1626 S CREST DR 90035
Certificate Information: 1626 S CREST DR 90035
- Application / Permit
- 20010-30000-04389
- Plan Check / Job No.
- B20WL05005
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2 story SFD with 1 car attached garage & basement.
- Permit Issued
- Issued on 5/17/2022
- Issuing Office
- Current Status
- CofO Issued on 11/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 1/11/2021 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 1/21/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/27/2022 | JASON JANGADA |
| Issued | 5/17/2022 | APPLICANT |
| Building Plans Picked Up | 5/20/2022 | APPLICANT |
| CofO in Progress | 11/21/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 11/25/2024 | RICHARD STEINBACH |
| CofO Issued | 11/25/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/25/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2021 | THOMAS LANG |
| GPI Written Notices | Cleared | 6/28/2021 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 6/28/2021 | VLADIMIR ARUTYUNYAN |
| Permit | Cleared | 6/29/2021 | THOMAS LANG |
| Sewer availability | Cleared | 7/7/2021 | THOMAS LANG |
| Trees in Parkway | Cleared | 8/12/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 8/30/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 12/2/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/15/2021 | THAN WIN |
Contact Information
| Architect | Langer-Voss,, Naomi; Lic. No.: C32512 | 210 WEST 101 STREET-8G NEW YORK, NY 10025 |
| Contractor | Harari Construction Inc; Lic. No.: 1017539-B | 9719 OAKMORE ROAD LOS ANGELES, CA 90035 |
| Engineer | Howe,, Carl William; Lic. No.: C44773 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/8/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 8/8/2022 | Conditional Approval | EVAN COOPER |
| METHANE-Barrier | 8/8/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 8/8/2022 | Not Ready for Inspection | EVAN COOPER |
| Deputy Reinf. Concrete | 8/17/2022 | Conditional Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 9/9/2022 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Partial Approval | ANDREW NAVE |
| Deputy Other (see comments) | 9/15/2022 | Conditional Approval | RICHARD STEINBACH |
| Deputy Shotcrete | 9/15/2022 | Conditional Approval | RICHARD STEINBACH |
| Sewer | 12/19/2022 | Approved | JEREMY TODD |
| METHANE-Subgrade | 1/3/2023 | Approved | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 2/8/2023 | Partial Approval | DAVID FEILER |
| METHANE-Barrier | 2/8/2023 | Not Ready for Inspection | DAVID FEILER |
| Deputy Reinf. Concrete | 2/13/2023 | No Access for Inspection | DAVID FEILER |
| Deputy Methane Barrier | 2/17/2023 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 2/20/2023 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 2/20/2023 | Partial Approval | DAVID FEILER |
| METHANE-Barrier | 2/20/2023 | Off-Hour Fees Due | |
| Deputy Reinf. Concrete | 2/21/2023 | Conditional Approval | JEREMY TODD |
| Footing/Foundation/Slab | 5/3/2023 | Approved | JEREMY TODD |
| METHANE-Barrier | 5/3/2023 | Approved | JEREMY TODD |
| Deputy Reinf. Concrete | 5/8/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Partial Approval | JEREMY TODD |
| Deputy Wood Construction | 5/22/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 5/24/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Partial Approval | JEREMY TODD |
| Deputy Drilled-In Anchors | 5/26/2023 | Conditional Approval | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Partial Approval | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Approved | JEREMY TODD |
| Gas Test | 9/7/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 9/7/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/7/2023 | Approved | MEL KHACHATOURIAN |
| Sewer | 9/7/2023 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 11/15/2023 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 11/15/2023 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 12/26/2023 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 12/26/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 12/26/2023 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 12/26/2023 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 1/9/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 1/9/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 1/11/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 1/16/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 1/17/2024 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 2/9/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 3/7/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 8/16/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 8/16/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 9/6/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 9/6/2024 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 9/17/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 9/17/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 9/17/2024 | Corrections Issued | ARAM AVEDISIAN |
| Service/Power Release | 9/17/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 9/23/2024 | Approved | ARAM AVEDISIAN |
| Final | 11/8/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 11/8/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 11/8/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 11/8/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 11/8/2024 | Approved | MEL KHACHATOURIAN |
| Final | 11/19/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| Service/Power Release | 11/22/2024 | Approved | MEL KHACHATOURIAN |