341 S CLIFFWOOD AVE 90049

Certificate Information: 341 S CLIFFWOOD AVE 90049

Application / Permit
20010-30000-04143
Plan Check / Job No.
B20WL04829
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD WITH ATTACHED AGARAGE AND BASEMENT.
Permit Issued
Issued on 6/25/2021
Issuing Office
Current Status
CofO Issued on 6/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2020 APPLICANT
Assigned to Plan Check Engineer 11/10/2020 TARIK SAOUD
Corrections Issued 11/16/2020 TARIK SAOUD
Quality Review Completed 11/25/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 6/3/2021 TARIK SAOUD
Issued 6/25/2021 APPLICANT
Building Plans Picked Up 2/14/2022 APPLICANT
CofO in Progress 6/13/2023 OGANES TARAKHCHYAN
Permit Finaled 6/13/2023 DANIEL ORRANTE
CofO Issued 6/13/2023 DANIEL ORRANTE
Permit Finaled 6/13/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 12/23/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 12/24/2020 ANTHONY MAINEZ
Sewer availability Cleared 12/24/2020 ANTHONY MAINEZ
Trees in Parkway Cleared 1/11/2021 JOHN KIM
Specific Plan Cleared 1/20/2021 PEDRO AYALA
Frnt yard landscape/Water mgmt Cleared 3/16/2021 LOUIS ORTEGA
ZA Case Cleared 3/16/2021 LOUIS ORTEGA
Hydrant and Access approval Cleared 4/21/2021 JOHN CONNEALLY
Low Impact Development Cleared 5/25/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 5/25/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 6/3/2021 TARIK SAOUD
Excavation more than 5-ft deep Cleared 6/23/2021 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/9/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 8/20/2021 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/15/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 10/27/2021 Partial Approval JOHN KIDWELL
Underground Mechanical 10/27/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 11/10/2021 Corrections Issued JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/17/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 11/17/2021 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Approved JOHN KIDWELL
ELECTRICAL-Rough 1/27/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 1/27/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 1/27/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 1/28/2022 Approved JOHN KIDWELL
HVAC-Rough 1/28/2022 Corrections Issued JOHN KIDWELL
PLUMBING-Rough 2/2/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 2/8/2022 Approved JOHN KIDWELL
Green Building Rough 2/8/2022 Approved JOHN KIDWELL
HVAC-Rough 2/8/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 2/8/2022 Approved JOHN KIDWELL
Shower Pan 2/8/2022 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 2/8/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 2/15/2022 Approved JOHN KIDWELL
Insulation 2/22/2022 Approved JUAN VALENZUELA
Drywall Nailing 2/25/2022 Approved JUAN VALENZUELA
Gas Test 2/25/2022 Not Ready for Inspection JUAN VALENZUELA
Deputy Reinf. Concrete 5/31/2022 Partial Approval JOHN KIDWELL
Sewer 1/24/2023 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 1/24/2023 Partial Approval OGANES TARAKHCHYAN
Sewer 2/3/2023 Approved OGANES TARAKHCHYAN
HVAC-Final 4/24/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 4/24/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 5/23/2023 Approved JESUS RODRIGUEZ
Gas Test 5/23/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 5/23/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 5/23/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Approved JESUS RODRIGUEZ
Gas Test 5/24/2023 Approved JOHNNY MIRANDA
Final 5/25/2023 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 5/25/2023 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/25/2023 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 5/25/2023 Approved OGANES TARAKHCHYAN
Final 6/1/2023 Corrections Issued OGANES TARAKHCHYAN
Final 6/12/2023 OK to Issue CofO OGANES TARAKHCHYAN
Service/Power Release 6/12/2023 Approved OGANES TARAKHCHYAN