11008 W CASHMERE ST 90049

Certificate Information: 11008 W CASHMERE ST 90049

Application / Permit
20010-30000-04234
Plan Check / Job No.
B20WL04852
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DET. ADU IN REAR OF THE LOT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part 2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 1/13/2021
Issuing Office
Current Status
CofO Issued on 7/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2020 APPLICANT
Assigned to Plan Check Engineer 11/10/2020 REZA HAGHIGHAT
Corrections Issued 11/16/2020 REZA HAGHIGHAT
Quality Review Completed 11/25/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 1/13/2021 REZA HAGHIGHAT
Issued 1/13/2021 APPLICANT
Building Plans Picked Up 1/13/2021 APPLICANT
CofO in Progress 7/14/2023 CARLOS MATAMOROS
CofO in Progress 7/14/2023 CARLOS MATAMOROS
Permit Finaled 7/17/2023 DANIEL ORRANTE
CofO Issued 7/17/2023 DANIEL ORRANTE
Permit Finaled 7/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

Watercourse Cleared 11/19/2020 MAHELET GEBEYHU
Specific Plan Cleared 12/2/2020 FREDDY GARCIA
Address approval Cleared 12/3/2020 DINAH GARIN
ZA Case Cleared 12/3/2020 DENZEL HENDERSON
Low Impact Development Cleared 12/10/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/10/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/11/2020 DINAH GARIN
Sewer availability Cleared 12/11/2020 DINAH GARIN
Hydrant and Access approval Cleared 12/31/2020 JEREMY CARTER
GPI Written Notices Cleared 1/13/2021 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 1/13/2021 REZA HAGHIGHAT

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Bookie Development Inc; Lic. No.: 977585-B 10509 CLARKSON ROAD      LOS ANGELES, CA 90064
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/9/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 7/12/2021 Not Ready for Inspection CARLOS MATAMOROS
FLOOD-Elevation Certificate 7/16/2021 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 7/16/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 10/14/2021 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 11/15/2021 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/3/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 1/7/2022 Approved CARLOS MATAMOROS
Underground Mechanical 1/7/2022 Approved CARLOS MATAMOROS
HVAC-Rough 1/28/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 2/16/2022 Corrections Issued CARLOS MATAMOROS
FLOOD-Proofing Certificate 2/16/2022 Approved CARLOS MATAMOROS
Green Building Rough 2/16/2022 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 2/16/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 2/18/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 2/23/2022 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 3/11/2022 Not Ready for Inspection CARLOS MATAMOROS
Insulation 3/11/2022 Approved CARLOS MATAMOROS
Drywall Nailing 3/22/2022 Approved CARLOS MATAMOROS
Green Building Rough 3/22/2022 Approved CARLOS MATAMOROS
Shower Pan 5/3/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/17/2022 Approved CARLOS MATAMOROS
ELECTRICAL-Final 4/14/2023 Approved CARLOS MATAMOROS
HVAC-Final 5/1/2023 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 5/1/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 5/17/2023 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 5/22/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 5/22/2023 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 5/24/2023 Corrections Issued CARLOS MATAMOROS
Gas Test 5/26/2023 Approved CARLOS MATAMOROS
HVAC-Final 5/26/2023 Approved CARLOS MATAMOROS
PLUMBING-Final 5/26/2023 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 7/6/2023 Approved CARLOS MATAMOROS
Final 7/6/2023 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 7/6/2023 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 7/6/2023 SGSOV Approved CARLOS MATAMOROS
Service/Power Release 7/6/2023 Approved CARLOS MATAMOROS
Smoke Detectors 7/6/2023 Approved CARLOS MATAMOROS