10853 W OTSEGO ST 91601
Certificate Information: 10853 W OTSEGO ST 91601
- Application / Permit
- 20010-30000-04460
- Plan Check / Job No.
- B20WL05057
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3-story duplex w./ att. garages and ADU at rear of the lot per LAMC 12.22 A.33(c) and (e); 10853 Otsego St; (unit A) (1,697 sf ) (garage 373 sf); 10853 1/2 Otsego St; (unit B) (1742 sf) (garage 340sf); 10853 3/4 Otsego St; (ADU) (unit C) (486 sf); "COMPLY WITH DEPARTMENT ORDER effective date 05/27/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 6/11/2021
- Issuing Office
- Current Status
- CofO Issued on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2020 | REZA HAGHIGHAT |
| Corrections Issued | 12/15/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 12/24/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/5/2021 | APPLICANT |
| Plan Check Approved | 3/31/2021 | REZA HAGHIGHAT |
| Issued | 6/11/2021 | APPLICANT |
| CofO in Progress | 4/27/2022 | JACK KARGODORIAN |
| Permit Finaled | 5/4/2022 | MICHAEL SMITH |
| CofO Issued | 5/4/2022 | MICHAEL SMITH |
| Permit Finaled | 5/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 1/13/2021 | LOUIS ORTEGA |
| Hydrant and Access approval | Cleared | 2/23/2021 | MATTHEW CRAIG |
| Address approval | Cleared | 2/26/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2021 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 3/17/2021 | ANDRES COVARRUBIAS |
| Sewer availability | Cleared | 3/17/2021 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 3/23/2021 | LEE GUILBEAUX |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Geologist | , ; Lic. No.: GEO2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/24/2021 | Partial Approval | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 6/25/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2021 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2021 | Partial Approval | DANIEL DREW |
| ELECTRICAL-Rough | 10/22/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Partial Approval | DANIEL DREW |
| HVAC-Rough | 10/22/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 10/22/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 11/4/2021 | Approved | DANIEL DREW |
| Green Building Rough | 11/4/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 11/4/2021 | Approved | DANIEL DREW |
| Verify Sprinkler Sign Off | 11/4/2021 | Approved | DANIEL DREW |
| Insulation | 11/16/2021 | Partial Approval | DANIEL DREW |
| Insulation | 11/23/2021 | Conditional Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/23/2021 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 11/23/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 12/6/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 3/24/2022 | Corrections Issued | MATT KELLERMAN |
| HVAC-Final | 3/24/2022 | Corrections Issued | MATT KELLERMAN |
| ELECTRICAL-Final | 4/11/2022 | No Access for Inspection | MATT KELLERMAN |
| HVAC-Final | 4/11/2022 | No Access for Inspection | MATT KELLERMAN |
| PLUMBING-Final | 4/11/2022 | Corrections Issued | MATT KELLERMAN |
| Final | 4/22/2022 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 4/22/2022 | Approved | JACK KARGODORIAN |
| Green Building Final | 4/22/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/22/2022 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 4/22/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 4/22/2022 | Approved | JACK KARGODORIAN |
| Structural Steel Frame | 4/22/2022 | Approved | JACK KARGODORIAN |
| Final | 4/26/2022 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 4/26/2022 | Approved | JACK KARGODORIAN |
| Final | 4/27/2022 | OK to Issue CofO | JACK KARGODORIAN |