11/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Historic monument Cleared 2/5/2021 LOUIS ORTEGA
Miscellaneous Cleared 2/5/2021 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 2/17/2021 TRACY TATE
Sewer availability Cleared 2/17/2021 TRACY TATE
Specific Plan Cleared 2/18/2021 FREDDY GARCIA
Hydrant and Access approval Cleared 3/8/2021 KURT CORRAL
Low Impact Development Cleared 3/16/2021 JORGE MEJIA LEMUS
Permit Cleared 3/23/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 3/23/2021 DINAH GARIN
GPI Written Notices Cleared 3/26/2021 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 3/26/2021 REZA HAGHIGHAT

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Geologist , ; Lic. No.: GEO2985    17106 CEREDO PL    GRANADA HILLS, CA 91344

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/12/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/20/2021 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 5/24/2021 Partial Approval JOHN KIDWELL
Underground Mechanical 5/26/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 6/3/2021 Approved JOHN KIDWELL
Pre-Inspection 6/8/2021 Partial Inspection JOHN KIDWELL
Pre-Inspection 6/10/2021 Partial Approval JOHN KIDWELL
Wood Frame 7/9/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Approved JUAN VALENZUELA
Pre-Inspection 10/14/2021 Partial Inspection JOHN KIDWELL
PLUMBING-Rough 11/4/2021 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 11/8/2021 Approved JOHN KIDWELL
ELECTRICAL-Rough 11/19/2021 Approved JOHN KIDWELL
HVAC-Rough 11/19/2021 Corrections Issued JOHN KIDWELL
Interior/Exterior Lathing 11/19/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 11/22/2021 Approved JOHN KIDWELL
HVAC-Rough 11/23/2021 Approved ANDREW NAVE
Underground Mechanical 12/1/2021 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 12/7/2021 Approved JOHN KIDWELL
Green Building Rough 12/7/2021 Approved JOHN KIDWELL
Underground Mechanical 12/7/2021 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 12/7/2021 Approved JOHN KIDWELL
Insulation 12/17/2021 Approved KRISTEN CAUSEY
Underground Mechanical 12/21/2021 Partial Approval JOHN KIDWELL
Drywall Nailing 1/4/2022 Partial Approval JOHN KIDWELL
Drywall Nailing 1/13/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 1/13/2022 Partial Approval JUAN VALENZUELA
Special/Order Compliance 1/13/2022 Partial Inspection STEPHANIE SWANSON
Shower Pan 1/21/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/28/2022 Approved JOHN KIDWELL
Grounding or Bonding 2/22/2022 Partial Inspection JUAN VALENZUELA
Pre-Inspection 4/12/2022 Partial Inspection JOHN KIDWELL
Pre-Inspection 5/2/2022 Partial Inspection JUAN VALENZUELA
Pre-Inspection 5/5/2022 Partial Inspection JOHN KIDWELL
Sewer 5/13/2022 Approved KENNETH NAGLE
Gas Test 5/26/2022 Corrections Issued OGANES TARAKHCHYAN
Gas Test 6/1/2022 Approved JUAN VALENZUELA
Pre-Inspection 6/28/2022 Partial Inspection JOHN KIDWELL
Pre-Inspection 7/7/2022 Partial Inspection MICHAEL PELHAM
Pre-Inspection 7/25/2022 Partial Inspection KEVIN SARGSYAN
Pre-Inspection 8/18/2022 Partial Inspection KEVIN SARGSYAN
Gas Test 9/26/2022 Approved CARLOS MATAMOROS
PLUMBING-Final 9/26/2022 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 10/3/2022 Approved KEVIN SARGSYAN
HVAC-Final 10/14/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 10/24/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 10/24/2022 Approved KEVIN SARGSYAN
Final 11/3/2022 Conditional Approval DANIEL ORRANTE
Green Building Final 11/3/2022 Approved DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Approved DANIEL ORRANTE
Service/Power Release 11/3/2022 Approved DANIEL ORRANTE
Smoke Detectors 11/3/2022 Approved DANIEL ORRANTE
Special/Order Compliance 11/3/2022 Partial Inspection JUAN VALENZUELA
Final 11/7/2022 OK to Issue CofO DANIEL ORRANTE