12700 W MONTANA AVE 90049
Certificate Information: 12700 W MONTANA AVE 90049
- Application / Permit
- 20010-30000-04542
- Plan Check / Job No.
- B20WL05193
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD (3,214 sf) with attached 2-car garage (375 sf).
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 1/13/2021 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 1/21/2021 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/28/2021 | APPLICANT |
| Plan Check Approved | 5/30/2021 | REZA HAGHIGHAT |
| Issued | 7/20/2021 | APPLICANT |
| CofO in Progress | 10/1/2025 | ARAM AVEDISIAN |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
| CofO Issued | 10/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hold | Cleared | 12/29/2020 | JASON SHEETS |
| Permit | Cleared | 1/29/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2021 | DINAH GARIN |
| Sewer availability | Cleared | 2/2/2021 | DINAH GARIN |
| Specific Plan | Cleared | 2/8/2021 | FREDDY GARCIA |
| Hydrant and Access approval | Cleared | 3/10/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/24/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/29/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
| Engineer | Yadegari,, Shahriar; Lic. No.: C64591 | 10301 KESWICK AVE LOS ANGELES, CA 90064 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2022 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 5/27/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/15/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/22/2022 | Off-Hour Fees Due | |
| PLUMBING-Rough | 6/22/2022 | Partial Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 8/4/2022 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/31/2022 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 9/6/2022 | Approved | JOHN KIDWELL |
| Wood Frame | 10/4/2022 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Wood Construction | 10/6/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 10/6/2022 | Approved | ANDREW NAVE |
| Deputy Wood Construction | 10/14/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Wood Frame | 10/21/2022 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Corrections Issued | ANDREW NAVE |
| Wood Frame | 11/1/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 1/19/2023 | No Access for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 1/23/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 2/27/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 3/1/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/3/2023 | Conditional Approval | CLAYTON GRAHAM |
| HVAC-Rough | 3/3/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/3/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/6/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/6/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 3/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| Shower Pan | 3/20/2023 | Corrections Issued | CLAYTON GRAHAM |
| Special/Order Compliance | 3/20/2023 | Partial Inspection | JESUS PINEDA |
| Insulation | 3/24/2023 | Partial Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 4/3/2023 | Corrections Issued | CLAYTON GRAHAM |
| Deputy Wood Construction | 4/3/2023 | Conditional Approval | CLAYTON GRAHAM |
| Green Building Rough | 4/3/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Verify Sprinkler Sign Off | 4/3/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Shower Pan | 4/25/2023 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 4/25/2023 | Approved | JESUS PINEDA |
| Wood Frame | 4/25/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 5/9/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 5/9/2023 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 5/9/2023 | Conditional Approval | EVAN COOPER |
| PLUMBING-Rough | 5/9/2023 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 5/9/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 5/12/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 5/12/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 5/12/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Rough | 5/12/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Rough | 5/12/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 5/16/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 5/19/2023 | Not Ready for Inspection | JESUS PINEDA |
| Wood Frame | 5/19/2023 | Approved | JESUS PINEDA |
| Insulation | 5/23/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 6/1/2023 | Partial Approval | KENNETH NAGLE |
| Interior/Exterior Lathing | 7/11/2023 | Approved | JEREMY TODD |
| Underground Mechanical | 9/5/2023 | Corrections Issued | JESUS PINEDA |
| Sewer | 9/7/2023 | Partial Approval | BEN MOLSTAD |
| Gas Test | 9/12/2023 | Approved | BEN MOLSTAD |
| Sewer | 9/12/2023 | Approved | BEN MOLSTAD |
| Underground Mechanical | 9/12/2023 | Approved | BEN MOLSTAD |
| Grounding or Bonding | 10/4/2023 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 1/16/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 1/29/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 1/29/2024 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 1/30/2024 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 1/30/2024 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/1/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Final | 3/1/2024 | No Access for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 3/5/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Final | 3/5/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/12/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 11/15/2024 | Not Ready for Inspection | KIRK SANDERS |
| Final | 11/15/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 11/15/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 11/15/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 11/15/2024 | Corrections Issued | KIRK SANDERS |
| Structural Steel Frame | 11/15/2024 | Approved | KIRK SANDERS |
| Drywall Nailing | 11/20/2024 | Approved | KIRK SANDERS |
| Final | 11/20/2024 | Corrections Issued | KIRK SANDERS |
| Service/Power Release | 11/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 11/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| Service/Power Release | 4/28/2025 | Approved | MICHAEL PELHAM |
| Final | 9/26/2025 | Partial Approval | ARAM AVEDISIAN |
| Smoke Detectors | 9/26/2025 | Approved | ARAM AVEDISIAN |
| Final | 10/1/2025 | OK to Issue CofO | ARAM AVEDISIAN |