1918 W WALCOTT WAY 90039
Certificate Information: 1918 W WALCOTT WAY 90039
- Application / Permit
- 20010-30000-04270
- Plan Check / Job No.
- B20WL04907
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-Story ADU per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 11/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 12/11/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 12/17/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/24/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 1/18/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 2/25/2022 | DAVID CASTILLO |
| Plan Check Approved | 3/17/2022 | DAVID CASTILLO |
| Issued | 4/5/2022 | APPLICANT |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| CofO in Progress | 11/12/2024 | HAMIK HARTOUNIAN |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
| CofO Issued | 11/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 4/29/2021 | MATTHEW CRAIG |
| Sewer availability | Cleared | 5/13/2021 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 6/24/2021 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 12/22/2021 | THAN WIN |
| GPI Written Notices | Cleared | 3/15/2022 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
| Engineer | Marte,, Julie Anne; Lic. No.: C84066 | PO BOX 1406 GLENDORA, CA 91740 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 6/14/2022 | Corrections Issued | THOMAS LOGRASSO |
| Sewer | 6/27/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/25/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/16/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/23/2022 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 9/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 9/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 9/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/9/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 9/9/2022 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2022 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 10/5/2022 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Shower Pan | 10/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Underground Mechanical | 10/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/17/2022 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Corrections Issued | THOMAS LOGRASSO |
| Gas Test | 10/17/2022 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/17/2022 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 10/17/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/9/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 11/9/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 11/9/2022 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 11/9/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 11/9/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 11/9/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/29/2022 | Partial Approval | THOMAS LOGRASSO |
| HVAC-Rough | 11/29/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 11/29/2022 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 12/1/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/1/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 7/11/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 7/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 7/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 7/11/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/31/2023 | Approved | THOMAS LOGRASSO |
| Final | 8/31/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 8/31/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 8/31/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 10/30/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 10/30/2024 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 10/30/2024 | Not Required | HAMIK HARTOUNIAN |
| Final | 11/6/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 11/7/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 11/12/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |