206-206 1/2 E 29TH ST 90011
Certificate Information: 206-206 1/2 E 29TH ST 90011
- Application / Permit
- 20010-30000-04688
- Plan Check / Job No.
- B20WL05315
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 3-STORY DUPLEX B W./ ATT. 4-CAR GARAGE (REAR) (DUPLEX B)
- Permit Issued
- Issued on 5/23/2021
- Issuing Office
- Current Status
- CofO Issued on 6/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | REZA HAGHIGHAT |
| Corrections Issued | 12/23/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 12/29/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 3/23/2021 | REZA HAGHIGHAT |
| Issued | 5/23/2021 | APPLICANT |
| CofO in Progress | 5/10/2022 | HORACE FULTZ |
| Permit Finaled | 6/2/2022 | DEROLD HAUFF |
| CofO Issued | 6/2/2022 | DEROLD HAUFF |
| Permit Finaled | 6/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 1/12/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 2/11/2021 | ROBERT DUFF |
| Frnt yard landscape/Water mgmt | Cleared | 3/1/2021 | LOUIS ORTEGA |
| Low Impact Development | Cleared | 3/12/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/12/2021 | ROSA SILVA |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Inman,, Donald J; Lic. No.: C11888 | 5131 FOX HILLS AVENUE BUENA PARK, CA 90621 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/30/2021 | Corrections Issued | ANSON MAGLASANG |
| Sewer | 6/30/2021 | Corrections Issued | ANSON MAGLASANG |
| Underground Mechanical | 6/30/2021 | Corrections Issued | ANSON MAGLASANG |
| Underground Mechanical | 7/1/2021 | Partial Approval | HORACE FULTZ |
| Footing/Foundation/Slab | 7/19/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| METHANE-Barrier | 7/19/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 7/19/2021 | Approved | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 7/22/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/29/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Barrier | 7/29/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Structural Steel Frame | 7/29/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/3/2021 | Approved | JOAQUIN GREENOUGH |
| METHANE-Barrier | 8/3/2021 | Approved | JOAQUIN GREENOUGH |
| Structural Steel Frame | 8/3/2021 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2021 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 10/25/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 10/25/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 10/25/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 10/29/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 11/4/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 11/4/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 11/5/2021 | Partial Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/10/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 11/10/2021 | Approved | JOAQUIN GREENOUGH |
| METHANE-Rough | 11/10/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 11/10/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 11/19/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/23/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| METHANE-Rough | 11/23/2021 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 11/23/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 11/30/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 12/3/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 12/10/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 12/10/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 3/21/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Gas Test | 3/21/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 3/21/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Final | 3/21/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 3/21/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/5/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 5/5/2022 | Approved | HORACE FULTZ |
| Final | 5/5/2022 | OK to Issue CofO | HORACE FULTZ |
| Green Building Final | 5/5/2022 | Approved | HORACE FULTZ |
| HVAC-Final | 5/5/2022 | Approved | HORACE FULTZ |
| PLUMBING-Final | 5/5/2022 | Approved | HORACE FULTZ |
| Service/Power Release | 5/5/2022 | Approved | HORACE FULTZ |
| Smoke Detectors | 5/5/2022 | Approved | HORACE FULTZ |
| Verify Sprinkler Sign Off | 5/5/2022 | Approved | HORACE FULTZ |