854 N CRESCENT HEIGHTS BLVD 90046
Certificate Information: 854 N CRESCENT HEIGHTS BLVD 90046
- Application / Permit
- 20010-30000-04683
- Plan Check / Job No.
- B20WL05312
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH BASEMENT, ROOF TOP DECK, AND ATATCHED 1-CAR GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 12/12/2021
- Issuing Office
- Current Status
- CofO Issued on 7/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2021 | SERGIO SILVA |
| Corrections Issued | 1/20/2021 | SERGIO SILVA |
| Quality Review Completed | 1/28/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 6/1/2021 | SERGIO SILVA |
| Plan Check Approved | 11/18/2021 | SERGIO SILVA |
| Issued | 12/12/2021 | APPLICANT |
| Building Plans Picked Up | 12/14/2021 | APPLICANT |
| CofO in Progress | 6/26/2024 | AMIR NAZARIAN |
| CofO Issued | 7/2/2024 | DEROLD HAUFF |
| Permit Finaled | 7/2/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2021 | RENZ SORIANO |
| Permit | Cleared | 3/11/2021 | RENZ SORIANO |
| Miscellaneous | Cleared | 3/31/2021 | SERGIO SILVA |
| Sewer availability | Cleared | 3/31/2021 | RENZ SORIANO |
| Trees in Parkway | Cleared | 4/7/2021 | JOHN KIM |
| Excavation more than 5-ft deep | Cleared | 5/11/2021 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 5/19/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 6/29/2021 | SUNG JOON WON |
| Work Adjacent to Public Way | Cleared | 10/12/2021 | JOSE RODRIGUEZ |
| Roof/Waste drainage to street | Cleared | 10/21/2021 | STEVE MELGAR |
| Green Code | Cleared | 11/18/2021 | SERGIO SILVA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
| Engineer | Mahmoudkhani,, Behnam; Lic. No.: C88488 | 120 W WILSON AVE 1550 GLENDALE, CA 91203 |
| Engineer | Nguyen,, Tuan Minh; Lic. No.: S5883 | 5552 W 123RD PLACE HAWTHORNE, CA 90250 |
| Engineer | Zhang,, Quguang; Lic. No.: L8968 | 9080 TELSTAR AVE 303 EL MONTE, CA 91731 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/8/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/8/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 3/3/2022 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/26/2022 | Partial Approval | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 5/17/2022 | Corrections Issued | ADAM ESCOTO |
| Footing/Foundation/Slab | 5/17/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Pre-Inspection | 5/18/2022 | Partial Approval | JOSEPH MCGARRY |
| Deputy Steel/Welding | 6/8/2022 | Conditional Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 6/17/2022 | Approved | JOSEPH MCGARRY |
| Pre-Inspection | 6/17/2022 | Approved | JOSEPH MCGARRY |
| Deputy Steel/Welding | 7/26/2022 | No Access for Inspection | JULIAN AMAYA |
| Deputy Steel/Welding | 8/2/2022 | No Access for Inspection | JULIAN AMAYA |
| Deputy Steel/Welding | 8/3/2022 | Approved | JULIAN AMAYA |
| Deputy Wood Construction | 8/12/2022 | Conditional Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 12/22/2022 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 1/17/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 1/23/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 2/21/2023 | Partial Approval | MICHAEL LEWIS |
| Green Building Rough | 2/21/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 2/21/2023 | Approved | MICHAEL LEWIS |
| Insulation | 3/17/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 3/29/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Shower Pan | 4/5/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 4/18/2023 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 4/18/2023 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 5/9/2023 | Approved | LILIANA PORTILLO |
| Gas Test | 6/21/2023 | Approved | LILIANA PORTILLO |
| Sewer | 6/21/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 6/21/2023 | Approved | LILIANA PORTILLO |
| Gas Test | 8/29/2023 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 9/5/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/11/2023 | Corrections Issued | LILIANA PORTILLO |
| Final | 10/11/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 10/11/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 10/11/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 10/18/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/25/2023 | Partial Approval | LILIANA PORTILLO |
| Final | 10/25/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/18/2024 | Partial Inspection | AMIR NAZARIAN |
| ELECTRICAL-Final | 4/18/2024 | Partial Inspection | AMIR NAZARIAN |
| Final | 4/18/2024 | Partial Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 4/18/2024 | Partial Inspection | AMIR NAZARIAN |
| Green Building Final | 4/18/2024 | Partial Inspection | AMIR NAZARIAN |
| HVAC-Final | 4/18/2024 | Partial Inspection | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Service/Power Release | 4/18/2024 | Partial Inspection | AMIR NAZARIAN |
| Smoke Detectors | 4/18/2024 | Partial Inspection | AMIR NAZARIAN |
| HVAC-Final | 4/26/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Final | 5/10/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | AMIR NAZARIAN |
| Final | 5/14/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 5/14/2024 | Approved | AMIR NAZARIAN |
| Green Building Final | 5/14/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Approved | AMIR NAZARIAN |
| Service/Power Release | 5/14/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Smoke Detectors | 5/14/2024 | Approved | AMIR NAZARIAN |
| Service/Power Release | 5/15/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 6/25/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Service/Power Release | 6/25/2024 | Approved | AMIR NAZARIAN |