237-237 1/2 N ROSELAKE AVE 90026
Certificate Information: 237-237 1/2 N ROSELAKE AVE 90026
- Application / Permit
- 20010-30000-04324
- Plan Check / Job No.
- B20WL04943
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY TYPE VB DUPLEX WITH ATTACHED 1-CAR GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 7/2/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | SERGIO SILVA |
| Corrections Issued | 12/17/2020 | SERGIO SILVA |
| Quality Review Completed | 12/24/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/4/2021 | APPLICANT |
| Applicant returned to address corrections | 5/18/2021 | SERGIO SILVA |
| Plan Check Approved | 6/28/2021 | SERGIO SILVA |
| Issued | 7/2/2021 | APPLICANT |
| CofO in Progress | 10/26/2022 | FREDDIE RIVERA |
| Permit Finaled | 11/3/2022 | RONALD MYRICK |
| CofO Issued | 11/3/2022 | RONALD MYRICK |
| Permit Finaled | 11/3/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/6/2021 | MATTHEW CRAIG |
| Address approval | Cleared | 1/11/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 1/13/2021 | CECILIO NAVARRO |
| Highway dedication | Cleared | 2/10/2021 | CECILIO NAVARRO |
| Trees in Parkway | Cleared | 2/25/2021 | JOHN KIM |
| Frnt yard landscape/Water mgmt | Cleared | 3/3/2021 | LOUIS ORTEGA |
| Low Impact Development | Cleared | 3/3/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/5/2021 | RENZ SORIANO |
| Permit | Cleared | 4/15/2021 | CECILIO NAVARRO |
| GPI Written Notices | Cleared | 6/2/2021 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 6/2/2021 | SERGIO SILVA |
| Green Code | Cleared | 6/28/2021 | SERGIO SILVA |
Contact Information
| Architect | , ; Lic. No.: C35150 | , |
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Azad,, Jila H; Lic. No.: C77585 | 2340 FOX HILLS DRIVE UNIT 305 LOS ANGELES, CA 90064 |
| Engineer | Inman,, Donald J; Lic. No.: C11888 | 5131 FOX HILLS AVENUE BUENA PARK, CA 90621 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/16/2021 | Partial Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 7/26/2021 | Approved | ROBERT VORHIS |
| METHANE-Barrier | 7/26/2021 | Approved | ROBERT VORHIS |
| METHANE-Subgrade | 7/26/2021 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2022 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/1/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/25/2022 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Rough | 2/25/2022 | Approved | RUBEN SALAS |
| Green Building Rough | 2/25/2022 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Rough | 2/25/2022 | Corrections Issued | RUBEN SALAS |
| METHANE-Rough | 2/25/2022 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 2/25/2022 | Approved | RUBEN SALAS |
| Rough-Elec/Plmb/HVAC | 2/25/2022 | Partial Approval | RUBEN SALAS |
| Verify Sprinkler Sign Off | 2/25/2022 | Not Ready for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 3/4/2022 | Partial Approval | AMY COLIN |
| Green Building Rough | 3/4/2022 | Approved | AMY COLIN |
| HVAC-Rough | 3/4/2022 | Approved | AMY COLIN |
| METHANE-Rough | 3/4/2022 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 3/4/2022 | Not Ready for Inspection | AMY COLIN |
| Insulation | 3/15/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 3/24/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 3/24/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 4/1/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/1/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/20/2022 | Approved | FREDDIE RIVERA |
| Shower Pan | 5/20/2022 | Approved | FREDDIE RIVERA |
| HVAC-Final | 9/20/2022 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 9/20/2022 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/22/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 9/22/2022 | Approved | FREDDIE RIVERA |
| Final | 9/22/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 9/22/2022 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 9/22/2022 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 9/22/2022 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 9/27/2022 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 9/29/2022 | Approved | FREDDIE RIVERA |
| Final | 9/29/2022 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 9/29/2022 | Approved | FREDDIE RIVERA |
| HVAC-Final | 9/29/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 9/29/2022 | Approved | FREDDIE RIVERA |
| Service/Power Release | 9/29/2022 | Approved | FREDDIE RIVERA |