12700 W MONTANA AVE 90049

Certificate Information: 12700 W MONTANA AVE 90049

Application / Permit
20010-30000-04542
Plan Check / Job No.
B20WL05193
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story SFD (3,214 sf) with attached 2-car garage (375 sf).
Permit Issued
Issued on 7/20/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 1/13/2021 VLADIMIR ARUTYUNYAN
Quality Review Completed 1/21/2021 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/28/2021 APPLICANT
Plan Check Approved 5/30/2021 REZA HAGHIGHAT
Issued 7/20/2021 APPLICANT
CofO in Progress 10/1/2025 ARAM AVEDISIAN
Permit Finaled 10/7/2025 RICHARD STEINBACH
CofO Issued 10/7/2025 RICHARD STEINBACH
Permit Finaled 10/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Hold Cleared 12/29/2020 JASON SHEETS
Permit Cleared 1/29/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/2/2021 DINAH GARIN
Sewer availability Cleared 2/2/2021 DINAH GARIN
Specific Plan Cleared 2/8/2021 FREDDY GARCIA
Hydrant and Access approval Cleared 3/10/2021 MATTHEW CRAIG
Low Impact Development Cleared 4/24/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/29/2021 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401
Engineer Yadegari,, Shahriar; Lic. No.: C64591 10301 KESWICK AVE      LOS ANGELES, CA 90064

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/26/2022 Approved OGANES TARAKHCHYAN
Pre-Inspection 5/27/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 6/15/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 6/15/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 6/22/2022 Off-Hour Fees Due
PLUMBING-Rough 6/22/2022 Partial Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 8/3/2022 Not Ready for Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 8/4/2022 Approved JOHN KIDWELL
Footing/Foundation/Slab 8/31/2022 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 9/6/2022 Approved JOHN KIDWELL
Wood Frame 10/4/2022 Corrections Issued ASHLEY THOMPSON
Deputy Wood Construction 10/6/2022 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 10/6/2022 Approved ANDREW NAVE
Deputy Wood Construction 10/14/2022 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Corrections Issued CHRISTOPHER WILSON
Wood Frame 10/21/2022 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Corrections Issued ANDREW NAVE
Wood Frame 11/1/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/19/2023 No Access for Inspection CLAYTON GRAHAM
ELECTRICAL-Rough 1/23/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Rough 2/27/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Rough 3/1/2023 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Rough 3/3/2023 Conditional Approval CLAYTON GRAHAM
HVAC-Rough 3/3/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 3/3/2023 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Rough 3/6/2023 Approved CLAYTON GRAHAM
PLUMBING-Rough 3/6/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Rough 3/16/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 3/16/2023 Corrections Issued CLAYTON GRAHAM
Shower Pan 3/20/2023 Corrections Issued CLAYTON GRAHAM
Special/Order Compliance 3/20/2023 Partial Inspection JESUS PINEDA
Insulation 3/24/2023 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 4/3/2023 Corrections Issued CLAYTON GRAHAM
Deputy Wood Construction 4/3/2023 Conditional Approval CLAYTON GRAHAM
Green Building Rough 4/3/2023 Not Ready for Inspection CLAYTON GRAHAM
Verify Sprinkler Sign Off 4/3/2023 Not Ready for Inspection CLAYTON GRAHAM
Shower Pan 4/25/2023 Approved JESUS PINEDA
Verify Sprinkler Sign Off 4/25/2023 Approved JESUS PINEDA
Wood Frame 4/25/2023 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 5/9/2023 Approved EVAN COOPER
HVAC-Rough 5/9/2023 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 5/9/2023 Conditional Approval EVAN COOPER
PLUMBING-Rough 5/9/2023 Not Ready for Inspection EVAN COOPER
Shower Pan 5/9/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 5/12/2023 Approved CLAYTON GRAHAM
Drywall Nailing 5/12/2023 Corrections Issued CLAYTON GRAHAM
Green Building Rough 5/12/2023 Approved CLAYTON GRAHAM
HVAC-Rough 5/12/2023 Approved CLAYTON GRAHAM
PLUMBING-Rough 5/12/2023 Approved CLAYTON GRAHAM
Insulation 5/16/2023 Corrections Issued HERBERT GIRON
Insulation 5/19/2023 Not Ready for Inspection JESUS PINEDA
Wood Frame 5/19/2023 Approved JESUS PINEDA
Insulation 5/23/2023 Approved JESUS PINEDA
Drywall Nailing 6/1/2023 Partial Approval KENNETH NAGLE
Interior/Exterior Lathing 7/11/2023 Approved JEREMY TODD
Underground Mechanical 9/5/2023 Corrections Issued JESUS PINEDA
Sewer 9/7/2023 Partial Approval BEN MOLSTAD
Gas Test 9/12/2023 Approved BEN MOLSTAD
Sewer 9/12/2023 Approved BEN MOLSTAD
Underground Mechanical 9/12/2023 Approved BEN MOLSTAD
Grounding or Bonding 10/4/2023 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 1/16/2024 Corrections Issued BEN MOLSTAD
Gas Test 1/29/2024 Approved ASHLEY THOMPSON
PLUMBING-Final 1/29/2024 Approved ASHLEY THOMPSON
ELECTRICAL-Final 1/30/2024 Corrections Issued ARAM AVEDISIAN
HVAC-Final 1/30/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 3/1/2024 Not Ready for Inspection TEMISTOCLES CAAL
HVAC-Final 3/1/2024 No Access for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 3/5/2024 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Final 3/5/2024 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 3/12/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 11/15/2024 Not Ready for Inspection KIRK SANDERS
Final 11/15/2024 Corrections Issued KIRK SANDERS
Green Building Final 11/15/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 11/15/2024 SGSOV Approved KIRK SANDERS
Service/Power Release 11/15/2024 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 11/15/2024 Corrections Issued KIRK SANDERS
Structural Steel Frame 11/15/2024 Approved KIRK SANDERS
Drywall Nailing 11/20/2024 Approved KIRK SANDERS
Final 11/20/2024 Corrections Issued KIRK SANDERS
Service/Power Release 11/20/2024 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 11/20/2024 Not Ready for Inspection KIRK SANDERS
Service/Power Release 4/28/2025 Approved MICHAEL PELHAM
Final 9/26/2025 Partial Approval ARAM AVEDISIAN
Smoke Detectors 9/26/2025 Approved ARAM AVEDISIAN
Final 10/1/2025 OK to Issue CofO ARAM AVEDISIAN