442-442 1/2 E SHERMAN CL 90291
Certificate Information: 442-442 1/2 E SHERMAN CL 90291
- Application / Permit
- 20010-30000-04480
- Plan Check / Job No.
- B20WL05090
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 3-story s.f.d. w/ roof deck, attached garage, and an attached ADU.
- Permit Issued
- Issued on 6/13/2022
- Issuing Office
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | RICHARD GARCIA |
| Corrections Issued | 11/29/2020 | RICHARD GARCIA |
| Quality Review Completed | 12/11/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/25/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 4/13/2022 | RICHARD GARCIA |
| Plan Check Approved | 5/2/2022 | RICHARD GARCIA |
| Issued | 6/13/2022 | APPLICANT |
| Building Plans Picked Up | 6/14/2022 | APPLICANT |
| CofO in Progress | 2/29/2024 | HERBERT GIRON |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
| CofO Issued | 3/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hold | Cleared | 6/22/2021 | JASON SHEETS |
| Low Impact Development | Cleared | 6/23/2021 | SUNG JOON WON |
| Address approval | Cleared | 7/1/2021 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 7/1/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 7/2/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2021 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 9/9/2021 | JOHN CONNEALLY |
| Coastal Zone | Cleared | 9/16/2021 | DANIEL CORONADO |
| Specific Plan | Cleared | 9/16/2021 | DANIEL CORONADO |
| Specific Plan | Cleared | 9/16/2021 | DANIEL CORONADO |
| ZI | Cleared | 9/16/2021 | DANIEL CORONADO |
| ZI | Cleared | 9/16/2021 | DANIEL CORONADO |
| ZI | Cleared | 9/16/2021 | DANIEL CORONADO |
| ZI | Cleared | 9/16/2021 | DANIEL CORONADO |
| Historic monument | Cleared | 9/21/2021 | MELISSA JONES |
| Green Code | Cleared | 4/13/2022 | RICHARD GARCIA |
Contact Information
| Architect | Daham,, Ramsey Walid; Lic. No.: C34257 | 127 ARENA STREET EL SEGUNDO, CA 90245 |
| Contractor | Owner-Builder | , |
| Engineer | Alexander,, Andy; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Methane Barrier | 6/21/2022 | Conditional Approval | RICHARD STEINBACH |
| Pre-Inspection | 6/22/2022 | Corrections Issued | DAVID FEILER |
| METHANE-Barrier | 8/23/2022 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 9/7/2022 | Corrections Issued | DAVID FEILER |
| METHANE-Barrier | 9/7/2022 | Approved | DAVID FEILER |
| METHANE-Subgrade | 9/7/2022 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 9/9/2022 | Approved | DAVID FEILER |
| PLUMBING-Rough | 9/9/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Rough | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| Verify Sprinkler Sign Off | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| Deputy Wood Construction | 11/7/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 12/9/2022 | Approved | EVAN COOPER |
| Wood Frame | 12/9/2022 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 1/10/2023 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 1/27/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/27/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2023 | Conditional Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 2/1/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/17/2023 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 2/24/2023 | Conditional Approval | EVAN COOPER |
| Wood Frame | 2/24/2023 | Approved | EVAN COOPER |
| Insulation | 3/1/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 3/8/2023 | Approved | EVAN COOPER |
| Gas Test | 3/8/2023 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 3/8/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/8/2023 | Approved | EVAN COOPER |
| Gas Test | 4/17/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 7/24/2023 | Approved | EVAN COOPER |
| Final | 7/24/2023 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 7/24/2023 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Final | 7/24/2023 | Approved | EVAN COOPER |
| METHANE-Rough | 7/24/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 7/24/2023 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 7/24/2023 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 7/24/2023 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 7/24/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/14/2023 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 8/14/2023 | Approved | HERBERT GIRON |
| Green Building Final | 8/17/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 8/17/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 8/17/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 8/24/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 8/24/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 9/19/2023 | Corrections Issued | HERBERT GIRON |
| Final | 9/19/2023 | Corrections Issued | HERBERT GIRON |
| Final | 1/18/2024 | Partial Inspection | HERBERT GIRON |
| Service/Power Release | 1/18/2024 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 1/25/2024 | Approved | HERBERT GIRON |
| Final | 1/25/2024 | Corrections Issued | HERBERT GIRON |
| Final | 2/27/2024 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 2/27/2024 | Approved | HERBERT GIRON |
| Service/Power Release | 2/28/2024 | Approved | HERBERT GIRON |