204-204 1/2 E 29TH ST 90011

Certificate Information: 204-204 1/2 E 29TH ST 90011

Application / Permit
20010-30000-04687
Plan Check / Job No.
B20WL05315
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-STORY DUPLEX (FRONT) (DUPLEX A)
Permit Issued
Issued on 5/23/2021
Issuing Office
Current Status
CofO Issued on 6/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 REZA HAGHIGHAT
Corrections Issued 12/23/2020 REZA HAGHIGHAT
Quality Review Completed 12/29/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 3/23/2021 REZA HAGHIGHAT
Issued 5/23/2021 APPLICANT
CofO in Progress 5/10/2022 HORACE FULTZ
Permit Finaled 6/2/2022 DEROLD HAUFF
CofO Issued 6/2/2022 DEROLD HAUFF
Permit Finaled 6/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/11/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/12/2021 CECILIO NAVARRO
Sewer availability Cleared 1/12/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 2/11/2021 ROBERT DUFF
Frnt yard landscape/Water mgmt Cleared 3/1/2021 LOUIS ORTEGA
Low Impact Development Cleared 3/12/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/12/2021 ROSA SILVA

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Inman,, Donald J; Lic. No.: C11888 5131 FOX HILLS AVENUE      BUENA PARK, CA 90621

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/30/2021 Corrections Issued ANSON MAGLASANG
Sewer 6/30/2021 Corrections Issued ANSON MAGLASANG
Underground Mechanical 6/30/2021 Corrections Issued ANSON MAGLASANG
Underground Mechanical 7/1/2021 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 7/19/2021 Corrections Issued JOAQUIN GREENOUGH
METHANE-Barrier 7/19/2021 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 7/19/2021 Approved JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 7/22/2021 Conditional Approval JOAQUIN GREENOUGH
METHANE-Rough 7/22/2021 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/27/2021 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 7/27/2021 Corrections Issued JOAQUIN GREENOUGH
Structural Steel Frame 7/27/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/2/2021 Approved JOAQUIN GREENOUGH
METHANE-Barrier 8/2/2021 Approved JOAQUIN GREENOUGH
Structural Steel Frame 8/3/2021 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/23/2021 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 10/25/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 10/25/2021 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 10/25/2021 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 10/25/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Corrections Issued JOAQUIN GREENOUGH
Deputy Wood Construction 10/29/2021 Conditional Approval ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 11/4/2021 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 11/4/2021 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 11/5/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/10/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 11/10/2021 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 11/10/2021 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 11/10/2021 Approved JOAQUIN GREENOUGH
Insulation 11/16/2021 Partial Approval JOAQUIN GREENOUGH
Shower Pan 11/16/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/23/2021 Corrections Issued JOAQUIN GREENOUGH
Insulation 11/30/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Pre-Inspection 11/30/2021 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/1/2021 Partial Approval HORACE FULTZ
Insulation 12/1/2021 Approved HORACE FULTZ
Drywall Nailing 12/10/2021 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 12/10/2021 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 3/21/2022 Corrections Issued JOAQUIN GREENOUGH
Gas Test 3/21/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Final 3/21/2022 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Final 3/21/2022 Partial Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 3/21/2022 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 3/21/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/5/2022 Approved HORACE FULTZ
ELECTRICAL-Final 5/5/2022 Approved HORACE FULTZ
Final 5/5/2022 OK to Issue CofO HORACE FULTZ
Green Building Final 5/5/2022 Approved HORACE FULTZ
HVAC-Final 5/5/2022 Approved HORACE FULTZ
PLUMBING-Final 5/5/2022 Approved HORACE FULTZ
Service/Power Release 5/5/2022 Approved HORACE FULTZ
Smoke Detectors 5/5/2022 Approved HORACE FULTZ