12316 W 4TH HELENA DR 90049
Certificate Information: 12316 W 4TH HELENA DR 90049
- Application / Permit
- 20010-30000-04574
- Plan Check / Job No.
- B20WL05237
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Ground Floor and 2-Story ADU Addition over Attached 2-Car Garage ADU RFA Exemption per GCS 65852.2(e)(1)(B)(ii) and LAMC 12.22 A.33(c),(d), and (g)
- Permit Issued
- Issued on 1/10/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | DAVID CASTILLO |
| Corrections Issued | 1/22/2021 | DAVID CASTILLO |
| Quality Review Completed | 1/26/2021 | TARIK SAOUD |
| Building Plans Picked Up | 1/28/2021 | APPLICANT |
| Applicant returned to address corrections | 4/7/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 4/27/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/25/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/3/2021 | DAVID CASTILLO |
| Plan Check Approved | 12/17/2021 | DAVID CASTILLO |
| Issued | 1/10/2022 | APPLICANT |
| CofO in Progress | 6/9/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 6/9/2023 | DANIEL ORRANTE |
| CofO Issued | 6/9/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/9/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2021 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2021 | CATHERINE ADROVER |
| Sewer availability | Cleared | 4/5/2021 | CATHERINE ADROVER |
| Miscellaneous | Cleared | 4/28/2021 | PEDRO AYALA |
| Low Impact Development | Cleared | 7/22/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/30/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 11/4/2021 | DAVID CASTILLO |
Contact Information
| Architect | Norris,, Tommy; Lic. No.: C37119 | 475 WASHINGTON BLVD MARINA DEL REY, CA 90292 |
| Contractor | S K Construction; Lic. No.: 633705-B | 901 CALLE SERRA SAN DIMAS, CA 91773 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/19/2022 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 5/4/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/13/2022 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 5/24/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Wood Construction | 5/25/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/23/2022 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 6/23/2022 | Approved | JOHN KIDWELL |
| Deputy Wood Construction | 7/27/2022 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 7/29/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 8/3/2022 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 8/3/2022 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Rough | 8/11/2022 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 8/25/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 9/21/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 9/21/2022 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 9/21/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 9/29/2022 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 9/29/2022 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/7/2022 | Approved | ANDREW NAVE |
| Insulation | 10/7/2022 | Approved | ANDREW NAVE |
| Drywall Nailing | 10/13/2022 | Approved | CLAYTON GRAHAM |
| Final | 4/24/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 4/24/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/24/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/24/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| Final | 5/11/2023 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/11/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Pre-Inspection | 5/25/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 5/31/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 6/8/2023 | OK to Issue CofO | OGANES TARAKHCHYAN |