442-442 1/2 E SHERMAN CL 90291

Certificate Information: 442-442 1/2 E SHERMAN CL 90291

Application / Permit
20010-30000-04480
Plan Check / Job No.
B20WL05090
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-story s.f.d. w/ roof deck, attached garage, and an attached ADU.
Permit Issued
Issued on 6/13/2022
Issuing Office
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 RICHARD GARCIA
Corrections Issued 11/29/2020 RICHARD GARCIA
Quality Review Completed 12/11/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/25/2022 RICHARD GARCIA
Applicant returned to address corrections 4/13/2022 RICHARD GARCIA
Plan Check Approved 5/2/2022 RICHARD GARCIA
Issued 6/13/2022 APPLICANT
Building Plans Picked Up 6/14/2022 APPLICANT
CofO in Progress 2/29/2024 HERBERT GIRON
Permit Finaled 3/6/2024 DANIEL ORRANTE
CofO Issued 3/6/2024 DANIEL ORRANTE
Permit Finaled 3/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Hold Cleared 6/22/2021 JASON SHEETS
Low Impact Development Cleared 6/23/2021 SUNG JOON WON
Address approval Cleared 7/1/2021 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 7/1/2021 DENNIS BRAGIN
Sewer availability Cleared 7/2/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 7/6/2021 DENNIS BRAGIN
Hydrant and Access approval Cleared 9/9/2021 JOHN CONNEALLY
Coastal Zone Cleared 9/16/2021 DANIEL CORONADO
Specific Plan Cleared 9/16/2021 DANIEL CORONADO
Specific Plan Cleared 9/16/2021 DANIEL CORONADO
ZI Cleared 9/16/2021 DANIEL CORONADO
ZI Cleared 9/16/2021 DANIEL CORONADO
ZI Cleared 9/16/2021 DANIEL CORONADO
ZI Cleared 9/16/2021 DANIEL CORONADO
Historic monument Cleared 9/21/2021 MELISSA JONES
Green Code Cleared 4/13/2022 RICHARD GARCIA

Contact Information

Architect Daham,, Ramsey Walid; Lic. No.: C34257 127 ARENA STREET      EL SEGUNDO, CA 90245
Contractor Owner-Builder       ,
Engineer Alexander,, Andy; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 6/21/2022 Conditional Approval RICHARD STEINBACH
Pre-Inspection 6/22/2022 Corrections Issued DAVID FEILER
METHANE-Barrier 8/23/2022 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 9/7/2022 Corrections Issued DAVID FEILER
METHANE-Barrier 9/7/2022 Approved DAVID FEILER
METHANE-Subgrade 9/7/2022 Approved DAVID FEILER
Footing/Foundation/Slab 9/9/2022 Approved DAVID FEILER
PLUMBING-Rough 9/9/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 11/4/2022 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Partial Approval DAVID FEILER
Green Building Rough 11/4/2022 Not Ready for Inspection DAVID FEILER
METHANE-Rough 11/4/2022 Not Ready for Inspection DAVID FEILER
Verify Sprinkler Sign Off 11/4/2022 Not Ready for Inspection DAVID FEILER
Deputy Wood Construction 11/7/2022 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 12/9/2022 Approved EVAN COOPER
Wood Frame 12/9/2022 Partial Approval EVAN COOPER
PLUMBING-Rough 1/10/2023 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 1/27/2023 Approved EVAN COOPER
PLUMBING-Rough 1/27/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/1/2023 Conditional Approval JESUS RODRIGUEZ
HVAC-Rough 2/1/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/17/2023 Partial Approval EVAN COOPER
Deputy Wood Construction 2/24/2023 Conditional Approval EVAN COOPER
Wood Frame 2/24/2023 Approved EVAN COOPER
Insulation 3/1/2023 Approved EVAN COOPER
Drywall Nailing 3/8/2023 Approved EVAN COOPER
Gas Test 3/8/2023 Not Ready for Inspection EVAN COOPER
Green Building Rough 3/8/2023 Approved EVAN COOPER
Interior/Exterior Lathing 3/8/2023 Approved EVAN COOPER
Gas Test 4/17/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 7/24/2023 Approved EVAN COOPER
Final 7/24/2023 Not Ready for Inspection EVAN COOPER
Green Building Final 7/24/2023 Not Ready for Inspection EVAN COOPER
METHANE-Final 7/24/2023 Approved EVAN COOPER
METHANE-Rough 7/24/2023 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/24/2023 SGSOV Approved EVAN COOPER
Service/Power Release 7/24/2023 Not Ready for Inspection EVAN COOPER
Smoke Detectors 7/24/2023 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 7/24/2023 Approved EVAN COOPER
PLUMBING-Final 8/14/2023 Corrections Issued HERBERT GIRON
Smoke Detectors 8/14/2023 Approved HERBERT GIRON
Green Building Final 8/17/2023 Approved HERBERT GIRON
HVAC-Final 8/17/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/17/2023 Approved HERBERT GIRON
ELECTRICAL-Final 8/24/2023 Corrections Issued HERBERT GIRON
HVAC-Final 8/24/2023 Approved HERBERT GIRON
ELECTRICAL-Final 9/19/2023 Corrections Issued HERBERT GIRON
Final 9/19/2023 Corrections Issued HERBERT GIRON
Final 1/18/2024 Partial Inspection HERBERT GIRON
Service/Power Release 1/18/2024 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 1/25/2024 Approved HERBERT GIRON
Final 1/25/2024 Corrections Issued HERBERT GIRON
Final 2/27/2024 OK to Issue CofO HERBERT GIRON
Service/Power Release 2/27/2024 Approved HERBERT GIRON
Service/Power Release 2/28/2024 Approved HERBERT GIRON