12316 W 4TH HELENA DR 90049

Certificate Information: 12316 W 4TH HELENA DR 90049

Application / Permit
20010-30000-04574
Plan Check / Job No.
B20WL05237
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Ground Floor and 2-Story ADU Addition over Attached 2-Car Garage ADU RFA Exemption per GCS 65852.2(e)(1)(B)(ii) and LAMC 12.22 A.33(c),(d), and (g)
Permit Issued
Issued on 1/10/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 DAVID CASTILLO
Corrections Issued 1/22/2021 DAVID CASTILLO
Quality Review Completed 1/26/2021 TARIK SAOUD
Building Plans Picked Up 1/28/2021 APPLICANT
Applicant returned to address corrections 4/7/2021 DAVID CASTILLO
Applicant returned to address corrections 4/27/2021 DAVID CASTILLO
Applicant returned to address corrections 8/25/2021 DAVID CASTILLO
Applicant returned to address corrections 11/3/2021 DAVID CASTILLO
Plan Check Approved 12/17/2021 DAVID CASTILLO
Issued 1/10/2022 APPLICANT
CofO in Progress 6/9/2023 OGANES TARAKHCHYAN
Permit Finaled 6/9/2023 DANIEL ORRANTE
CofO Issued 6/9/2023 DANIEL ORRANTE
Permit Finaled 6/9/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/25/2021 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 4/5/2021 CATHERINE ADROVER
Sewer availability Cleared 4/5/2021 CATHERINE ADROVER
Miscellaneous Cleared 4/28/2021 PEDRO AYALA
Low Impact Development Cleared 7/22/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 7/30/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 11/4/2021 DAVID CASTILLO

Contact Information

Architect Norris,, Tommy; Lic. No.: C37119 475 WASHINGTON BLVD      MARINA DEL REY, CA 90292
Contractor S K Construction; Lic. No.: 633705-B 901 CALLE SERRA      SAN DIMAS, CA 91773
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/19/2022 Partial Approval JOHN KIDWELL
Underground Mechanical 5/4/2022 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/13/2022 Approved KENNETH NAGLE
BUILDING-Rough-Frame 5/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 5/24/2022 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 5/25/2022 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/23/2022 Partial Approval JOHN KIDWELL
Green Building Rough 6/23/2022 Approved JOHN KIDWELL
Deputy Wood Construction 7/27/2022 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 7/29/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 8/3/2022 Partial Approval ANDREW NAVE
PLUMBING-Rough 8/3/2022 Corrections Issued ANDREW NAVE
PLUMBING-Rough 8/11/2022 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Approved KEVIN SARGSYAN
HVAC-Rough 8/25/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 9/21/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 9/21/2022 Partial Approval JOHN KIDWELL
Shower Pan 9/21/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 9/29/2022 Corrections Issued STEPHANIE SWANSON
Insulation 9/29/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 10/7/2022 Approved ANDREW NAVE
Insulation 10/7/2022 Approved ANDREW NAVE
Drywall Nailing 10/13/2022 Approved CLAYTON GRAHAM
Final 4/24/2023 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 4/24/2023 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/24/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 4/24/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 5/11/2023 Approved JESUS RODRIGUEZ
Final 5/11/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 5/11/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 5/11/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/11/2023 SGSOV Approved JESUS RODRIGUEZ
Pre-Inspection 5/25/2023 Approved OGANES TARAKHCHYAN
Final 5/31/2023 Corrections Issued OGANES TARAKHCHYAN
Final 6/8/2023 OK to Issue CofO OGANES TARAKHCHYAN